CPUC/ANF Environmental Monitoring Activities

Pacific Pipeline Construction Project

Aspen Environmental Group Friday, December 18, 1998
   

The following is a brief summary of the environmental monitoring activities that were completed on December 18, 1998. This summary is based on reports directly received from the field and has not been edited. If you have any questions please contact (818) 597-3407. Please note the item number and the correction that should be made. This report is intended to serve as a communication document and as an instrument for quality control.

Construction Highlights

12/18/98 (Friday)

Segment 1 report for 12/18/98: No work was done at Emidio and Grapevine Pump Stations. At the Stream Crossing #4 bore (EMP 9.03) tie-in of the bore to the mainline was completed and backfill was in progress. The segment of pipe to tie-into the Tecuya Creek/I-5 bore was being welded, x-rayed and coated from EMP 9.86 to 9.78. The pipe is being pushed through the California Aqueduct bore (EMP 12.28). Casing is being installed at both the Stream Crossing #9 (EMP 15.35) and the Tejon Bench/I-5 (EMP 16.49) bores. On Grapevine Rd., shading, compaction and conduit occurred to EMP 15.55. Backfill progress in this area and Tejon Bench is slow due to the abundance of rock present in the excavated soil. The soil has to be run through a sifter to separate it from the rock, then trucked back to the trench for shading and backfill. On Tejon Bench, shading is in progress from EMP 16.87 to 16.57. Trench occurred to EMP 17.98. Pipe has been welded, x-rayed and coated to EMP 18.00. On Lebec Rd., excavation of the trench continued working south to EMP 21.67. Pipe was welded, x-rayed and coated to EMP 21.64.

Inspection Summar

In the past 24 hours, 3 inspection event(s) were reported for 3 spread(s). Of these inspections, 0 were non-compliance event(s). Also 0 non-compliance resolution report(s) was resolved.

Non-Compliance Reports (NCR's) Issued

No new non-compliance reports were issued during the last reporting period.

Non-Compliance Resolution Reports (NCRR's) Issued

No new non-compliance reports were issued during the last reporting period.

Summary of Follow-up Items for Today

No follow-up items were reported for today.