             Welcome to the California Public Utilities Commission (CPUC) website 
              for the California Environmental Quality Act (CEQA) review of the 
              proposed Sunrise Powerlink Transmission Line Project. Applications 
              for this project were submitted to the CPUC on December 14, 
              2005 (A.05-12-014) and August 4, 2006 (A.06-08-010). This site 
              provides access to public documents and information relevant to 
              the CEQA and National Environmental Policy Act (NEPA) review processes. 
             Background 
            SDG&E has filed an application with the CPUC to construct the 
              Sunrise Powerlink Project (SRPL). The CPUC is the CEQA lead agency 
              and the U.S. Bureau of Land Management (BLM) is the lead agency 
              under NEPA. The CPUC and BLM are preparing an Environmental Impact 
              Report (EIR, under CEQA) and an Environmental Impact Statement (EIS, 
              under NEPA), which will be published as a single joint document, 
              an EIR/EIS. 
            This project was approved by the California Independent System 
              Operator on August 3, 2006. The Proponent's Environmental Assessment 
              was filed with the CPUC on August 4, 2006 and is available 
              on SDG&E's 
              project website. 
            The CPUC maintains other web pages for documents related to its 
              proceeding on the SRPL, where it makes available documents filed 
              by parties to that proceeding. The web page for Application A.06-08-010 
              incorporates the earlier filing, and lists documents and rulings 
              filed in the proceedings. The CPUC also maintains a page of general 
              information on the SRPL project. 
            The SRPL Project, as proposed by SDG&E, includes a new, approximately 
              90-mile, 500 kV line from Imperial Valley Substation (in Imperial 
              County, near the City of El Centro) to a new Central East Substation 
              (in central San Diego County, south of the intersection of County 
              Highways S22 and S2). The 500 kV portion would 
              approximately follow the eastern boundary of BLM lands west of El 
              Centro and SR 78, and would pass through Anza-Borrego Desert 
              State Park. 
            The SRPL Project also proposes approximately 60 miles of 230 kV 
              transmission lines from the new Central East Substation to SDG&E's 
              existing Peñasquitos Substation (in the City of San 
              Diego). SDG&E proposes to construct two segments underground 
              (one segment south of Ramona and another in the community of Ranchos 
              Peñasquitos, San Diego). Figure 1 
              shows an overview of the proposed project route. 
            Draft EIR/EIS 
            The Draft EIR/EIS was released to the public on January 3, 
              2008. It is available here and is also 
              available for review at numerous area libraries 
              and government offices. 
            Copies of the Executive Summary of the Draft EIR/EIS along with 
              a DVD of the complete document may be requested. The CPUC and BLM 
              also have a limited number of copies of the complete six-volume 
              Draft EIR/EIS document available to the public. Requests for documents 
              should be made to (866) 711-3106 (phone or fax) or via e-mail to 
              sunrise@aspeneg.com. 
            Resumen en Español. Un resumen del borrador Informe 
              de Impacto Ambiental/Declaración de Impacto Ambiental en 
              español está disponible aquí. 
            Submitting Comments on the Draft EIR/EIS. Written comments 
              on the Draft EIR/EIS must be postmarked or received by fax or e-mail 
              no later than April 11, 2008. Please be sure to include your name, 
              address, and telephone number. Written comments on the Draft EIR/EIS 
              should be sent to: 
            CPUC/BLM 
              c/o Aspen Environmental Group 
              235 Montgomery Street, Suite 935 
              San Francisco, CA 94104 
              Fax: (866) 711-3106 
              Email:  sunrise@aspeneg.com 
 
            Informational Workshops. The CPUC and BLM held 9 informational 
              workshops during the week of January 28, 2008. These informal 
              workshops provided an opportunity to speak with the specialists 
              who wrote the Draft EIR/EIS and ask questions. While written comments 
              could be submitted during these workshops, there were no facilities 
              to record oral comments. 
            Public Participation Hearings. The Public 
              Participation Hearings will be held on the dates listed in the 
              table below to receive oral and written comments from interested 
              parties. CPUC Administrative Law Judge Steven Weissman will conduct 
              the Public Participation Hearings, and receive comments on the Draft 
              EIR/EIS and any other issues of concern related to the SDG&E 
              CPCN application. These oral comments will be recorded and entered 
              into the public record.  
             
            
               
                   
                   Table 1. 
                    Sunrise Powerlink Draft EIR/EIS Public Workshops & Public 
                    Participation Hearings 
                      
                 | 
               
               
                 
                    
                    LOCATION AND TELEPHONE 
                      
                 | 
                 
                    
                    DATE AND TIME 
                      
                 | 
               
               
                 
                    
                    Public Participation Hearings  
                    (to make oral comments on the Draft EIR/EIS) 
                      
                 | 
               
               
                |  
                   Downtown San Diego 
                    San Diego County Administration Center 
                    Board of Supervisors Chamber 
                    1600 Pacific Coast Highway,  San Diego, CA 92101 
                    858-694-3900  
                 | 
                 
                   Monday, February 25 
                    1:30 p.m. 
                 | 
               
               
                |  
                   Pine Valley 
                     Mountain Empire High School, Gymnasium  
                    3305 Buckman Springs Road, Pine Valley, CA 91962 
                    619-473-8601 
                 | 
                 
                   Monday, February 25 
                    6:30 p.m. 
                 | 
               
               
                |  
                   Borrego Springs 
                    Borrego Springs Resort, De Anza Room 
                    1112 Tilting T Drive, Borrego Springs, CA 92004 
                    760-767-5700 
                 | 
                 
                   Tuesday, February 26 
                    1:00 p.m. 
                 | 
               
               
                |  
                   Ramona 
                    Charles Nunn Performing Arts Center 
                    1520 Hanson Lane, Ramona, CA 92065 
                    760-787-2000 (Ramona School District) 
                 | 
                 
                   Tuesday, February 26 
                    7:00 p.m. 
                 | 
               
               
                |  
                   Julian 
                    Julian Town Hall 
                    2129 Main Street, Julian, CA 92036 
                    760-765-1857 
                 | 
                 
                   Wednesday, February 27 
                    10:30 a.m. 
                 | 
               
               
                 
                    
                    Workshops on Draft EIR/EIS 
                      
                 | 
               
               
                |  
                   El 
                    Centro 
                    CALWorks, Meeting Rooms B & C 
                    2995 S. 4th Street, El Centro, CA 92243 
                    760-336-4030 
                 | 
                 
                   Monday, 
                    January 28 
                    12:30 to 2:30 p.m. 
                    Presentation: 12:40 to 12:55 
                 | 
               
               
                |  
                   Alpine 
                     
                    Alpine Community Center, Sage Room 
                    1830 Alpine Boulevard, Alpine, CA 91901 
                    619-445-7330 
                 | 
                 
                   Monday, 
                    January 28 
                    7:00 to 9:00 p.m. 
                    Presentation: 7:10 to 7:25 
                 | 
               
               
                |  
                   Temecula 
                    Community Recreation Center, Multipurpose Room 
                    30875 Rancho Vista Road, Temecula, CA 92592 
                    951-694-6410 
                 | 
                 
                   Tuesday, January 29 
                    1:00 to 3:00 p.m. 
                    Presentation: 1:10 to 1:25 
                 | 
               
               
                |  
                   San Diego-Rancho Peñasquitos 
                    Hilltop Recreation Center 
                    9711 Oviedo Way, San Diego, CA 92129 
                    858-538-8198 
                 | 
                 
                   Tuesday, January 29 
                    7:00 to 9:00 p.m. 
                    Presentation: 7:10 to 7:25 
                 | 
               
               
                |  
                   Ramona 
                    Ramona Community Center 
                    434 Aqua Lane, Ramona, CA 92065 
                    760-789-0999 
                 | 
                 
                   Wednesday, January 30 
                    2:00 to 4:00 p.m. 
                    Presentation: 2:10 to 2:25 
                 | 
               
               
                |  
                   Warner Springs 
                    Warner School Cafeteria 
                    30951 Highway 79, Warner Springs, CA 92086 
                    760-782-3517 
                 | 
                 
                   Wednesday, January 30 
                    7:00 to 9:00 p.m. 
                    Presentation: 7:10 to 7:25 
                 | 
               
               
                |  
                   Pine Valley 
                     Mountain Empire High School, Gymnasium 
                    3305 Buckman Springs Road, Pine Valley, CA 91962 
                    619-473-8601 
                 | 
                 
                   Thursday, January 31 
                    3:30 to 5:30 p.m. and 7:00 to 9:00 p.m. 
                    Presentations: 3:40 and 7:10. 
                 | 
               
               
                |  
                   Borrego Springs 
                    Borrego Springs High School, Community Room 
                    2281 Diegueño Road, Borrego Springs, CA 92004 
                    760-767-5357 
                 | 
                 
                   Friday, February 1 
                    1:00 to 4:00 p.m. 
                    Presentation: 1:10 to 1:25 
                 | 
               
             
            EIR/EIS Alternatives 
            Throughout 2007, the CPUC and BLM gathered information on alternatives 
              to the proposed Sunrise Powerlink Project through an extensive public 
              involvement process. Information and documents from that process 
              are available here. 
            Documents Available 
            In addition to the EIR/EIS, other documents that were published 
              during the CEQA and NEPA processes are available here. 
            Data Requests 
            The EIR/EIS Team submits Data Requests to SDG&E and other entities 
              when it needs specific information to support EIR/EIS preparation. 
              These requests are available here at 
              the time they are issued. 
            For Additional Information 
            To request additional information or to be added to the mailing 
              list, please contact us by email, fax, or phone, as follows: 
            
            The CPUC's Project Manager is: 
            Billie Blanchard, CPUC Project Manager 
              California Public Utilities Commission 
              505 Van Ness Avenue 
              San Francisco CA 94102 
              Tel. (415) 703-2068 
              Fax (415) 703-2200 
              Email:  bcb@cpuc.ca.gov 
           |