             Welcome to the California Public Utilities Commission (CPUC) website 
              for the California Environmental Quality Act (CEQA) review of the 
              proposed Sunrise Powerlink Transmission Line Project. Applications 
              for this project were submitted to CPUC on December 14, 2005 
              (A.05-12-014) and August 4, 2006 (A.06-08-010). The Proponent's 
              Environmental Assessment was filed with the CPUC on August 4, 
              2006 and is available on SDG&E's 
              project website. This project was approved by the California 
              Independent System Operator on August 3, 2006. This site provides 
              access to public documents and information relevant to the CEQA 
              and National Environmental Policy Act (NEPA) review processes. The 
              CPUC voted on December 18, 2008 to approve the Final Environmentally 
              Superior Southern Route (see Decision D.08-12-058) 
              and a Notice of Determination was 
              submitted to the State Clearinghouse. The Bureau of Land Management 
              (BLM) issued a Record of Decision approving 
              the same route on January 20, 2009.
              
               JUMP TO: 
                Contact Information During 
                Construction 
                Construction Progress and Mitigation Monitoring 
                 
                Notices to Proceed 
                CPUC Variance Approvals 
                USFS Variance Approvals 
                Determinations of NEPA Adequacy 
                Helicopter Operations and FAA Compliance 
                Project Modifications Report  
                Final EIR/EIS 
                Draft EIR/EIS 
                EIR/EIS Alternatives 
                Documents Available 
                Data Requests 
                Requests for Technical Information Related to 
                the Draft EIR/EIS 
                For Additional Information 
             
             
               
            
  
             
               
                 
                  Contact 
                    Information During Construction 
                 | 
               
               
                |  
                  
                 | 
               
             
            Construction 
              Progress and Mitigation Monitoring 
             Construction of the Sunrise Powerlink Project began in September 
              2010 with the establishment of some construction yards and existing 
              substation upgrades. Notices to Proceed (NTPs) have been issued 
              by the CPUC for each of these activities. The majority of construction 
              is expected to start in November/December 2010 once the CPUC and 
              each applicable agency (BLM and/or USFS) issues NTPs for each segment. 
              Issuance of NTPs will be contingent upon SDG&E compliance with 
              pre-construction requirements as specified by the approved mitigation 
              measures and responsible agency permitting requirements. Approved 
              pre-compliance reports, permit applications, and other documents 
              are available in their final form here. 
              NTPs that have been issued to SDG&E are noted in the table below. 
             SDG&E is constructing the Sunrise Powerlink Project in 25 transmission 
              segments and with several additional work areas and separate substations, 
              as follows: 
               
             
               
                |  
                  
                 | 
               
               
                |  
                   Segment 
                 | 
                 
                   Description 
                 | 
                 
                   Jurisdiction 
                 | 
                 
                   Type 
                 | 
                 
                   NTP Request Submitted 
                 | 
                 
                   NTP Issued 
                 | 
                 
                   Construction Authorized² 
                 | 
               
               
                | Segment 1 | 
                Imperial Valley Substation | 
                BLM | 
                Substation Upgrades | 
                BLM request submitted 01/19/11 | 
                BLM NTP #1 issued 02/3/11 
                 | 
                 
                   02/04/11 
                 | 
               
               
                | Segment 2 | 
                Imperial Valley Substation to Pyramid Mining (MP0 
                  to MP19.2) | 
                CPUC 
                  BLM | 
                500 kV Overhead | 
                 
                   CPUC request submitted 11/09/10 
                    for non-federal lands only; 3/28/11; BLM request submitted 
                    03/25/11 
                 | 
                CPUC NTP #13 issued 01/13/11 
                  for non-federal lands only; modified 02/24/11; 
                  BLM NTP #2 issued 04/04/11 (19.9MB) | 
                 
                   01/20/11 
                 | 
               
               
                | Segment 3 | 
                Pyramid Mining to Mountain Springs Grade (MP19.2 
                  to MP23.2) | 
                CPUC 
                  BLM | 
                500 kV Overhead | 
                 
                   CPUC request submitted 11/09/10 
                    for non-federal lands only; BLM request submitted 03/25/11 
                 | 
                CPUC NTP #13 issued 01/13/11 
                  for non-federal lands only; modified 02/24/11; 
                  BLM NTP #2 issued 04/04/11 (19.9MB) | 
                 
                   01/20/11 
                 | 
               
               
                | Segment 4 | 
                Mountain Springs Grade to Jade (MP23.2 to MP30.3) | 
                CPUC 
                  BLM | 
                500 kV Overhead | 
                 
                   CPUC request submitted 11/09/10 
                    for non-federal lands only; BLM request submitted 03/25/11 
                 | 
                CPUC NTP #13 issued 01/13/11 
                  for non-federal lands only; modified 02/24/11; 
                  BLM NTP #2 issued 04/04/11 (19.9MB) | 
                 
                   01/20/11 
                 | 
               
               
                | Segment 5 | 
                Jade to I-8 (McCain Valley) (MP30.3 to MP39.7) | 
                CPUC 
                  BLM | 
                500 kV Overhead | 
                 
                   CPUC request submitted 11/09/10 
                    for non-federal lands only; BLM request submitted 03/25/11 
                 | 
                CPUC NTP #13 issued 01/13/11 
                  for non-federal lands only; modified 02/24/11; 
                  BLM NTP #2 issued 04/04/11 (19.9MB) | 
                 
                   01/20/11 
                 | 
               
               
                | Segment 6 | 
                I-8 (McCain Valley) to USFS (MP39.7 to MP52.5) | 
                CPUC 
                  BLM 
                  USFS | 
                500 kV Overhead | 
                 
                   CPUC request submitted 11/09/10 
                    for non-federal lands only; BLM request submitted 03/25/11; 
                    USFS request submitted 07/29/11 
                   
                 | 
                CPUC NTP #13 issued 01/13/11 
                  for non-federal lands only; modified 02/24/11; 
                  BLM NTP #2 issued 04/04/11 (19.9MB); 
                  USFS NTP #1 issued 08/09/11 | 
                 
                   01/20/11 
                 | 
               
               
                | Segment 7 | 
                USFS East (MP52.5 to MP61.3) | 
                CPUC 
                  BLM 
                  USFS | 
                500 kV Overhead | 
                 
                   CPUC request submitted 11/09/10 
                    for non-federal lands only; BLM request submitted 03/25/11; 
                    USFS request submitted 07/29/11 
                   
                 | 
                CPUC NTP #13 issued 01/13/11 
                  for non-federal lands only; modified 02/24/11; 
                  BLM NTP #2 issued 04/04/11 (19.9MB); 
                  USFS NTP #1 issued 08/09/11 | 
                 
                   01/20/11 
                 | 
               
               
                | Segment 8 | 
                USFS East to Cameron Substation (MP61.3 to MP65.4) | 
                CPUC 
                  BLM | 
                500 kV Overhead | 
                 
                   CPUC request submitted 11/09/10 
                    for non-federal lands only; BLM request submitted 03/25/11 
                 | 
                CPUC NTP #13 issued 01/13/11 
                  for non-federal lands only; modified 02/24/11; 
                  BLM NTP #2 issued 04/04/11 (19.9MB) | 
                 
                   01/20/11 
                 | 
               
               
                | Segment 9 | 
                MP65.4 to MP70.9 | 
                CPUC 
                  BLM | 
                500 kV Overhead | 
                 
                   CPUC request submitted 11/09/10 
                    for non-federal lands only; BLM request submitted 03/25/11 
                 | 
                CPUC NTP #13 issued 01/13/11 
                  for non-federal lands only; modified 02/24/11; 
                  BLM NTP #2 issued 04/04/11 (19.9MB) | 
                 
                   01/20/11 
                 | 
               
               
                | Segment 10 | 
                MP70.9 to MP74.8 | 
                CPUC 
                  BLM 
                  USFS | 
                500 kV Overhead | 
                 
                   CPUC request submitted 11/09/10 
                    for non-federal lands only; BLM request submitted 03/25/11; 
                    USFS request submitted 07/29/11 
                   
                 | 
                CPUC NTP #13 issued 01/13/11 
                  for non-federal lands only; modified 02/24/11; 
                  BLM NTP #2 issued 04/04/11 (19.9MB); 
                  USFS NTP #1 issued 08/09/11 | 
                 
                   01/20/11 
                 | 
               
               
                | Segment 11 | 
                MP74.8 to MP77.6 | 
                CPUC 
                  BLM | 
                500 kV Overhead | 
                 
                   CPUC request submitted 11/09/10 
                    for non-federal lands only; BLM request submitted 03/25/11 
                 | 
                CPUC NTP #13 issued 01/13/11 
                  for non-federal lands only; modified 02/24/11; 
                  BLM NTP #2 issued 04/04/11 (19.9MB) | 
                 
                   01/20/11 
                 | 
               
               
                | Segment 12 | 
                MP77.6 to MP90.0 | 
                CPUC 
                  BLM 
                  USFS | 
                500 kV Overhead | 
                 
                   CPUC request submitted 11/09/10 
                    for non-federal lands only; BLM request submitted 03/25/11; 
                    USFS request submitted 07/29/11 
                   
                 | 
                CPUC NTP #13 issued 01/13/11 
                  for non-federal lands only; modified 02/24/11; 
                  BLM NTP #2 issued 04/04/11 (19.9MB); 
                  USFS NTP #1 issued 08/09/11 | 
                 
                   01/20/11 
                 | 
               
               
                | Segment 13 | 
                Suncrest Substation (Modified Route D Substation) | 
                CPUC | 
                New 500/230 kV Substation | 
                10/20/10; 11/09/10 
                  for non-federal lands only | 
                CPUC NTP #11 issued 12/15/10 | 
                 
                   12/17/10 
                 | 
               
               
                | Segment 14 | 
                Suncrest Substation to Alpine Boulevard (MP90.0 to 
                  MP92.8) | 
                CPUC 
                  USFS | 
                230 kV Overhead | 
                 
                   CPUC request submitted 11/09/10 
                    for non-federal lands only; BLM request submitted 03/25/11; 
                    USFS request submitted 07/29/11 
                   
                 | 
                CPUC NTP #13 issued 01/13/11 
                  for non-federal lands only; modified 02/24/11; 
                  BLM NTP #2 issued 04/04/11 (19.9MB); 
                  USFS NTP #1 issued 08/09/11 | 
                 
                   01/20/11 
                 | 
               
               
                | Segment 15 | 
                Alpine Boulevard Underground (MP92.8 to MP99.0) | 
                CPUC | 
                230 kV Underground | 
                10/13/10; 11/09/10 
                  for non-federal lands only | 
                CPUC NTP #10 issued 11/23/10 | 
                 
                   11/30/10 
                 | 
               
               
                | Segment 16 | 
                Peutz Valley to El Monte Valley (MP99.0 to MP105.5) | 
                CPUC 
                  BLM 
                  USFS | 
                230 kV Overhead | 
                 
                   CPUC request submitted 11/09/10 
                    for non-federal lands only; BLM request submitted 03/25/11; 
                    USFS request submitted 07/29/11 
                   
                 | 
                CPUC NTP #13 issued 01/13/11 
                  for non-federal lands only; modified 02/24/11; 
                  BLM NTP #2 issued 04/04/11 (19.9MB); 
                  USFS NTP #1 issued 08/09/11 | 
                 
                   01/20/11 
                 | 
               
               
                | Segment 17 | 
                El Monte Valley to Highway 67 (MP105.5 to MP112.7) | 
                CPUC 
                  BLM | 
                230 kV Overhead | 
                 
                   CPUC request submitted 11/09/10 
                    for non-federal lands only; BLM request submitted 03/25/11 
                 | 
                CPUC NTP #13 issued 01/13/11 
                  for non-federal lands only; modified 02/24/11; 
                  BLM NTP #2 issued 04/04/11 (19.9MB) | 
                 
                   01/20/11 
                 | 
               
               
                | Segment 18 | 
                Highway 67 to Sycamore Canyon Substation (MP112.7 
                  to MP118.1) | 
                CPUC | 
                230 kV Overhead | 
                 
                   CPUC request submitted 11/09/10 
                    for non-federal lands only; BLM request submitted 03/25/11 
                 | 
                CPUC NTP #13 issued 01/13/11 
                  for non-federal lands only; modified 02/24/11; 
                  BLM NTP #2 issued 04/04/11 (19.9MB) | 
                 
                   01/20/11 
                 | 
               
               
                | Segment 19 | 
                Sycamore Canyon Substation | 
                CPUC | 
                Substation Upgrades | 
                CPUC request not yet submitted;¹ BLM request 
                  submitted 03/25/11 | 
                CPUC NTP #13 issued 01/13/11 
                  for non-federal lands only; modified 02/24/11; 
                  BLM NTP #2 issued 04/04/11 (19.9MB) | 
                 
                   01/20/11 
                 | 
               
               
                | Segment 20 | 
                Sycamore to Elliot 69 kV Reconductor | 
                CPUC | 
                69 kV Reconductoring | 
                 
                   CPUC request submitted 11/09/10; 
                    BLM request submitted 03/25/11 
                 | 
                CPUC NTP #13 issued 01/13/11 
                  for non-federal lands only; modified 02/24/11; 
                  BLM NTP #2 issued 04/04/11 (19.9MB) | 
                 
                   01/20/11 
                 | 
               
               
                | Segment 21 | 
                Sycamore to Scripps 69 kV Reconductor | 
                CPUC | 
                69 kV Reconductoring | 
                 
                   CPUC request submitted 11/09/10; 
                    BLM request submitted 03/25/11 
                 | 
                CPUC NTP #13 issued 01/13/11 
                  for non-federal lands only; modified 02/24/11; 
                  BLM NTP #2 issued 04/04/11 (19.9MB) | 
                 
                   01/20/11 
                 | 
               
               
                | Segment 22 | 
                Sycamore to Pomerado 69 kV Reconductor | 
                CPUC | 
                69 kV Reconductoring | 
                 
                   CPUC request submitted 11/09/10; 
                    BLM request submitted 03/25/11 
                 | 
                CPUC NTP #13 issued 01/13/11 
                  for non-federal lands only; modified 02/24/11; 
                  BLM NTP #2 issued 04/04/11 (19.9MB) | 
                 
                   01/20/11 
                 | 
               
               
                | Segment 23 | 
                South Bay Substation Upgrades | 
                CPUC | 
                Substation Upgrades | 
                02/08/10 | 
                CPUC NTP #2 issued 04/29/10, updated 08/3/10 | 
                 
                   09/17/10 
                 | 
               
               
                | Segment 24 | 
                Encina Switchyard Upgrades | 
                CPUC | 
                Substation Upgrades | 
                05/26/10 | 
                CPUC NTP #6 issued 09/28/10 | 
                 
                   10/15/10 
                 | 
               
               
                | Segment 25 | 
                San Luis Rey Substation Upgrades | 
                CPUC | 
                Substation Upgrades | 
                02/04/10 | 
                CPUC NTP #1 issued 04/28/10, updated 08/3/10 | 
                 
                   09/17/10  
                 | 
               
               
                |  N/A | 
                White Star Telecomm Site | 
                CPUC | 
                Telecomm Site | 
                05/28/10 | 
                CPUC NTP #7 issued 09/28/10 | 
                 
                   10/08/10 
                 | 
               
               
                | N/A | 
                Pomerado Substation Upgrade  
                  (part of PMR submittal) | 
                CPUC | 
                Substation Upgrades | 
                06/09/10 | 
                CPUC NTP #8 issued 09/28/10 | 
                 
                     
                 | 
               
               
                | N/A  | 
                Scripps Substation Upgrade 
                  (part of PMR submittal) | 
                CPUC | 
                Substation Upgrades | 
                06/09/10 | 
                CPUC NTP #9 issued 09/28/10 | 
                 
                     
                 | 
               
               
                |  
                   Construction Yards and Other Workspace 
                 | 
               
               
                | Alpine Yard 18, Town of Alpine | 
                CPUC | 
                Construction Yard | 
                02/26/10 | 
                CPUC NTP #3 issued 05/20/10, updated 08/3/10 | 
                 
                   09/17/10 
                 | 
               
               
                | Alpine Yard 18A, Town of Alpine | 
                CPUC | 
                Construction Yard | 
                01/26/10 | 
                CPUC NTP #4 issued 05/28/10, updated 08/3/10 | 
                 
                   09/17/10 
                 | 
               
               
                | Rough Acres Phase I Yard, Boulevard 
                  area, San Diego County | 
                CPUC | 
                Construction Yard | 
                02/18/10 | 
                CPUC NTP #5 issued 09/28/10 | 
                 
                   10/06/10 
                 | 
               
               
                Rough Acres Phase II Yard, Boulevard area, 
                  San Diego County 
                 | 
                CPUC | 
                Construction Yard | 
                11/29/10 | 
                CPUC NTP #12 issued 12/28/10 
                 | 
                 
                   Not yet authorized  
                 | 
               
             
            1 - No NTP request submitted as of 04/04/11. 
            2 - Compliance with all remaining pre-construction mitigation measures 
            and NTP conditions satisfied 
             
            The CPUC, in conjunction with SDG&E, BLM, USFS and other Responsible 
              Agencies, drafted a Mitigation Monitoring Compliance and Reporting 
              Program (MMCRP) to ensure compliance with mitigation measures approved 
              in the Final EIR/EIS, as well as with the terms and conditions associated 
              with the BLM right-of-way. Although changes may be made to the document 
              as construction progresses, a current final version of the MMCRP 
              document and attachments, including a map 
              of the approved route with segments, is found here. 
             A CPUC Environmental Monitor (EM) is monitoring construction activities 
              to ensure that they are conducted in accordance with the approved 
              mitigation measures and permit conditions. Weekly reports documenting 
              construction status and compliance activities are posted here. 
            As defined by the MMCRP, at various times throughout project construction, 
              the need for extra workspace or additional access roads may be identified. 
              Similarly, changes to the project requirements (e.g., mitigation 
              measures, specifications, etc.) may be needed to facilitate construction 
              (e.g., nighttime construction in response to a planned power outage) 
              or provide more effective protection of resources (e.g., installation 
              of additional erosion control outside of approved disturbance areas). 
              The CPUC Project Manager, along with the CPUC EMs, will implement 
              the variance procedures defined in the MMCRP to evaluate each proposed 
              project change for its potential for creating significant environmental 
              effects to determine whether supplemental CEQA and/or NEPA review 
              is required. Variance Requests processed to date are provided in 
              the table below. 
            
               
                |  
                  
                 | 
               
               
                |  
                   Variance 
                    Request 
                 | 
                 
                   Date 
                    Requested 
                 | 
                 
                   Date 
                    Issued 
                 | 
                 
                   Segment 
                 | 
                Description | 
               
               
                |  
                   #1 
                 | 
                 
                   11/4/10  
                 | 
                 
                  
                 | 
                 
                   N/A 
                 | 
                Thomas Yard, Imperial County | 
               
               
                |  
                   #2 
                 | 
                 
                   12/22/10 
                 | 
                 
                  
                 | 
                 
                   N/A 
                 | 
                Sycamore Estates Construction Yard. Comments submitted 
                  to SDG&E 01/06/11. | 
               
               
                |  
                   #3 
                 | 
                 
                   01/06/11 
                 | 
                 
                  
                 | 
                 
                   All 
                 | 
                Variance from Mitigation Measure B-8a 
                  to allow limited tree trimming to occur between January 1 
                  and September 15. | 
               
               
                |  
                   #3 MOD 
                 | 
                 
                   01/21/11 
                 | 
                 
                  
                 | 
                 
                   All 
                 | 
                Allow limited vegetation clearing between January 15 
                  and September 15 | 
               
               
                |  
                   #4 
                 | 
                 
                   01/13/11 
                 | 
                 
                  
                 | 
                 
                   N/A 
                 | 
                Helicopter Temporary Landing Pad area at the Alpine 
                  Regional Field Offices | 
               
               
                |  
                   #5 
                 | 
                 
                   02/01/11 
                 | 
                 
                  
                 | 
                 
                   Link 3, Segment 13 
                 | 
                 Site improvements at the Wilson Construction Yard 
                  and along Bell Bluff Trail | 
               
               
                |  
                   #6 
                 | 
                 
                   02/01/11 
                 | 
                 
                  
                 | 
                 
                   Link 5, Segment 16 
                 | 
                Variance from Mitigation Measure H-1a 
                  (CC) to allow work outside of the dry season | 
               
               
                |  
                   #7 
                 | 
                 
                   02/11/11 
                 | 
                 
                  
                 | 
                 
                   Link 3, Segment 13 
                 | 
                Expand work limits along Bell Bluff Truck Trail | 
               
               
                |  
                   #8 
                 | 
                 
                   03/02/11 
                 | 
                 
                  
                 | 
                 
                   Link 2 
                 | 
                Alternative access route to structure EP27 | 
               
               
                |  
                   #9 
                 | 
                 
                   03/29/11 
                 | 
                 
                  
                 | 
                 
                   All 
                 | 
                Variance from Mitigation Measure N-1a 
                  and expanded workdays/hours | 
               
               
                |  
                   #10 
                 | 
                 
                   04/05/11 
                 | 
                 
                  
                 | 
                 
                   Link 4 
                 | 
                Expand work space north of Viejas Creek Bridge | 
               
               
                |  
                   #11 
                 | 
                 
                   04/06/11 
                 | 
                 
                  
                 | 
                 
                   Link 1 
                 | 
                Add additional 200-ft-by-150-ft extra workspace east 
                  of structure EP 215 | 
               
               
                |  
                   #12 
                 | 
                 
                   04/15/11 
                 | 
                 
                  
                 | 
                 
                   Link 1 
                 | 
                Add turnaround along the access road to Structure 
                  EP 220-1 | 
               
               
                |  
                   #13 
                 | 
                 
                   04/25/11 
                 | 
                 
                  
                 | 
                 
                   Link 1 
                 | 
                Request to add communication shelters near EP215 
                  and EP54-1 | 
               
               
                |  
                   #14 
                 | 
                 
                   04/28/11 
                 | 
                 
                  
                 | 
                 
                   Projectwide 
                 | 
                Variance from the approved Construction Yard Visual 
                  Screening Plan  | 
               
               
                |  
                   #15 
                 | 
                 
                   05/12/11 
                 | 
                 
                  
                 | 
                 
                   Link 2 
                 | 
                Alternate reroutes along approved the access road 
                  to structure EP84 | 
               
               
                |  
                   #16 
                 | 
                 
                   05/16/11  
                 | 
                 
                  
                 | 
                 
                   Link 4 
                 | 
                Request to use four vehicle equipment parking areas 
                  in Link 4 | 
               
               
                |  
                   #17 
                 | 
                 
                   05/18/11  
                 | 
                 
                  
                 | 
                 
                   Segment 24 
                 | 
                Modification to the driveway at the Encina Substation | 
               
               
                |  
                   #18 
                 | 
                 
                   06/27/11 
                 | 
                 
                  
                 | 
                 
                   Link 1 
                 | 
                Installation of gates along a number of project access 
                  roads in the Jacumba area | 
               
               
                |  
                   #19 
                 | 
                 
                   06/27/11 
                 | 
                 
                  
                 | 
                 
                   Rough Acres Yard  
                 | 
                Temporary installation of a foundation and towers 
                  at the yard site | 
               
               
                |  
                   #20 
                 | 
                 
                   7/11/11 
                 | 
                 
                  
                 | 
                 
                   Link 5 
                 | 
                Modification of a temporary access route to pull 
                  site between CP 48-2 and CP 49-1, 
                  addition of a pull site along the access road between CP 49-1 
                  and CP 50-1 and addition of a site approximately 
                  600 feet south of CP 51-2 to stockpile soil | 
               
               
                |  
                   #21 
                 | 
                 
                   07/07/11 
                 | 
                 
                  
                 | 
                 
                   Link 1 
                 | 
                Permits workspace and access for guarding of facilities 
                  near GS-NF-37 and GS-BLM-4/GS-NF-41 | 
               
               
                |  
                   #22 
                 | 
                 
                   07/15/11 
                 | 
                 
                  
                 | 
                 
                   Link 1 
                 | 
                Requests use of the Fromm construction yard | 
               
               
                |  
                   #23 
                 | 
                 
                   08/15/11 
                 | 
                 
                   Under Review 
                 | 
                 
                   Links 1, 2, and 5 
                 | 
                Helicopter landing pads and TSAPs on non-federal 
                  lands | 
               
               
                |  
                   #24 
                 | 
                 
                   08/25/11 
                 | 
                 
                  
                 | 
                 
                   Link 3 
                 | 
                Vegetation clearing at the Suncrest Substation for 
                  fire safety | 
               
               
                |  
                   #25 
                 | 
                 
                   09/01/11 
                 | 
                 
                  
                 | 
                 
                   Links 1, 2, and 5 
                 | 
                Prolonged use of previously approved TEWS areas | 
               
               
                |  
                   #26 
                 | 
                 
                   09/16/11 
                 | 
                 
                  
                 | 
                 
                   Link 2 
                 | 
                Tank stand placement adjacent to Barrett Substation | 
               
             
            On Cleveland National Forest (CNF) lands the USFS District Ranger 
              will evaluate and provide variance review and approval. Variance 
              requests processed to date are provided in the table below. 
            
               
                |  
                  
                 | 
               
               
                |  
                   Variance 
                    Request 
                 | 
                 
                   Date 
                    Requested 
                 | 
                 
                   Date 
                    Issued 
                 | 
                 
                   Segment 
                 | 
                Description | 
               
               
                |  
                   #1 
                 | 
                 
                   08/30/11 
                 | 
                 
                  
                 | 
                 
                   USFS lands 
                 | 
                Conduct work until 1:00pm on PAL fire danger days | 
               
             
            SDG&E has submitted a compilation of micrositing changes to 
              the approved Project on BLM lands. A determination of NEPA 
              Adequacy (DNA) was conducted. Please see the table below. 
            
               
                 
                  Determinations of 
                    NEPA Adequacy 
                 | 
               
               
                |  
                   DNA 
                    Request 
                 | 
                 
                   Date 
                    Requested 
                 | 
                 
                   Date 
                    Issued 
                 | 
                 
                   Segment 
                 | 
                Description | 
               
               
                |  
                   #1 
                 | 
                 
                   06/22/11 
                 | 
                 
                  
                 | 
                 
                   Links 1, 2, and 5 
                 | 
                Micrositing changes to the approved project on BLM 
                  lands | 
               
             
            The following table provides the FAA authorizations granted to 
              SDG&E for use of the sky crane from the project construction 
              yards for tower construction activities. In addition, the CPUC incident 
              response letter to two sky crane related incidents is also provided. 
              On September 27, 2011, the CPUC issued a Stop 
              Work Order affecting project helicopters, pending resolution 
              of issues. On October 4, 2011, the CPUC determined that the 
              issues had been resolved and notified SDG&E 
              that it could resume helicopter operations. 
            
            Project 
              Modifications Report  
            Determination: The CPUC and BLM have published the CEQA 
              and NEPA Determination on SDG&E's proposed Project Modifications; 
              the supporting documents are available here. 
              After careful review of the proposed modifications, as documented 
              in the Determination Memorandum and BLM Determination of NEPA Adequacy 
              and in accordance with the CEQA and NEPA requirements, the CPUC 
              and BLM have determined that the changes to the Sunrise Powerlink 
              Project are within the scope of the Certificate of Public Convenience 
              and Necessity and Record of Decision issued by the CPUC and BLM 
              respectively. 
             Background: After the Final Environmentally Superior Southern 
              Route was approved by CPUC in December 2008 and BLM in January of 
              2009, SDG&E began the process of completing final project design 
              and engineering. As is common, some project components were modified 
              as engineering was completed. Modifications result from compliance 
              with adopted mitigation measures requiring resource avoidance to 
              minimize or avoid environmental impacts and final engineering design 
              requirements. In addition, some project components have been relocated 
              to accommodate landowner location preferences where possible in 
              compliance with mitigation requirements. As a part of this process, 
              SDG&E has been working with landowners regarding project components 
              and transmission line routes within their properties. 
             On January 22, 2010, SDG&E submitted to CPUC and BLM an internal 
              administrative draft of its Project Modification Report (PMR) that 
              defined changes made to the project along the entire route after 
              publication of the Final EIR/EIS. The document explained the reason 
              for each change, and presented the comparative environmental impacts 
              of the project components analyzed in the Final EIR/EIS and those 
              presented in the PMR. All changes included in the report were reviewed 
              by the lead agencies, CPUC and BLM, along with the cooperating, 
              responsible and resource agencies. The CPUC compiled and submitted 
              comments to SDG&E from the EIR/EIS Team and other agencies to 
              ensure that the PMR document included sufficient information to 
              make a determination for each reroute. SDG&E has since incorporated 
              comments, conclusions, and made required changes. 
             On May 14, 2010, SDG&E submitted to CPUC and BLM a final Project 
              Modifications Report that defines changes made to the project 
              along the entire route after publication of the Final EIR/EIS. Similar 
              to the administrative draft PMR, the final PMR document explains 
              the reason for each change, and presents the comparative environmental 
              impacts of the project components analyzed in the Final EIR/EIS 
              and those presented in the PMR. The final PMR document is found 
              here. 
             The CPUC accepted public comments on the Final PMR from May 14 
              to June 7, 2010, and reviewed all comments while evaluating 
              the proposed modifications. 
             Final EIR/EIS 
            The Final EIR/EIS was released to the public on October 13, 
              2008. The Final EIR/EIS is available here 
              and is also available at numerous area libraries 
              and government offices. Copies of the Executive Summary of the 
              Final EIR/EIS along with a DVD of the complete document may be requested. 
              CPUC and BLM also have a limited number of copies of the complete 
              four-volume Final EIR/EIS document available to the public. Requests 
              for documents should be made to (866) 711-3106 (phone or fax) or 
              via email to sunrise@aspeneg.com. 
            The Notice of Availability provides 
              further information on the approval processes for CPUC and BLM. 
              Pursuant to NEPA requirements, the Final EIR/EIS and Proposed Land 
              Use Plan Amendment will be available for review for 30 calendar 
              days from the date the Environmental Protection Agency (EPA) publishes 
              the Notice of Availability (NOA) in the Federal Register, which 
              is expected to occur on October 17, 2008. The review period 
              would end on November 15, 2008. 
             
            Copies of the Executive Summary of the Final EIR/EIS along with 
              a DVD of the complete document may be requested. CPUC and BLM also 
              have a limited number of copies of the complete four-volume Final 
              EIR/EIS document available to the public. Requests for documents 
              should be made to (866) 711-3106 (phone or fax) or via email to 
              sunrise@aspeneg.com. 
            Draft 
              EIR/EIS 
             CPUC and BLM published the Draft EIR/EIS in January 2008. Please 
              note that the Final EIR/EIS (described above) includes the entire 
              text of the Draft EIR/EIS, modified where necessary in response 
              to comments on the Draft EIR/EIS. The original text of the Draft 
              EIR/EIS document is available here. 
            EIR/EIS 
              Alternatives 
            Throughout 2007, CPUC and BLM gathered information on alternatives 
              to the proposed Sunrise Powerlink Project through an extensive public 
              involvement process. Information and documents from that process 
              are available here. 
            Documents 
              Available 
            In addition to the EIR/EIS, other documents that were published 
              during the CEQA and NEPA processes are available here. 
              Documents and letters that were compiled following publication of 
              the Final EIR/EIS, such as SDG&E Biological Assessment, USFWS 
              Biological Opinion, BLM Section 106 Programmatic Agreement, and 
              appeals to the BLM Interior Board of Land Appeals, are also included. 
             
            In response to concerns from the Lakeside community, a fact sheet 
              that summarizes past public notification and consideration of alternative 
              routes in the community of Lakeside is available here 
              (posted February 24, 2009). A similar fact sheet on public 
              notification was prepared for the Town of Alpine in January 2010 
              and is available here. 
            
            Data 
              Requests 
            The EIR/EIS Team submits Data Requests to SDG&E and other entities 
              when it needs specific information to support EIR/EIS preparation. 
              These requests are available here at 
              the time they are issued. 
            Requests for 
              Technical Information Related to the Draft EIR/EIS 
            During the 90-day public comment period on the Draft EIR/EIS, various 
              parties submitted requests for technical information related to 
              that document. The information provided is available here. 
             
            For 
              Additional Information 
            To request additional information or to be added to the mailing 
              list, please contact us by email, fax, or phone, as follows: 
            
            The CPUC's Project Manager is: 
            Billie Blanchard, CPUC Project Manager 
              California Public Utilities Commission 
              505 Van Ness Avenue 
              San Francisco CA 94102 
              Tel. (415) 703-2068 
              Fax (415) 703-2200 
              Email:  bcb@cpuc.ca.gov
             
           |