              Welcome to the California Public Utilities Commission (CPUC) website 
              for the California Environmental Quality Act (CEQA) review of the 
              Sunrise Powerlink Transmission Line Project. Applications for this 
              project were submitted to CPUC on December 14, 2005 (A.05-12-014) 
              and August 4, 2006 (A.06-08-010). The Proponent's Environmental 
              Assessment was filed with the CPUC on August 4, 2006. This 
              project was approved by the California Independent System Operator 
              on August 3, 2006. This site provides access to public documents 
              and information relevant to the CEQA and National Environmental 
              Policy Act (NEPA) review processes. The CPUC voted on December 18, 
              2008 to approve the Final Environmentally Superior Southern Route 
              (see Decision D.08-12-058) and a Notice 
              of Determination was submitted to the State Clearinghouse. The 
              Bureau of Land Management (BLM) issued a Record 
              of Decision approving the same route on January 20, 2009. 
            
  
               
                 
                  JUMP TO: 
                    Mitigation Monitoring, Compliance, and 
                    Reporting Program - Final Report 
                    Construction and Mitigation Monitoring 
                    Mitigation Monitoring Compliance and 
                    Reporting Plan  
                    Notices to Proceed 
                    Construction Monitoring Reports 
                    CPUC Variance Approvals 
                    USFS Variance Approvals 
                    Other Agency Variance Approvals 
                    Determinations of NEPA Adequacy 
                    Helicopter Operations and FAA Compliance 
                    Project Modifications Report  
                    Final EIR/EIS 
                    Draft EIR/EIS 
                    EIR/EIS Alternatives 
                    Documents Available 
                    Data Requests 
                    Requests for Technical Information Related 
                    to the Draft EIR/EIS 
                    For Additional Information 
                 
               
             
             
               
            
  
             Final 
              Mitigation Monitoring, Compliance, and Reporting Program Report 
             A Final Mitigation Monitoring, Compliance, and Reporting Program 
              Report has been prepared and can be found here. 
              The report provides a broad summary of the entire project including 
              preconstruction review, document approvals, NTPs, variances and 
              DNAs, construction progress, mitigation monitoring, compliance, 
              closeout tasks, and restoration as well as operations and maintenance 
              expectations.
             Construction 
              and Mitigation Monitoring 
             Construction of the Sunrise Powerlink Project began in September 
              2010 with the establishment of some construction yards and existing 
              substation upgrades. Mainline construction began in November 2010. 
              The Sunrise Powerlink was energized in June 2012. Remaining punch 
              list work was conducted through June 2013. Ongoing restoration activities 
              continue. Prior to construction all work was approved under segmented 
              Notices to Proceed (NTPs) issued by the CPUC, BLM, USFS, or MCAS 
              Miramar depending on jurisdiction, area, and type of work.
              Issuance of NTPs was contingent upon SDG&E compliance with 
              pre-construction requirements as specified by the approved mitigation 
              measures and responsible agency permitting requirements. Approved 
              pre-compliance reports, permits, and other documents are available 
              in their final form here. All NTPs issued 
              to SDG&E are noted in the table below. 
             SDG&E divided the Sunrise Powerlink Project into 25 segments 
              including several additional work areas, as follows: 
               
             
               
                |  
                   Notices to Proceed 
                 | 
               
               
                |  
                   Segment 
                 | 
                 
                   Description 
                 | 
                 
                   Jurisdiction 
                 | 
                 
                   Type 
                 | 
                 
                   NTP Request Submitted 
                 | 
                 
                   NTP Issued 
                 | 
                 
                   Construction 
                     Authorized* 
                 | 
               
               
                | Segment 1 | 
                Imperial Valley Substation | 
                BLM | 
                Substation Upgrades | 
                BLM request submitted 01/19/11 | 
                BLM NTP #1 issued 02/3/11 
                 | 
                 
                   02/04/11 
                 | 
               
               
                | Segment 2 | 
                Imperial Valley Substation to Pyramid Mining (MP0 
                  to MP19.2) | 
                CPUC 
                  BLM | 
                500 kV Overhead | 
                 
                   CPUC request submitted 11/09/10 
                    for non-federal lands only; 3/28/11; BLM request submitted 
                    03/25/11 
                 | 
                CPUC NTP #13 issued 01/13/11 
                  for non-federal lands only; modified 02/24/11; 
                  BLM NTP #2 issued 04/04/11 (19.9MB) | 
                 
                   01/20/11 
                 | 
               
               
                | Segment 3 | 
                Pyramid Mining to Mountain Springs Grade (MP19.2 
                  to MP23.2) | 
                CPUC 
                  BLM | 
                500 kV Overhead | 
                 
                   CPUC request submitted 11/09/10 
                    for nonfederal lands only; BLM request submitted 03/25/11 
                 | 
                CPUC NTP #13 issued 01/13/11 
                  for nonfederal lands only; modified 02/24/11; 
                  BLM NTP #2 issued 04/04/11 (19.9MB) | 
                 
                   01/20/11 
                 | 
               
               
                | Segment 4 | 
                Mountain Springs Grade to Jade (MP23.2 to MP30.3) | 
                CPUC 
                  BLM | 
                500 kV Overhead | 
                 
                   CPUC request submitted 11/09/10 
                    for nonfederal lands only; BLM request submitted 03/25/11 
                 | 
                CPUC NTP #13 issued 01/13/11 
                  for nonfederal lands only; modified 02/24/11; 
                  BLM NTP #2 issued 04/04/11 (19.9MB) | 
                 
                   01/20/11 
                 | 
               
               
                | Segment 5 | 
                Jade to I-8 (McCain Valley) (MP30.3 to MP39.7) | 
                CPUC 
                  BLM | 
                500 kV Overhead | 
                 
                   CPUC request submitted 11/09/10 
                    for nonfederal lands only; BLM request submitted 03/25/11 
                 | 
                CPUC NTP #13 issued 01/13/11 
                  for nonfederal lands only; modified 02/24/11; 
                  BLM NTP #2 issued 04/04/11 (19.9MB) | 
                 
                   01/20/11 
                 | 
               
               
                | Segment 6 | 
                I-8 (McCain Valley) to USFS (MP39.7 to MP52.5) | 
                CPUC 
                  BLM 
                  USFS | 
                500 kV Overhead | 
                 
                   CPUC request submitted 11/09/10 
                    for nonfederal lands only; BLM request submitted 03/25/11; 
                    USFS request submitted 07/29/11 
                   
                 | 
                CPUC NTP #13 issued 01/13/11 
                  for nonfederal lands only; modified 02/24/11; 
                  BLM NTP #2 issued 04/04/11 (19.9MB); 
                  USFS NTP #1 issued 08/09/11 | 
                 
                   01/20/11 
                 | 
               
               
                | Segment 7 | 
                USFS East (MP52.5 to MP61.3) | 
                CPUC 
                  BLM 
                  USFS | 
                500 kV Overhead | 
                 
                   CPUC request submitted 11/09/10 
                    for nonfederal lands only; BLM request submitted 03/25/11; 
                    USFS request submitted 07/29/11 
                   
                 | 
                CPUC NTP #13 issued 01/13/11 
                  for nonfederal lands only; modified 02/24/11; 
                  BLM NTP #2 issued 04/04/11 (19.9MB); 
                  USFS NTP #1 issued 08/09/11 | 
                 
                   01/20/11 
                 | 
               
               
                | Segment 8 | 
                USFS East to Cameron Substation (MP61.3 to MP65.4) | 
                CPUC 
                  BLM | 
                500 kV Overhead | 
                 
                   CPUC request submitted 11/09/10 
                    for nonfederal lands only; BLM request submitted 03/25/11 
                 | 
                CPUC NTP #13 issued 01/13/11 
                  for nonfederal lands only; modified 02/24/11; 
                  BLM NTP #2 issued 04/04/11 (19.9MB) | 
                 
                   01/20/11 
                 | 
               
               
                | Segment 9 | 
                MP65.4 to MP70.9 | 
                CPUC 
                  BLM | 
                500 kV Overhead | 
                 
                   CPUC request submitted 11/09/10 
                    for nonfederal lands only; BLM request submitted 03/25/11 
                 | 
                CPUC NTP #13 issued 01/13/11 
                  for nonfederal lands only; modified 02/24/11; 
                  BLM NTP #2 issued 04/04/11 (19.9MB) | 
                 
                   01/20/11 
                 | 
               
               
                | Segment 10 | 
                MP70.9 to MP74.8 | 
                CPUC 
                  BLM 
                  USFS | 
                500 kV Overhead | 
                 
                   CPUC request submitted 11/09/10 
                    for nonfederal lands only; BLM request submitted 03/25/11; 
                    USFS request submitted 07/29/11 
                   
                 | 
                CPUC NTP #13 issued 01/13/11 
                  for nonfederal lands only; modified 02/24/11; 
                  BLM NTP #2 issued 04/04/11 (19.9MB); 
                  USFS NTP #1 issued 08/09/11 | 
                 
                   01/20/11 
                 | 
               
               
                | Segment 11 | 
                MP74.8 to MP77.6 | 
                CPUC 
                  BLM | 
                500 kV Overhead | 
                 
                   CPUC request submitted 11/09/10 
                    for nonfederal lands only; BLM request submitted 03/25/11 
                 | 
                CPUC NTP #13 issued 01/13/11 
                  for nonfederal lands only; modified 02/24/11; 
                  BLM NTP #2 issued 04/04/11 (19.9MB) | 
                 
                   01/20/11 
                 | 
               
               
                | Segment 12 | 
                MP77.6 to MP90.0 | 
                CPUC 
                  BLM 
                  USFS | 
                500 kV Overhead | 
                 
                   CPUC request submitted 11/09/10 
                    for nonfederal lands only; BLM request submitted 03/25/11; 
                    USFS request submitted 07/29/11 
                   
                 | 
                CPUC NTP #13 issued 01/13/11 
                  for nonfederal lands only; modified 02/24/11; 
                  BLM NTP #2 issued 04/04/11 (19.9MB); 
                  USFS NTP #1 issued 08/09/11 | 
                 
                   01/20/11 
                 | 
               
               
                | Segment 13 | 
                Suncrest Substation (Modified Route D Substation) | 
                CPUC | 
                New 500/230 kV Substation | 
                10/20/10; 11/09/10 
                  for nonfederal lands only | 
                CPUC NTP #11 issued 12/15/10 | 
                 
                   12/17/10 
                 | 
               
               
                | Segment 14 | 
                Suncrest Substation to Alpine Boulevard (MP90.0 to 
                  MP92.8) | 
                CPUC 
                  USFS | 
                230 kV Overhead | 
                 
                   CPUC request submitted 11/09/10 
                    for nonfederal lands only; BLM request submitted 03/25/11; 
                    USFS request submitted 07/29/11 
                   
                 | 
                CPUC NTP #13 issued 01/13/11 
                  for nonfederal lands only; modified 02/24/11; 
                  BLM NTP #2 issued 04/04/11 (19.9MB); 
                  USFS NTP #1 issued 08/09/11 | 
                 
                   01/20/11 
                 | 
               
               
                | Segment 15 | 
                Alpine Boulevard Underground (MP92.8 to MP99.0) | 
                CPUC | 
                230 kV Underground | 
                10/13/10; 11/09/10 
                  for nonfederal lands only | 
                CPUC NTP #10 issued 11/23/10 | 
                 
                   11/30/10 
                 | 
               
               
                | Segment 16 | 
                Peutz Valley to El Monte Valley (MP99.0 to MP105.5) | 
                CPUC 
                  BLM 
                  USFS | 
                230 kV Overhead | 
                 
                   CPUC request submitted 11/09/10 
                    for nonfederal lands only; BLM request submitted 03/25/11; 
                    USFS request submitted 07/29/11 
                   
                 | 
                CPUC NTP #13 issued 01/13/11 
                  for nonfederal lands only; modified 02/24/11; 
                  BLM NTP #2 issued 04/04/11 (19.9MB); 
                  USFS NTP #1 issued 08/09/11 | 
                 
                   01/20/11 
                 | 
               
               
                | Segment 17 | 
                El Monte Valley to Highway 67 (MP105.5 to MP112.7) | 
                CPUC 
                  BLM | 
                230 kV Overhead | 
                 
                   CPUC request submitted 11/09/10 
                    for nonfederal lands only; BLM request submitted 03/25/11 
                 | 
                CPUC NTP #13 issued 01/13/11 
                  for nonfederal lands only; modified 02/24/11; 
                  BLM NTP #2 issued 04/04/11 (19.9MB) | 
                 
                   01/20/11 
                 | 
               
               
                | Segment 18 | 
                Highway 67 to Sycamore Canyon Substation (MP112.7 
                  to MP118.1) | 
                CPUC | 
                230 kV Overhead | 
                 
                   CPUC request submitted 11/09/10 
                    for nonfederal lands only; BLM request submitted 03/25/11 
                 | 
                CPUC NTP #13 issued 01/13/11 
                  for nonfederal lands only; modified 02/24/11; 
                  BLM NTP #2 issued 04/04/11 (19.9MB) | 
                 
                   01/20/11 
                 | 
               
               
                | Segment 19 | 
                Sycamore Canyon Substation | 
                CPUC | 
                Substation Upgrades | 
                CPUC request not yet submitted;¹ BLM request 
                  submitted 03/25/11 | 
                CPUC NTP #13 issued 01/13/11 
                  for nonfederal lands only; modified 02/24/11; 
                  BLM NTP #2 issued 04/04/11 (19.9MB) | 
                 
                   01/20/11 
                 | 
               
               
                | Segment 20 | 
                Sycamore to Elliot 69 kV Reconductor | 
                CPUC | 
                69 kV Reconductoring | 
                 
                   CPUC request submitted 11/09/10; 
                    BLM request submitted 03/25/11 
                 | 
                CPUC NTP #13 issued 01/13/11 
                  for nonfederal lands only; modified 02/24/11; 
                  BLM NTP #2 issued 04/04/11 (19.9MB) | 
                 
                   01/20/11 
                 | 
               
               
                | Segment 21 | 
                Sycamore to Scripps 69 kV Reconductor | 
                CPUC | 
                69 kV Reconductoring | 
                 
                   CPUC request submitted 11/09/10; 
                    BLM request submitted 03/25/11 
                 | 
                CPUC NTP #13 issued 01/13/11 
                  for nonfederal lands only; modified 02/24/11; 
                  BLM NTP #2 issued 04/04/11 (19.9MB) | 
                 
                   01/20/11 
                 | 
               
               
                | Segment 22 | 
                Sycamore to Pomerado 69 kV Reconductor | 
                CPUC | 
                69 kV Reconductoring | 
                 
                   CPUC request submitted 11/09/10; 
                    BLM request submitted 03/25/11 
                 | 
                CPUC NTP #13 issued 01/13/11 
                  for nonfederal lands only; modified 02/24/11; 
                  BLM NTP #2 issued 04/04/11 (19.9MB) | 
                 
                   01/20/11 
                 | 
               
               
                | Segment 23 | 
                South Bay Substation Upgrades | 
                CPUC | 
                Substation Upgrades | 
                02/08/10 | 
                CPUC NTP #2 issued 04/29/10, updated 08/3/10 | 
                 
                   09/17/10 
                 | 
               
               
                | Segment 24 | 
                Encina Switchyard Upgrades | 
                CPUC | 
                Substation Upgrades | 
                05/26/10 | 
                CPUC NTP #6 issued 09/28/10 | 
                 
                   10/15/10 
                 | 
               
               
                | Segment 25 | 
                San Luis Rey Substation Upgrades | 
                CPUC | 
                Substation Upgrades | 
                02/04/10 | 
                CPUC NTP #1 issued 04/28/10, updated 08/3/10 | 
                 
                   09/17/10  
                 | 
               
               
                |  N/A | 
                White Star Telecomm Site | 
                CPUC | 
                Telecomm Site | 
                05/28/10 | 
                CPUC NTP #7 issued 09/28/10 | 
                 
                   10/08/10 
                 | 
               
               
                | N/A | 
                Pomerado Substation Upgrade  
                  (part of PMR submittal) | 
                CPUC | 
                Substation Upgrades | 
                06/09/10 | 
                CPUC NTP #8 issued 09/28/10 | 
                 
                     
                 | 
               
               
                | N/A  | 
                Scripps Substation Upgrade 
                  (part of PMR submittal) | 
                CPUC | 
                Substation Upgrades | 
                06/09/10 | 
                CPUC NTP #9 issued 09/28/10 | 
                 
                     
                 | 
               
               
                |  
                   Construction Yards and Other Workspace 
                 | 
               
               
                | Alpine Yard 18, Town of Alpine | 
                CPUC | 
                Construction Yard | 
                02/26/10 | 
                CPUC NTP #3 issued 05/20/10, updated 08/3/10 | 
                 
                   09/17/10 
                 | 
               
               
                | Alpine Yard 18A, Town of Alpine | 
                CPUC | 
                Construction Yard | 
                01/26/10 | 
                CPUC NTP #4 issued 05/28/10, updated 08/3/10 | 
                 
                   09/17/10 
                 | 
               
               
                | Rough Acres Phase I Yard, Boulevard 
                  area, San Diego County | 
                CPUC | 
                Construction Yard | 
                02/18/10 | 
                CPUC NTP #5 issued 09/28/10 | 
                 
                   10/06/10 
                 | 
               
               
                Rough Acres Phase II Yard, Boulevard area, 
                  San Diego County 
                 | 
                CPUC | 
                Construction Yard | 
                11/29/10 | 
                CPUC NTP #12 issued 12/28/10 
                 | 
                 
                   Not yet authorized  
                 | 
               
             
            *Compliance with all remaining pre-construction mitigation 
            measures and NTP conditions satisfied 
             
            The CPUC, in conjunction with SDG&E, BLM, USFS, and other Responsible 
              Agencies, drafted a Mitigation Monitoring Compliance and Reporting 
              Program (MMCRP) to ensure compliance with mitigation measures approved 
              in the Final EIR/EIS, as well as with the terms and conditions associated 
              with the BLM right-of-way. A current version of the MMCRP document 
              and attachments, including a map 
              of the approved route with segments, is found here. 
             CPUC Environmental Monitors (EMs) assisted the CPUC, BLM, and USFS 
              by monitoring construction activities to ensure that they were conducted 
              in accordance with approved mitigation measures and permit conditions. 
              Weekly reports documenting construction activities and compliance 
              are posted here. 
            As defined by the MMCRP, at various times throughout project construction, 
              needs for extra workspace or micrositing changes were identified. 
              Similarly, minor changes to the project requirements (e.g., mitigation 
              measures, specifications, etc.) were needed to facilitate construction 
              (e.g., nighttime construction in response to a planned power outage). 
              The CPUC Project Manager, along with the CPUC EMS, implemented the 
              variance procedures defined in the MMCRP to evaluate each proposed 
              project change for its potential for creating significant environmental 
              effects to determine whether supplemental CEQA and/or NEPA review 
              was required. CPUC Variance Requests processed are provided in the 
              table below. 
               
             
               
                |  
                   CPUC Variance Approvals 
                 | 
               
               
                |  
                   Variance 
                    Request 
                 | 
                 
                   Date 
                    Requested 
                 | 
                 
                   Date 
                    Issued 
                 | 
                 
                   Segment 
                 | 
                Description | 
               
               
                |  
                   #1 
                 | 
                 
                   11/04/10  
                 | 
                 
                  
                 | 
                 
                   N/A 
                 | 
                Thomas Yard, Imperial County | 
               
               
                |  
                   #2 
                 | 
                 
                   12/22/10 
                 | 
                 
                  
                 | 
                 
                   N/A 
                 | 
                Sycamore Estates Construction Yard. Comments submitted 
                  to SDG&E 01/06/11. | 
               
               
                |  
                   #3 
                 | 
                 
                   01/06/11 
                 | 
                 
                  
                 | 
                 
                   All 
                 | 
                Variance from Mitigation Measure B-8a 
                  to allow limited tree trimming to occur between January 1 
                  and September 15. | 
               
               
                |  
                   #3 MOD 
                 | 
                 
                   01/21/11 
                 | 
                 
                  
                 | 
                 
                   All 
                 | 
                Allow limited vegetation clearing between January 15 
                  and September 15 | 
               
               
                |  
                   #4 
                 | 
                 
                   01/13/11 
                 | 
                 
                  
                 | 
                 
                   N/A 
                 | 
                Helicopter Temporary Landing Pad area at the Alpine 
                  Regional Field Offices | 
               
               
                |  
                   #5 
                 | 
                 
                   02/01/11 
                 | 
                 
                  
                 | 
                 
                   Link 3, Segment 13 
                 | 
                 Site improvements at the Wilson Construction Yard 
                  and along Bell Bluff Trail | 
               
               
                |  
                   #6 
                 | 
                 
                   02/01/11 
                 | 
                 
                  
                 | 
                 
                   Link 5, Segment 16 
                 | 
                Variance from Mitigation Measure H-1a 
                  (CC) to allow work outside of the dry season | 
               
               
                |  
                   #7 
                 | 
                 
                   02/11/11 
                 | 
                 
                  
                 | 
                 
                   Link 3, Segment 13 
                 | 
                Expand work limits along Bell Bluff Truck Trail | 
               
               
                |  
                   #8 
                 | 
                 
                   03/02/11 
                 | 
                 
                  
                 | 
                 
                   Link 2 
                 | 
                Alternative access route to structure EP27 | 
               
               
                |  
                   #9 
                 | 
                 
                   03/29/11 
                 | 
                 
                  
                 | 
                 
                   All 
                 | 
                Variance from Mitigation Measure N-1a 
                  and expanded workdays/hours | 
               
               
                |  
                   #10 
                 | 
                 
                   04/05/11 
                 | 
                 
                  
                 | 
                 
                   Link 4 
                 | 
                Expand work space north of Viejas Creek Bridge | 
               
               
                |  
                   #11 
                 | 
                 
                   04/06/11 
                 | 
                 
                  
                 | 
                 
                   Link 1 
                 | 
                Add additional 200-ft-by-150-ft extra workspace east 
                  of structure EP 215 | 
               
               
                |  
                   #12 
                 | 
                 
                   04/15/11 
                 | 
                 
                  
                 | 
                 
                   Link 1 
                 | 
                Add turnaround along the access road to Structure 
                  EP 220-1 | 
               
               
                |  
                   #13 
                 | 
                 
                   04/25/11 
                 | 
                 
                  
                 | 
                 
                   Link 1 
                 | 
                Request to add communication shelters near EP215 
                  and EP54-1 | 
               
               
                |  
                   #13 MOD 
                 | 
                 
                   05/06/12 
                 | 
                 
                  
                 | 
                 
                   Link 1 
                 | 
                Alter two previously approved telecom shelter configurations. | 
               
               
                |  
                   #14 
                 | 
                 
                   04/28/11 
                 | 
                 
                  
                 | 
                 
                   Projectwide 
                 | 
                Variance from the approved Construction Yard Visual 
                  Screening Plan  | 
               
               
                |  
                   #15 
                 | 
                 
                   05/12/11 
                 | 
                 
                  
                 | 
                 
                   Link 2 
                 | 
                Alternate reroutes along approved the access road 
                  to structure EP84 | 
               
               
                |  
                   #16 
                 | 
                 
                   05/16/11  
                 | 
                 
                  
                 | 
                 
                   Link 4 
                 | 
                Request to use four vehicle equipment parking areas 
                  in Link 4 | 
               
               
                |  
                   #17 
                 | 
                 
                   05/18/11  
                 | 
                 
                  
                 | 
                 
                   Segment 24 
                 | 
                Modification to the driveway at the Encina Substation | 
               
               
                |  
                   #18 
                 | 
                 
                   06/27/11 
                 | 
                 
                  
                 | 
                 
                   Link 1 
                 | 
                Installation of gates along a number of project access 
                  roads in the Jacumba area | 
               
               
                |  
                   #19 
                 | 
                 
                   06/27/11 
                 | 
                 
                  
                 | 
                 
                   Rough Acres Yard  
                 | 
                Temporary installation of a foundation and towers 
                  at the yard site | 
               
               
                |  
                   #20 
                 | 
                 
                   07/11/11 
                 | 
                 
                  
                 | 
                 
                   Link 5 
                 | 
                Modification of a temporary access route to pull 
                  site between CP 48-2 and CP 49-1, 
                  addition of a pull site along the access road between CP 49-1 
                  and CP 50-1 and addition of a site approximately 
                  600 feet south of CP 51-2 to stockpile soil | 
               
               
                |  
                   #21 
                 | 
                 
                   07/07/11 
                 | 
                 
                  
                 | 
                 
                   Link 1 
                 | 
                Permits workspace and access for guarding of facilities 
                  near GS-NF-37 and GS-BLM-4/GS-NF-41 | 
               
               
                |  
                   #22 
                 | 
                 
                   07/15/11 
                 | 
                 
                  
                 | 
                 
                   Link 1 
                 | 
                Requests use of the Fromm construction yard | 
               
               
                |  
                   #23 
                 | 
                 
                   08/15/11 
                 | 
                 
                  
                 | 
                 
                   Links 1, 2, and 5 
                 | 
                Use of landing platforms and tower staging access 
                  pads | 
               
               
                |  
                   #24 
                 | 
                 
                   08/25/11 
                 | 
                 
                  
                 | 
                 
                   Link 3 
                 | 
                Vegetation clearing at the Suncrest Substation for 
                  fire safety | 
               
               
                |  
                   #25 
                 | 
                 
                   09/01/11 
                 | 
                 
                  
                 | 
                 
                   Links 1, 2, and 5 
                 | 
                Prolonged use of previously approved TEWS areas | 
               
               
                |  
                   #26 
                 | 
                 
                   09/16/11 
                 | 
                 
                  
                 | 
                 
                   Link 2 
                 | 
                Tank stand placement adjacent to Barrett Substation | 
               
               
                |  
                   #27 
                 | 
                 
                   09/20/11 
                 | 
                 
                  
                 | 
                 
                   Link 1 
                 | 
                Two extra workspace locations near Mountain Springs 
                  Grade | 
               
               
                |  
                   #28 
                 | 
                 
                   10/31/11 
                 | 
                 
                  
                 | 
                 
                   Link 3 
                 | 
                Request to work during red flag warning days at the 
                  Suncrest Substation | 
               
               
                |  
                   #29 
                 | 
                 
                   10/21/11 
                 | 
                 
                  
                 | 
                 
                   Links 1, 2, and 5 
                 | 
                Guard structure installations | 
               
               
                |  
                   #30 
                 | 
                 
                   11/01/11 
                 | 
                 
                  
                 | 
                 
                   Links 1, 2, and 5 
                 | 
                Temporary parking and turnaround areas | 
               
               
                |  
                   #30 MOD #1 
                 | 
                 
                   02/09/12 
                 | 
                 
                  
                 | 
                 
                   CP 75, Overhead 
                 | 
                Parking area long-lining | 
               
               
                |  
                   #31 
                 | 
                 
                   11/08/11 
                 | 
                 
                   Rescinded 
                 | 
                 
                   Links 1, 2, and 5 
                 | 
                Variance to NTP #13 Condition #37 regarding work 
                  practices during precipitation events | 
               
               
                |  
                   #32 
                 | 
                 
                   11/16/11 
                 | 
                 
                  
                 | 
                 
                   Links 1, 2, and 5 
                 | 
                Guard structure installations and pull site modifications | 
               
               
                |  
                   #33 
                 | 
                 
                   11/28/11 
                 | 
                 
                  
                 | 
                 
                   Links 1, 2, and 5 
                 | 
                Temporary TSAP and pull site modification | 
               
               
                |  
                   #34 
                 | 
                 
                   11/29/11 
                 | 
                 
                  
                 | 
                 
                   Projectwide 
                 | 
                Mitigation Measure B-7h, Eagle Buffers | 
               
               
                |  
                   #35 
                 | 
                 
                   12/22/11 
                 | 
                 
                  
                 | 
                 
                   Link 5 
                 | 
                Modify Access Road to Tower CP59 | 
               
               
                |  
                   #36 
                 | 
                 
                   01/20/12 
                 | 
                 
                  
                 | 
                 
                   Overhead 
                 | 
                Vegetation clearance | 
               
               
                |  
                   #37 
                 | 
                 
                   01/20/12 
                 | 
                 
                  
                 | 
                 
                   Overhead 
                 | 
                Anchor block placement | 
               
               
                |  
                   #37 Clarification 
                 | 
                 
                  
                 | 
                 
                  
                 | 
                 
                  
                 | 
                  | 
               
               
                |  
                   #38 
                 | 
                 
                   02/10/12 
                 | 
                 
                  
                 | 
                 
                   Segment 5 
                 | 
                Install a gate near CP55 | 
               
               
                |  
                   #39 
                 | 
                 
                   02/10/12 
                 | 
                 
                   Rescinded 
                 | 
                 
                   Segment 4A 
                 | 
                Pull-site CP23 restoration | 
               
               
                |  
                   #40 
                 | 
                 
                   03/20/12 
                 | 
                 
                  
                 | 
                 
                   Segment 5 
                 | 
                Use of an area near GS-NF-7 for staging | 
               
               
                |  
                   #41 
                 | 
                 
                   04/17/12 
                 | 
                 
                  
                 | 
                 
                   Segment 5 
                 | 
                Driveway improvements | 
               
               
                |  
                   #42 
                 | 
                 
                   05/09/12 
                 | 
                 
                   Rescinded 05/19/12 
                 | 
                 
                   Links 1, 2, and 5 
                 | 
                 Placement of temporary concrete block anchors outside 
                  of three approved tower work areas | 
               
               
                |  
                   #43 
                 | 
                 
                   09/05/12 
                 | 
                 
                  
                 | 
                 
                   Projectwide 
                 | 
                Leaving in place project improvements at five construction 
                  yards to accomodate landowner requests | 
               
               
                |  
                   #44 
                 | 
                 
                   09/06/12 
                 | 
                 
                  
                 | 
                 
                   Links 4 and 5 
                 | 
                Permanent use of two TSAPs for telecommunications 
                  equipment and designation of temporary TSAP as permanent | 
               
               
                |  
                   #45 
                 | 
                 
                   09/07/13 
                 | 
                 
                  
                 | 
                 
                   Link 1 
                 | 
                Converts temporary access road to permanent | 
               
             
            In July 2010 the U.S. Forest Service's Supplemental 
              Information Report (SIR) acknowledged the Final Environmentally 
              Superior Southern Route as well as changes in the proposed action. 
              On Cleveland National Forest (CNF) lands the USFS evaluated and 
              provided variance review and approval. USFS Variance Requests processed 
              are provided in the table below. 
               
             
               
                |  
                   USFS Variance Approvals 
                 | 
               
               
                |  
                   Date 
                    Issued 
                 | 
                 
                   Segment 
                 | 
                Description | 
               
               
                |  
                  
                 | 
                 
                   USFS lands 
                 | 
                Conduct work until 1:00pm on PAL fire danger days | 
               
               
                |  
                  
                 | 
                 
                   USFS lands 
                 | 
                Work on PAL fire danger days | 
               
               
                |  
                  
                 | 
                 
                   USFS lands 
                 | 
                Work on PAL fire danger days | 
               
               
                |  
                  
                 | 
                 
                   USFS lands 
                 | 
                Work on PAL fire danger days | 
               
               
                |  
                  
                 | 
                 
                   USFS lands 
                 | 
                Work on PAL fire danger days | 
               
               
                |  
                   08/25/11 
                 | 
                 
                   Link 2 
                 | 
                Request for work sites along La Posta Road | 
               
               
                |  
                  
                 | 
                 
                   USFS lands 
                 | 
                Work on PAL fire danger days | 
               
               
                |  
                  
                 | 
                 
                   USFS lands 
                 | 
                Work on PAL fire danger days | 
               
               
                |  
                  
                 | 
                 
                   USFS lands 
                 | 
                Work on PAL fire danger days | 
               
               
                |  
                  
                 | 
                 
                   USFS lands 
                 | 
                Work on PAL fire danger days | 
               
               
                |  
                  
                 | 
                 
                   USFS lands 
                 | 
                Work on PAL fire danger days | 
               
               
                |  
                  
                 | 
                 
                   USFS lands 
                 | 
                Work on PAL fire danger days | 
               
               
                |  
                  
                 | 
                 
                   USFS lands 
                 | 
                Work on PAL fire danger days | 
               
               
                |  
                  
                 | 
                 
                   USFS lands 
                 | 
                Work on PAL fire danger days | 
               
               
                |  
                  
                 | 
                 
                   USFS lands 
                 | 
                Work on PAL fire danger days | 
               
               
                |  
                   10/28/11 
                 | 
                 
                   USFS lands 
                 | 
                Request for work sites, addition of a subcontractor, 
                  and insecticide use | 
               
               
                |  
                  
                 | 
                 
                   USFS lands 
                 | 
                Work on PAL fire danger days | 
               
               
                |  
                  
                 | 
                 
                   USFS lands 
                 | 
                Work on PAL fire danger days | 
               
               
                |  
                  
                 | 
                 
                   USFS lands 
                 | 
                Work on PAL fire danger days | 
               
               
                |  
                   Dec 2011 
                 | 
                 
                   Eagle Buffer areas 
                 | 
                Work in eagle breeding season | 
               
               
                |  
                  
                 | 
                 
                   USFS lands 
                 | 
                Work on PAL fire danger days | 
               
               
                |  
                  
                 | 
                 
                   USFS lands 
                 | 
                Work on PAL fire danger days | 
               
               
                |  
                  
                 | 
                 
                   USFS lands 
                 | 
                Work on PAL fire danger days | 
               
               
                |  
                   01/19/12 
                 | 
                 
                   USFS Lands 
                 | 
                Work on PAL fire danger days | 
               
               
                |  
                  
                 | 
                 
                   USFS lands 
                 | 
                Work on PAL fire danger days | 
               
               
                |  
                   02/02/12 
                 | 
                 
                   USFS lands 
                 | 
                Work on PAL fire danger days | 
               
               
                |  
                   02/08/12 
                 | 
                 
                   USFS lands 
                 | 
                Extension of vegetation clearing, TSAP 
                  and access road revision, temporary work areas, helicopter landing 
                  area, and temporary weather station installation. | 
               
               
                |  
                   02/09/12 
                 | 
                 
                   USFS lands 
                 | 
                Work on PAL fire danger days | 
               
               
                |  
                   02/16/12 
                 | 
                 
                   USFS lands 
                 | 
                Work on PAL fire danger days | 
               
               
                |  
                   02/23/12 
                 | 
                 
                   USFS lands 
                 | 
                Work on PAL fire danger days | 
               
               
                |  
                   03/01/12 
                 | 
                 
                   USFS lands 
                 | 
                Work on PAL fire danger days | 
               
               
                |  
                   03/08/12 
                 | 
                 
                   USFS lands 
                 | 
                Work on PAL fire danger days | 
               
               
                |  
                   03/08/12 
                 | 
                 
                   USFS lands 
                 | 
                Sunday work | 
               
               
                |  
                   03/19/12 
                 | 
                 
                   USFS lands 
                 | 
                Sunday work | 
               
               
                |  
                   03/22/12 
                 | 
                 
                   USFS lands 
                 | 
                Work on PAL fire danger days | 
               
               
                |  
                   03/29/12 
                 | 
                 
                   USFS lands 
                 | 
                Work on PAL fire danger days | 
               
               
                |  
                  
                 | 
                 
                   USFS lands 
                 | 
                Concurrence that Bell Bluff and Thing 
                  Valley golden eagle nests are inactive - permission to enter 
                  buffer areas | 
               
               
                |  
                   04/12/12 
                 | 
                 
                   USFS lands 
                 | 
                Work on PAL fire danger days | 
               
               
                |  
                   04/26/12 
                 | 
                 
                   USFS lands 
                 | 
                Work on PAL fire danger days | 
               
               
                |  
                   05/10/12 
                 | 
                 
                   USFS lands 
                 | 
                Work on PAL fire danger days | 
               
               
                |  
                   05/20/12 
                 | 
                 
                   USFS lands 
                 | 
                Work on PAL fire danger days | 
               
               
                |  
                   05/31/12 
                 | 
                 
                   USFS lands 
                 | 
                Work on PAL fire danger days | 
               
               
                |  
                   06/04/12 
                 | 
                 
                   USFS lands 
                 | 
                Sunday and holiday work | 
               
               
                |  
                   06/07/12 
                 | 
                 
                   USFS lands 
                 | 
                Work on PAL fire danger days | 
               
               
                |  
                   06/14/12 
                 | 
                 
                   USFS lands 
                 | 
                Work on PAL fire danger days | 
               
             
            From time to time, local jurisdictions issued variances from a 
              local ordinance or regulation that it administers. Variance requests 
              processed to date are provided in the table below. 
               
             
               
                |  
                   Other Agency Variance Approvals 
                 | 
               
               
                | Agency | 
                 
                   Variance 
                 | 
                 
                   Date 
                    Requested 
                 | 
                 
                   Date 
                    Issued 
                 | 
                 
                   Segment 
                 | 
                Description | 
               
               
                | County of Imperial | 
                 
                   #1 
                 | 
                 
                   10/06/10 
                 | 
                 
                  
                 | 
                 
                   Link 1 
                 | 
                Extended work hours | 
               
               
                | County of San Diego | 
                 
                   #2 
                 | 
                 
                   03/28/11 
                 | 
                 
                  
                 | 
                 
                   Link 4 
                 | 
                Traffic control permit, Alpine Boulevard | 
               
               
                | County of San Diego | 
                 
                   #3 
                 | 
                 
                   09/30/11 
                 | 
                 
                  
                 | 
                 
                   Various 
                 | 
                Alternative construction work hours and days of work, 
                  Sundays 10/16/11 through 11/27/11 plus Friday 11/25/11 | 
               
               
                | County of San Diego | 
                 
                   #3 
                    amended 
                 | 
                 
                     
                 | 
                 
                  
                 | 
                 
                   Various 
                 | 
                Amendment to variance 3973-11-8-008 
                  (NV) restricting Sunday work at some locations | 
               
               
                | City of San Diego | 
                 
                   #4 
                 | 
                 
                     
                 | 
                 
                  
                 | 
                 
                   Link 5 
                 | 
                Sunday construction at Stonebridge Parkway | 
               
               
                | County of San Diego | 
                 
                   #5 
                 | 
                 
                   02/01/12 
                 | 
                 
                  
                 | 
                 
                   East County locations 
                 | 
                Work on 8 Sundays between 03/25/12 and 05/20/12 | 
               
             
            SDG&E submitted a number of micrositing changes to the approved 
              Project on BLM lands. In response, Determination of NEPA Adequacy 
              (DNA) analyses were conducted. Please see the table below. 
               
             
               
                |  
                   Determinations of NEPA Adequacy 
                 | 
               
               
                |  
                   DNA 
                    Request 
                 | 
                 
                   Date 
                    Requested 
                 | 
                 
                   Date 
                    Issued 
                 | 
                 
                   Segment 
                 | 
                Description | 
               
               
                |  
                   PMR DNA 
                 | 
                 
                  
                 | 
                 
                  
                 | 
                 
                   Projectwide 
                 | 
                PMR modifications (see PMR section 
                  below) | 
               
               
                |  
                   BLM NTP #2 DNA 
                 | 
                 
                  
                 | 
                 
                  
                 | 
                 
                   Links 1, 2, and 5 
                 | 
                Changes submitted and approved under BLM 
                  NTP #2 (19.9MB) | 
               
               
                |  
                   #1 
                 | 
                 
                   06/22/11 
                 | 
                 
                  
                 | 
                 
                   Links 1, 2, and 5 
                 | 
                Micrositing changes to the approved project on BLM 
                  lands | 
               
               
                |  
                   #2 
                 | 
                 
                   10/21/11 
                 | 
                 
                  
                 | 
                 
                   Overhead 
                 | 
                Micrositing | 
               
               
                |  
                   #3 
                 | 
                 
                   02/08/12 
                 | 
                 
                  
                 | 
                 
                   Overhead 
                 | 
                Anchor block micrositing | 
               
               
                |  
                   #4 
                 | 
                 
                   11/09/12 
                 | 
                 
                  
                 | 
                CP60/EP146 | 
                Permanent use of TSAPs and placement of radio communications 
                  facilities | 
               
             
            The following table provides the FAA authorizations granted to 
              SDG&E for use of the sky crane from the project construction 
              yards for tower construction activities. In addition, the CPUC incident 
              response letter to two sky crane related incidents is also provided. 
              On September 27, 2011, the CPUC issued a Stop 
              Work Order affecting project helicopters, pending resolution 
              of issues. On October 4, 2011, the CPUC determined that the 
              issues had been resolved and notified SDG&E 
              that it could resume helicopter operations. 
               
             
            Project 
              Modifications Report  
            Determination: The CPUC and BLM have published the CEQA 
              and NEPA Determination on SDG&E's proposed Project Modifications; 
              the supporting documents are available here. 
              After careful review of the proposed modifications, as documented 
              in the Determination Memorandum and BLM Determination of NEPA Adequacy 
              and in accordance with the CEQA and NEPA requirements, the CPUC 
              and BLM have determined that the changes to the Sunrise Powerlink 
              Project are within the scope of the Certificate of Public Convenience 
              and Necessity and Record of Decision issued by the CPUC and BLM 
              respectively. 
             Background: After the Final Environmentally Superior Southern 
              Route was approved by CPUC in December 2008 and BLM in January of 
              2009, SDG&E began the process of completing final project design 
              and engineering. As is common, some project components were modified 
              as engineering was completed. Modifications result from compliance 
              with adopted mitigation measures requiring resource avoidance to 
              minimize or avoid environmental impacts and final engineering design 
              requirements. In addition, some project components have been relocated 
              to accommodate landowner location preferences where possible in 
              compliance with mitigation requirements. As a part of this process, 
              SDG&E has been working with landowners regarding project components 
              and transmission line routes within their properties. 
             On January 22, 2010, SDG&E submitted to CPUC and BLM an internal 
              administrative draft of its Project Modification Report (PMR) that 
              defined changes made to the project along the entire route after 
              publication of the Final EIR/EIS. The document explained the reason 
              for each change, and presented the comparative environmental impacts 
              of the project components analyzed in the Final EIR/EIS and those 
              presented in the PMR. All changes included in the report were reviewed 
              by the lead agencies, CPUC and BLM, along with the cooperating, 
              responsible and resource agencies. The CPUC compiled and submitted 
              comments to SDG&E from the EIR/EIS Team and other agencies to 
              ensure that the PMR document included sufficient information to 
              make a determination for each reroute. SDG&E has since incorporated 
              comments, conclusions, and made required changes. 
             On May 14, 2010, SDG&E submitted to CPUC and BLM a final Project 
              Modifications Report that defines changes made to the project 
              along the entire route after publication of the Final EIR/EIS. Similar 
              to the administrative draft PMR, the final PMR document explains 
              the reason for each change, and presents the comparative environmental 
              impacts of the project components analyzed in the Final EIR/EIS 
              and those presented in the PMR. The final PMR document is found 
              here. 
             The CPUC accepted public comments on the Final PMR from May 14 
              to June 7, 2010, and reviewed all comments while evaluating 
              the proposed modifications. 
             Final EIR/EIS 
            The Final EIR/EIS was released to the public on October 13, 
              2008. The Final EIR/EIS is available here 
              and is also available at numerous area libraries 
              and government offices. Copies of the Executive Summary of the 
              Final EIR/EIS along with a DVD of the complete document may be requested. 
              CPUC and BLM also have a limited number of copies of the complete 
              four-volume Final EIR/EIS document available to the public. Requests 
              for documents should be made to the CPUC. Contact information appears 
              at the end of this page. 
            The Notice of Availability provides 
              further information on the approval processes for CPUC and BLM. 
              Pursuant to NEPA requirements, the Final EIR/EIS and Proposed Land 
              Use Plan Amendment will be available for review for 30 calendar 
              days from the date the Environmental Protection Agency (EPA) publishes 
              the Notice of Availability (NOA) in the Federal Register, which 
              is expected to occur on October 17, 2008. The review period 
              would end on November 15, 2008. 
             
            Copies of the Executive Summary of the Final EIR/EIS along with 
              a DVD of the complete document may be requested. CPUC and BLM also 
              have a limited number of copies of the complete four-volume Final 
              EIR/EIS document available to the public. Requests for documents 
              should be made to the CPUC. Contact information appears at the end 
              of this page. 
            Draft 
              EIR/EIS 
             CPUC and BLM published the Draft EIR/EIS in January 2008. Please 
              note that the Final EIR/EIS (described above) includes the entire 
              text of the Draft EIR/EIS, modified where necessary in response 
              to comments on the Draft EIR/EIS. The original text of the Draft 
              EIR/EIS document is available here. 
            EIR/EIS 
              Alternatives 
            Throughout 2007, CPUC and BLM gathered information on alternatives 
              to the proposed Sunrise Powerlink Project through an extensive public 
              involvement process. Information and documents from that process 
              are available here. 
            Documents 
              Available 
            In addition to the EIR/EIS, other documents that were published 
              during the CEQA and NEPA processes are available here. 
              Documents and letters that were compiled following publication of 
              the Final EIR/EIS, such as SDG&E Biological Assessment, USFWS 
              Biological Opinion, BLM Section 106 Programmatic Agreement, and 
              appeals to the BLM Interior Board of Land Appeals, are also included. 
             
            In response to concerns from the Lakeside community, a fact sheet 
              that summarizes past public notification and consideration of alternative 
              routes in the community of Lakeside is available here 
              (posted February 24, 2009). A similar fact sheet on public 
              notification was prepared for the Town of Alpine in January 2010 
              and is available here. 
            
            Data 
              Requests 
            The EIR/EIS Team submits Data Requests to SDG&E and other entities 
              when it needs specific information to support EIR/EIS preparation. 
              These requests are available here at 
              the time they are issued. 
            Requests for 
              Technical Information Related to the Draft EIR/EIS 
            During the 90-day public comment period on the Draft EIR/EIS, various 
              parties submitted requests for technical information related to 
              that document. The information provided is available here. 
             
            For 
              Additional Information 
            The CPUC's Project Manager is: 
            Billie Blanchard, CPUC Project Manager 
              California Public Utilities Commission 
              505 Van Ness Avenue 
              San Francisco CA 94102 
              Tel. (415) 703-2068 
              Fax (415) 703-2200 
              Email:  bcb@cpuc.ca.gov
             
           |