Daily Report

CPUC/ANF Environmental Monitoring Activities

Pacific Pipeline Construction Project

Aspen Environmental Group Saturday, December 05, 1998
   

The following is a brief summary of the environmental monitoring activities that were completed on December 05, 1998. This summary is based on reports directly received from the field and has not been edited. If you have any questions please contact (818) 597-3407. Please note the item number and the correction that should be made. This report is intended to serve as a communication document and as an instrument for quality control.

Construction Highlights

12/05/98 (Saturday)

Segment 1 report for 12/5/98: On Tejon Bench, the coating crew worked at EMP 16.55. On Grapevine Rd. welding, x-ray and coating occurred from 15.73 to 15.68. Electrical work continued at Grapevine Pump Station. At Emidio Pump Station, work on the office interior continued.

Inspection Summary

In the past 24 hours, 1 inspection event(s) were reported for 1 spread(s). Of these inspections, 0 were non-compliance event(s). Also 0 non-compliance resolution report(s) was resolved.

Non-Compliance Reports (NCR's) Issued

No new non-compliance reports were issued during the last reporting period.

Non-Compliance Resolution Reports (NCRR's) Issued

No new non-compliance reports were issued during the last reporting period.

Summary of Follow-up Items for Today

No follow-up items were reported for today.

Back to Daily Reports

Back to MMCRP Home Page