Daily Report

CPUC/ANF Environmental Monitoring Activities

Pacific Pipeline Construction Project

Aspen Environmental Group Wednesday, February 17, 1999
   

The following is a brief summary of the environmental monitoring activities that were completed between February 17, 1999 1:00 and 1:00 on February 18, 1999. This summary is based on reports directly received from the field and has not been edited. If you have any questions please contact (818) 597-3407. Please note the item number and the correction that should be made. This report is intended to serve as a communication document and as an instrument for quality control.

Construction Highlights

02/17/99 (Wednesday)

Segment 5 (Lynwood to Long Beach): Report for 2-17-99. Work progressed with the tie-in from the Wilmington refinery to the Huntway bore pit. Crews welded, x-rayed and wrapped pipe anticipating completion of welding on Thursday. In addition, crews installed two fire hydrants and continued paint work within the Wilmington refinery. Meanwhile, trenching crews completed 60' of ditch along the Huntway section while pipe was coated and electricians progressed with laying fiber optic conduit. Further, 80' of pipe was shaded along the southern section. Crews working at the Edison site, poured concrete for the vault end caps and began work in preparation of setting the vault box top.

Inspection Summar

In the past 24 hours, 1 inspection event(s) were reported for 1 spread(s). Of these inspections, 0 were non-compliance event(s). Also 0 non-compliance resolution report(s) was resolved.

Non-Compliance Reports (NCR's) Issued

No new non-compliance reports were issued during the last reporting period.

Non-Compliance Resolution Reports (NCRR's) Issued

No new non-compliance reports were issued during the last reporting period.

Summary of Follow-up Items for Today

No follow-up items were reported for today.