Daily Report

CPUC/ANF Environmental Monitoring Activities

Pacific Pipeline Construction Project

Aspen Environmental Group Tuesday, March 02, 1999
   

The following is a brief summary of the environmental monitoring activities that were completed between March 2, 1999 1:00 and 1:00 on March 3, 1999. This summary is based on reports directly received from the field and has not been edited. If you have any questions please contact (818) 597-3407. Please note the item number and the correction that should be made. This report is intended to serve as a communication document and as an instrument for quality control.

Construction Highlights

03/02/99 (Tuesday)

Segment 5 (Lynwood to Long Beach): Report for 3-2-99. Crews poured slurry across Alameda St and conducted a general clean up at the Edison station site. Vandals flipped over a water truck and damaged several other vehicles along the Huntway connection although crews were able to conduct work throughout the day. In addition, 60' of trench and backfill were completed today while welders fitted a tube turn onto a section of pipe. Further, a large spoil pile was moved to allow a clear path for traffic flow on Lomita Blvd. Finally, crews continued coating and painting of above ground pipe within the Wilmington refinery.

Inspection Summar

In the past 24 hours, 1 inspection event(s) were reported for 1 spread(s). Of these inspections, 0 were non-compliance event(s). Also 0 non-compliance resolution report(s) was resolved.

Non-Compliance Reports (NCR's) Issued

No new non-compliance reports were issued during the last reporting period.

Non-Compliance Resolution Reports (NCRR's) Issued

No new non-compliance reports were issued during the last reporting period.

Summary of Follow-up Items for Today

No follow-up items were reported for today.

Back to Daily Reports

Back to MMCRP Home Page