Daily Report

wpe7.gif (6380 bytes)

CPUC Environmental Monitoring Activities

SFPP Carson to Norwalk Project

Aspen Environmental Group Saturday, May 1, 1999

The following is a brief summary of the environmental monitoring activities that were completed between 1:00 on 05/01/99 and 1:00 on 05/02/99. This summary is based on reports directly received from the field and has not been edited. If you have any questions please contact (818) 597-3407. This report is intended to serve as a communication document and as an instrument for quality control.


Construction Highlights

Spread 1

City of Long Beach

Spread 1 work in the City of Long Beach has been completed.

City of Paramount

No Spread 1 work occurred in the City of Paramount during the shift.

City of Bellflower

No work occurred in the City of Bellflower during the shift.

City of Cerritos

The crew at the San Gabriel River bore cut off sections of the original lead joint of the 30-inch casing pipe that has broken off and is blocking the alignment. The crew cut off the last joint of casing pipe and pulled the augers back to cut the old section of pipe. Much of the shift was spent removing the obstruction from the path of the casing pipe and returning the augers to the inside of the casing pipe. Approximately 260 feet of casing pipe has been pushed through the bore.

City of Artesia

No work occurred in the City of Artesia during the shift.

City of Norwalk

No work occurred in the City of Norwalk during the shift.

Spread 2

Los Angeles County

No work occurred in Los Angeles County during the shift.

City of Long Beach

The crew at the Los Angeles River worked until 5:00 PM to complete welding and pushing the casing pipe through to DeForest Park. The contractor was notified that fugitive dust was an issue at both the Los Angeles River and at the San Gabriel River. A water truck was brought from the yard to water the access roads being used during the shift.

City of Paramount

No work occurred in the City of Paramount during the shift.

Watson Station

City of Carson

No work occurred at the Watson Station during the shift.

Industry Station

City of Walnut

The crew at the Industry Station continued laying and welding pipe between the two railroad bores towards the proposed pump and engine locations.

End of Report