Daily Report

CPUC/ANF Environmental Monitoring Activities

Pacific Pipeline Construction Project

Aspen Environmental Group Monday, March 01, 1999
   

The following is a brief summary of the environmental monitoring activities that were completed between March  01, 1999 1:00 and 1:00 on March 02, 1999. This summary is based on reports directly received from the field and has not been edited. If you have any questions please contact (818) 597-3407. Please note the item number and the correction that should be made. This report is intended to serve as a communication document and as an instrument for quality control.

Construction Highlights

03/01/99 (Monday)

Segment 5 (Lynwood to Long Beach) Report for 3-1-99. Edison site was cleaned and roadway prepared for concrete pour that will occur later in week . Crews at Huntway completed one weld and shaded and backfilled pipe south of Lomita Street. Trenching continued adjacent to existing GATX lines north of Lomita Street.

Inspection Summar

In the past 24 hours, 1 inspection event(s) were reported for 1 spread(s). Of these inspections, 0 were non-compliance event(s). Also 0 non-compliance resolution report(s) was resolved.

Non-Compliance Reports (NCR's) Issued

No new non-compliance reports were issued during the last reporting period.

Non-Compliance Resolution Reports (NCRR's) Issued

No new non-compliance reports were issued during the last reporting period.

Summary of Follow-up Items for Today

No follow-up items were reported for today.