CPUC/ANF Environmental Monitoring Activities Pacific Pipeline Construction Project |
Aspen Environmental Group | Tuesday, February 23, 1999 |
The following is a brief summary of the environmental monitoring activities that were completed between February 23, 1999 1:00 and 1:00 on February 24, 1999. This summary is based on reports directly received from the field and has not been edited. If you have any questions please contact (818) 597-3407. Please note the item number and the correction that should be made. This report is intended to serve as a communication document and as an instrument for quality control.
Construction Highlights
02/23/99 (Tuesday)Segment 5 (Lynwood to Long Beach): Report for 2-23-99. Backfill of the bore pit progressed while crews conducted a general clean up of the job site for the Edison location. Meanwhile, crews backfilled, shaded pipe and completed several sections of fiber optic duct along the Huntway section. In addition, crews fabricated several tube turns, set and welded one joint and excavated a short section of trench. Within the Wilmington refinery, crews continued painting and backfilling the bore pit.
Inspection Summar
In the past 24 hours, 1 inspection event(s) were reported for 1 spread(s). Of these inspections, 0 were non-compliance event(s). Also 0 non-compliance resolution report(s) was resolved.
Non-Compliance Reports (NCR's) Issued
No new non-compliance reports were issued during the last reporting period.
Non-Compliance Resolution Reports (NCRR's) Issued
No new non-compliance reports were issued during the last reporting period.
Summary of Follow-up Items for Today
No follow-up items were reported for today.