Daily Report

CPUC/ANF Environmental Monitoring Activities

Pacific Pipeline Construction Project

Aspen Environmental Group Thursday, February 18, 1999
   

The following is a brief summary of the environmental monitoring activities that were completed between February 18, 1999 1:00 and 1:00 on February 19, 1999. This summary is based on reports directly received from the field and has not been edited. If you have any questions please contact (818) 597-3407. Please note the item number and the correction that should be made. This report is intended to serve as a communication document and as an instrument for quality control.

Construction Highlights

02/18/99 (Thursday)

Segment 5 (Lynwood to Long Beach): Report for 2-18-99. Welders completed the tie-in on the 16'' line then crews worked backfilling the bore pit within the Wilmington refinery. Meanwhile, crews completed 40' of backfill then moved several drums from the right of way on the Huntway section. A large crane is being utilized to remove the shoring boxes from the Edison bore pit. In addition, crews placed a ring seal around the pipe and began backfilling the bore pit.

Inspection Summar

In the past 24 hours, 1 inspection event(s) were reported for 1 spread(s). Of these inspections, 0 were non-compliance event(s). Also 0 non-compliance resolution report(s) was resolved.

Non-Compliance Reports (NCR's) Issued

No new non-compliance reports were issued during the last reporting period.

Non-Compliance Resolution Reports (NCRR's) Issued

No new non-compliance reports were issued during the last reporting period.

Summary of Follow-up Items for Today

No follow-up items were reported for today.