CPUC/ANF Environmental Monitoring Activities Pacific Pipeline Construction Project |
Aspen Environmental Group | Thursday, February 25, 1999 |
The following is a brief summary of the environmental monitoring activities that were completed between February 25, 1999 1:00 and 1:00 on February 26, 1999. This summary is based on reports directly received from the field and has not been edited. If you have any questions please contact (818) 597-3407. Please note the item number and the correction that should be made. This report is intended to serve as a communication document and as an instrument for quality control.
Construction Highlights
02/25/99 (Thursday)Segment 5 (Lynwood to Long Beach): Report for 2-25-99. Backfilling of the bore pit and general clean up occurred at the Edison site. Meanwhile, crews trenched 60', shaded 100', set one joint in the ditch and completed 180' of fiber optic duct along the Huntway section. In addition, crews worked painting and backfilling within the Wilmington refinery.
Inspection Summar
In the past 24 hours, 1 inspection event(s) were reported for 1 spread(s). Of these inspections, 0 were non-compliance event(s). Also 0 non-compliance resolution report(s) was resolved.
Non-Compliance Reports (NCR's) Issued
No new non-compliance reports were issued during the last reporting period.
Non-Compliance Resolution Reports (NCRR's) Issued
No new non-compliance reports were issued during the last reporting period.
Summary of Follow-up Items for Today
No follow-up items were reported for today.