Daily Report

CPUC/ANF Environmental Monitoring Activities

Pacific Pipeline Construction Project

Aspen Environmental Group Thursday, December 31, 1998
   

The following is a brief summary of the environmental monitoring activities that were completed on December 31, 1998. This summary is based on reports directly received from the field and has not been edited. If you have any questions please contact (818) 597-3407. Please note the item number and the correction that should be made. This report is intended to serve as a communication document and as an instrument for quality control.

Construction Highlights

12/31/98 (Thursday)

Segment 1 (Emidio Pump Station to Copco Road): Report for 31 December 1998: Backfill began near an entrance to the Flying J, just north of Cuddy Creek, today; most backfill was complete, and some temporary asphalt was placed. The crew at the Warbler Skip along Lebec Road completed their tie in, while FOC crews struggled with the water-laden area to place conduit. Some initial paving was done on the north end of this work. Work on Tejon Bench consisted of the string of pipe for the Tejon Ranch water line, as well as lowering in of carrier pipe on the remaining ~140 feet of ditch. Crews at the I-5/Tejon Bench bore began pushing pipe through the casing. Backfill crews worked on upper Grapevine Road to prepare for paving. An excavator continued to work on the south side of Grapevine Creek, digging out a ditch line for the bore tie in. Continuing work occurred at Grapvine and Emidio Pump Stations. Minor backfill occurred on the south side of the aqueduct crossing. Spoil was being moved around at the frontage road, as well as slurry being poured around the valve area. Fiber optic crews finished pulling cable under I-5 at this location.

Inspection Summar

In the past 24 hours, 1 inspection event(s) were reported for 1 spread(s). Of these inspections, 0 were non-compliance event(s). Also 0 non-compliance resolution report(s) was resolved.

Non-Compliance Reports (NCR's) Issued

No new non-compliance reports were issued during the last reporting period.

Non-Compliance Resolution Reports (NCRR's) Issued

No new non-compliance reports were issued during the last reporting period.

Summary of Follow-up Items for Today

No follow-up items were reported for today.

Back to Daily Reports

Back to MMCRP Home Page