CPUC/ANF Environmental Monitoring Activities Pacific Pipeline Construction Project |
Aspen Environmental Group | Wednesday, March 03, 1999 |
The following is a brief summary of the environmental monitoring activities that were completed between March 3, 1999 1:00 and 1:00 on March 4, 1999. This summary is based on reports directly received from the field and has not been edited. If you have any questions please contact (818) 597-3407. Please note the item number and the correction that should be made. This report is intended to serve as a communication document and as an instrument for quality control.
Construction Highlights
03/03/99 (Wednesday)Segment 5 (Lynwood to Long Beach): Report for 3-2-99. Trenching for the Huntway connection neared completion today with crews working across Lomita Blvd. In addition, welders fabricated a section of pipe while 40' of backfill was completed. Meanwhile, final painting progressed within the Wilmington refinery.
Inspection Summar
In the past 24 hours, 1 inspection event(s) were reported for 1 spread(s). Of these inspections, 0 were non-compliance event(s). Also 0 non-compliance resolution report(s) was resolved.
Non-Compliance Reports (NCR's) Issued
No new non-compliance reports were issued during the last reporting period.
Non-Compliance Resolution Reports (NCRR's) Issued
No new non-compliance reports were issued during the last reporting period.
Summary of Follow-up Items for Today
No follow-up items were reported for today.