Daily Report

wpe7.gif (6380 bytes)

CPUC Environmental Monitoring Activities

SFPP Carson to Norwalk Project

Aspen Environmental Group Tuesday, May 11, 1999

The following is a brief summary of the environmental monitoring activities that were completed between 1:00 on 5/11/99 and 1:00 on 5/12/99. This summary is based on reports directly received from the field and has not been edited. If you have any questions please contact (818) 597-3407. This report is intended to serve as a communication document and as an instrument for quality control.


Construction Highlights

Spread 1

City of Long Beach

Spread 1 work in the City of Long Beach has been completed.

City of Paramount

No Spread 1 work occurred in the City of Paramount during the shift.

City of Bellflower

The crew on the west side of the San Gabriel River backfilled around the pipe and left the upper part of the trench open for the electrical conduit. The applicant was informed that Palo Verde Avenue needs to be cleaned by the end of the shift.

City of Cerritos

The crew at the San Gabriel River cleaned up the right-of-way and cleaned out the Baker tank. The crew backfilled and compacted the trench, leaving the top half open for the electrical conduit. A small crew prepared to pour the slab for the valve on the east side of the river.

City of Artesia

No work occurred in the City of Artesia during the shift.

City of Norwalk

No work occurred in the City of Norwalk during the shift.

Spread 2

Los Angeles County

The crew at the Compton Creek Bridge poured both zero-sack and two-sack slurry on the south side of the bridge during the shift. The pipe over the bridge received a second coat of paint. The backfilling crew continued pouring the concrete road surface on Santa Fe Avenue south of Compton Creek.

City of Long Beach

The crew at the Los Angeles River continued working on backfilling over the section of pipe between the 710 Freeway bore and the Los Angeles River bore and the bore pit. A small crew worked in DeForest Park backfilling the trench with native material. The crew removed the large rocks from the spoil.

City of Paramount

No work occurred in the City of Paramount during the shift.

Watson Station

City of Carson

The crew at the Watson Station worked on the faulty welds on the prover. The section of 16-inch pipe at the start of Spread 2 was not welded during the shift.

Norwalk Station

City of Norwalk

The welding crew continued to weld on the test-heads for the hydrostatic test at the Norwalk Station.

End of Report