July 1, 1997
    - Dean Shauers, Project Manager
 
    - Pacific Pipeline System, Inc.
 
    - 12201 E. Arapahoe Road, C10
 
    - Englewood, CO 80112
 
RE: Variance Request #88 - Relocation of 2457
feet of fiber optic conduit from the east side to the west side
of the Metropolitan Transportation Authority (MTA) right-of-way
between the Burbank Dog Pound exit location (station number
4646+96) and West Olive Avenue (station number 4671+53), Segment
3, City of Burbank.
Dear Mr. Shauers:
We have reviewed the above-referenced variance
request and approve your request, based on the following factor: 
    - The pipeline was installed in this area
        using a directional drill; therefore, the fiber optic
        conduit was not installed at that time. 
 
    - At the request of MTA, the relocation of
        the fiber optic conduit to approximately 75 feet west of
        the PPSI right-of-way has been requested to accommodate
        MTA and City of Burbank construction activities. On
        January 23, 1998, at the request of MTA, PPSI installed
        822 feet of the fiber optic conduit between Magnolia
        Boulevard and West Olive Avenue since a ditch had already
        been excavated by MTA for the installation of their own
        fiber optic conduit in this area. 
 
    - Installation of the remaining fiber optic
        conduit would require an 18-inch wide, 4-foot deep
        trench. The conduit would also be bored under the MTA
        tracks at two locations. The subject portion of the MTA
        right-of-way is currently under going major construction,
        including building demolition and the construction of a
        new roadway. By installing the PPSI fiber optic conduit
        approximately 75 feet west of the originally proposed
        location, no additional impacts would result due to the
        current construction in the area. 
 
    - The following measures shall be
        implemented.
 
    - All applicable mitigation measures for
    the project shall be implemented at the subject location. 
    - Prior to fiber optic conduit
    installation, PPSI and its contractor shall coordinate with
    MTA and the City of Burbank on the appropriate timing for
    conduit installation and railway safety. 
    - Fiber optic conduit installation at the
    subject location shall completed within 15 working days.
    - Implementation of this variance in
    accordance with the provisions noted above shall be verified
    on a random basis by a CPUC/ANF Environmental Monitor.
Sincerely,

    - Andrew Barnsdale
 
    - Project Manager
 