Daily Report

CPUC/ANF Environmental Monitoring Activities

Pacific Pipeline Construction Project

Aspen Environmental Group Tuesday, February 09, 1999
   

The following is a brief summary of the environmental monitoring activities that were completed between February 09, 1999 1:00 and 1:00 on February 10, 1999. This summary is based on reports directly received from the field and has not been edited. If you have any questions please contact (818) 597-3407. Please note the item number and the correction that should be made. This report is intended to serve as a communication document and as an instrument for quality control.

Construction Highlights

02/09/99 (Tuesday)

Segment 5 (Lynwood to Long Beach): Report for 2-9-99. Crews began excavation of the receiving bore pit at Lomita after crews pushed the final pipe section through the bore sleeve. However, due to rain crews halted digging and began shoring a weak section of the ditch at the southern end of the Huntway line. Meanwhile, minor electrical and valve packing work occurred within the Wilmington refinery. Crews at the Edision site south of the 91 Frwy welded lifting eyes onto the vault top while coating of above ground pipe continued at Lynwood station. In addition, crews installed a door to the control room area and placed concrete filled barriers near the station drive way.

Inspection Summar

In the past 24 hours, 1 inspection event(s) were reported for 1 spread(s). Of these inspections, 0 were non-compliance event(s). Also 0 non-compliance resolution report(s) was resolved.

Non-Compliance Reports (NCR's) Issued

No new non-compliance reports were issued during the last reporting period.

Non-Compliance Resolution Reports (NCRR's) Issued

No new non-compliance reports were issued during the last reporting period.

Summary of Follow-up Items for Today

No follow-up items were reported for today.