             Welcome to the California Public Utilities Commission (CPUC) website 
              for the California Environmental Quality Act (CEQA) review of the 
              proposed Sunrise Powerlink Transmission Line Project. Applications 
              for this project were submitted to the CPUC on December 14, 
              2005 (A.05-12-014) and August 4, 2006 (A.06-08-010). The Proponent's 
              Environmental Assessment was filed with the CPUC on August 4, 
              2006 and is available on SDG&E's 
              project website. This project was approved by the California 
              Independent System Operator on August 3, 2006. This site provides 
              access to public documents and information relevant to the CEQA 
              and National Environmental Policy Act (NEPA) review processes. The 
              CPUC voted on December 18, 2008 to approve the Final Environmentally 
              Superior Southern Route (see Decision D.08-12-058) 
              and a Notice of Determination was 
              submitted to the State Clearinghouse. The BLM issued a Record 
              of Decision approving the same route on January 20, 2009. 
             Construction Progress and Mitigation 
              Monitoring 
             Construction is scheduled to begin in March 2010, with the majority 
              of construction expected to start in June 2010 once the CPUC issues 
              Notices to Proceed for each segment. Issuance of Notices to Proceed 
              will be contingent upon SDG&E compliance with pre-construction 
              requirements as specified by the approved mitigation measures. SDG&E 
              is constructing the Sunrise Powerlink Project in 25 segments, as 
              follows: 
               
             
               
                | Segment | 
                Description | 
                Type | 
                Status | 
               
               
                | Segment 1 | 
                Imperial Valley Substation | 
                Substation Upgrades | 
                Not started | 
               
               
                | Segment 2 | 
                Imperial Valley Substation to Pyramid Mining 
                  (MP0 to MP19.2)  | 
                500 kV Overhead | 
                Not started | 
               
               
                | Segment 3 | 
                Pyramid Mining to Mountain Springs Grade (MP19.2 
                  to MP23.2)  | 
                500 kV Overhead | 
                Not started | 
               
               
                | Segment 4 | 
                Mountain Springs Grade to Jade (MP23.2 to 
                  MP30.3)  | 
                500 kV Overhead | 
                Not started | 
               
               
                | Segment 5 | 
                Jade to I-8 (McCain Valley) (MP30.3 to MP39.7) 
                   | 
                500 kV Overhead | 
                Not started | 
               
               
                | Segment 6 | 
                I-8 (McCain Valley) to USFS (MP39.7 to MP52.5) 
                   | 
                500 kV Overhead | 
                Not started | 
               
               
                | Segment 7 | 
                USFS East (MP52.5 to MP61.3)  | 
                500 kV Overhead | 
                Not started | 
               
               
                | Segment 8 | 
                USFS East to Cameron Substation (MP61.3 to 
                  MP65.4)  | 
                500 kV Overhead | 
                Not started | 
               
               
                | Segment 9 | 
                MP65.4 to MP70.9 | 
                500 kV Overhead | 
                Not started | 
               
               
                | Segment 10 | 
                MP70.9 to MP74.8 | 
                500 kV Overhead | 
                Not started | 
               
               
                | Segment 11 | 
                MP74.8 to MP77.6 | 
                500 kV Overhead | 
                Not started | 
               
               
                | Segment 12 | 
                MP77.6 to MP90.0 | 
                500 kV Overhead | 
                Not started | 
               
               
                | Segment 13 | 
                Suncrest Substation (Modified Route D Substation) | 
                New 500/230 kV Substation | 
                Not started | 
               
               
                | Segment 14 | 
                Suncrest Substation to Alpine Boulevard (MP90.0 
                  to MP92.8)  | 
                230 kV Overhead | 
                Not started | 
               
               
                | Segment 15 | 
                Alpine Boulevard Underground (MP92.8 to MP99.0) 
                   | 
                230 kV Underground | 
                Not started | 
               
               
                | Segment 16 | 
                Peutz Valley to El Monte Valley (MP99.0 to 
                  MP105.5)  | 
                230 kV Overhead | 
                Not started | 
               
               
                | Segment 17 | 
                El Monte Valley to Highway 67 (MP105.5 to 
                  MP112.7)  | 
                230 kV Overhead | 
                Not started | 
               
               
                | Segment 18 | 
                Highway 67 to Sycamore Canyon Substation (MP112.7 
                  to MP118.1)   | 
                230 kV Overhead | 
                Not started | 
               
               
                | Segment 19 | 
                Sycamore Canyon Substation | 
                Substation Upgrades 
                 | Not started
               |  
               
                | Segment 20 | 
                Sycamore to Elliot 69 kV Reconductor | 
                69 kV Reconductoring | 
                Not started | 
               
               
                | Segment 21 | 
                Sycamore to Scripps 69 kV Reconductor | 
                69 kV Reconductoring | 
                Not started | 
               
               
                | Segment 22 | 
                Sycamore to Pomerado 69 kV Reconductor | 
                69 kV Reconductoring | 
                Not started | 
               
               
                | Segment 23 | 
                South Bay Substation Upgrades | 
                Substation Upgrades | 
                Not started | 
               
               
                | Segment 24 | 
                Encina Substation Upgrades | 
                Substation Upgrades | 
                Not started | 
               
               
                | Segment 25 | 
                San Luis Rey Substation Upgrades | 
                Substation Upgrades | 
                Not started | 
               
             
            The CPUC in conjunction with SDG&E, BLM, USFS and other Responsible 
              Agencies, drafted a Mitigation Monitoring Compliance and Reporting 
              Program (MMCRP) to ensure compliance with mitigation measures approved 
              in the Final EIR/EIS, as well as with the terms and conditions associated 
              with the BLM Right of Way. Although changes may be made to the document 
              as construction progresses, a current final version of the MMCRP 
              document and attachments, including a map 
              of the approved route with segments, is found here. 
             A CPUC Environmental Monitor will be monitoring construction activities 
              to ensure that they are conducted in accordance with the approved 
              mitigation measures and permit conditions. Once construction begins, 
              this site will hold all weekly reports documenting this monitoring 
              activity. Reports on construction status and activities are posted 
              here. Other monitoring compliance reports, 
              permit applications, and documents are available in their final 
              form here. 
             
            Final EIR/EIS 
            The Final EIR/EIS was released to the public on October 13, 
              2008. The Final EIR/EIS is available here 
              and is also available at numerous area libraries 
              and government offices. Copies of the Executive Summary of the 
              Final EIR/EIS along with a DVD of the complete document may be requested. 
              The CPUC and BLM also have a limited number of copies of the complete 
              four-volume Final EIR/EIS document available to the public. Requests 
              for documents should be made to (866) 711-3106 (phone or fax) or 
              via email to sunrise@aspeneg.com. 
            The Notice of Availability provides 
              further information on the approval processes for the CPUC and the 
              BLM. Pursuant to NEPA requirements, the Final EIR/EIS and Proposed 
              Land Use Plan Amendment will be available for review for 30 calendar 
              days from the date the Environmental Protection Agency (EPA) publishes 
              the Notice of Availability (NOA) in the Federal Register, which 
              is expected to occur on October 17, 2008. The review period 
              would end on November 15, 2008. 
             
            Copies of the Executive Summary of the Final EIR/EIS along with 
              a DVD of the complete document may be requested. The CPUC and BLM 
              also have a limited number of copies of the complete four-volume 
              Final EIR/EIS document available to the public. Requests for documents 
              should be made to (866) 711-3106 (phone or fax) or via email to 
              sunrise@aspeneg.com. 
            Draft EIR/EIS 
            The CPUC and BLM published the Draft EIR/EIS in January 2008. Please 
              note that the Final EIR/EIS (described above) includes the entire 
              text of the Draft EIR/EIS, modified where necessary in response 
              to comments on the Draft EIR/EIS. The original text of the Draft 
              EIR/EIS document is available here. 
            EIR/EIS Alternatives 
            Throughout 2007, the CPUC and BLM gathered information on alternatives 
              to the proposed Sunrise Powerlink Project through an extensive public 
              involvement process. Information and documents from that process 
              are available here. 
            Documents Available 
            In addition to the EIR/EIS, other documents that were published 
              during the CEQA and NEPA processes are available here. 
              Documents and letters that were compiled following publication of 
              the Final EIR/EIS, such as SDG&E Biological Assessment, USFWS 
              Biological Opinion, BLM Section 106 Programmatic Agreement, and 
              appeals to the BLM Interior Board of Land Appeals, are also included. 
             
            In response to concerns from the Lakeside community, a fact sheet 
              that summarizes past public notification and consideration of alternative 
              routes in the community of Lakeside is available here 
              (posted February 24, 2009). A similar fact sheet on public 
              notification was prepared for the Town of Alpine in January 2010 
              and is available here. 
            
            Data Requests 
            The EIR/EIS Team submits Data Requests to SDG&E and other entities 
              when it needs specific information to support EIR/EIS preparation. 
              These requests are available here at 
              the time they are issued. 
            Requests for Technical Information 
              Related to the Draft EIR/EIS 
            During the 90-day public comment period on the Draft EIR/EIS, various 
              parties submitted requests for technical information related to 
              that document. The information provided has available here. 
             
            For Additional Information 
            To request additional information or to be added to the mailing 
              list, please contact us by email, fax, or phone, as follows: 
            
            The CPUC's Project Manager is: 
            Billie Blanchard, CPUC Project Manager 
              California Public Utilities Commission 
              505 Van Ness Avenue 
              San Francisco CA 94102 
              Tel. (415) 703-2068 
              Fax (415) 703-2200 
              Email:  bcb@cpuc.ca.gov
             
           |