|  
             Welcome to the California Public Utilities Commission (CPUC) website 
              for the California Environmental Quality Act (CEQA) review of the 
              proposed Sunrise Powerlink Transmission Line Project. Applications 
              for this project were submitted to CPUC on December 14, 2005 
              (A.05-12-014) and August 4, 2006 (A.06-08-010). The Proponent's 
              Environmental Assessment was filed with the CPUC on August 4, 
              2006 and is available on SDG&E's 
              project website. This project was approved by the California 
              Independent System Operator on August 3, 2006. This site provides 
              access to public documents and information relevant to the CEQA 
              and National Environmental Policy Act (NEPA) review processes. The 
              CPUC voted on December 18, 2008 to approve the Final Environmentally 
              Superior Southern Route (see Decision D.08-12-058) 
              and a Notice of Determination was 
              submitted to the State Clearinghouse. The Bureau of Land Management 
              (BLM) issued a Record of Decision approving 
              the same route on January 20, 2009. 
             Project Modifications Report
             After the Final Environmentally Superior Southern Route was approved 
              by CPUC in December 2008 and BLM in January of 2009, SDG&E began 
              the process of completing final project design and engineering. 
              As is common, some project components were modified as engineering 
              was completed. Modifications result from engineering design requirements, 
              and also from compliance with mitigation measures requiring resource 
              avoidance to minimize or avoid environmental impacts. In addition, 
              some project components have been relocated to accommodate landowner 
              location preferences where possible in compliance with mitigation 
              requirements. As a part of this process, SDG&E has been working 
              with landowners regarding project components and transmission line 
              routes within their properties. 
             On January 22, 2010, SDG&E submitted to CPUC and BLM an internal 
              administrative draft of its Project Modification Report (PMR) that 
              defined changes made to the project along the entire route after 
              publication of the Final EIR/EIS. The document explained the reason 
              for each change, and presented the comparative environmental impacts 
              of the project components analyzed in the Final EIR/EIS and those 
              presented in the PMR. All changes included in the report were reviewed 
              by the lead agencies, CPUC and BLM, along with the cooperating, 
              responsible and resource agencies. The CPUC compiled and submitted 
              comments to SDG&E from the EIR/EIS Team and other agencies to 
              ensure that the PMR document included sufficient information to 
              make a determination for each reroute. SDG&E has since incorporated 
              comments, conclusions, and made required changes. 
             On May 14, 2010, SDG&E submitted to CPUC and BLM a final Project 
              Modifications Report that defines changes made to the project 
              along the entire route after publication of the Final EIR/EIS. Similar 
              to the administrative draft PMR, the final PMR document explains 
              the reason for each change, and presents the comparative environmental 
              impacts of the project components analyzed in the Final EIR/EIS 
              and those presented in the PMR. The final PMR document is found 
              here. 
             All changes included in the final PMR will also be reviewed by 
              the lead agencies, CPUC and BLM, along with the cooperating, responsible 
              and resource agencies. These agencies will carefully evaluate each 
              proposed modification to ensure compliance with CEQA and NEPA. 
             An agency memorandum will be prepared by CPUC and BLM to document 
              the changes presented in the final PMR document and to determine 
              whether additional CEQA/NEPA review is required. All project-related 
              activities will be properly analyzed in compliance with CEQA and 
              NEPA. These activities are properly regulated in accordance with 
              the CPUC's transmission siting authority. An explanation of the 
              CPUC's determination regarding CEQA compliance will be posted on 
              this project website. 
             Written comments on the final PMR may be sent to: 
              
             
              
                
                  CPUC/BLM 
                    c/o Aspen Environmental Group 
                    235 Montgomery Street, Suite 935 
                    San Francisco, CA 94104 
                    Fax: (866) 711-3106 
                    Email: sunrise@aspeneg.com 
                 | 
               
             
            Please submit any written comments on the final PMR document so 
              that they are postmarked or received by fax or email no later than 
              Tuesday June 1, 2010. Please be sure to include your 
              name, address, and telephone number.  
            Construction Progress and Mitigation 
              Monitoring  
            Construction is scheduled to begin in April/May 2010 with the establishment 
              of some construction yards and existing substation upgrades. Notices 
              to Proceed (NTPs) will be issued by the CPUC for each of these activities. 
              The majority of construction is expected to start in June/July 2010 
              once the CPUC issues NTPs for each segment. Issuance of NTPs will 
              be contingent upon SDG&E compliance with pre-construction requirements 
              as specified by the approved mitigation measures and responsible 
              agency permitting requirements. Approved pre-compliance reports, 
              permit applications, and other documents are available in their 
              final form here. NTPs that have been 
              issued to SDG&E are available in their final form here.
             SDG&E is constructing the Sunrise Powerlink Project in 25 segments, 
              as follows: 
               
             
               
                | Segment | 
                Description | 
                Type | 
                Status | 
               
               
                | Segment 1 | 
                Imperial Valley Substation | 
                Substation Upgrades | 
                NTP request not yet submitted1 | 
               
               
                | Segment 2 | 
                Imperial Valley Substation to Pyramid Mining 
                  (MP0 to MP19.2)  | 
                500 kV Overhead | 
                NTP request not yet submitted1 | 
               
               
                | Segment 3 | 
                Pyramid Mining to Mountain Springs Grade (MP19.2 
                  to MP23.2)  | 
                500 kV Overhead | 
                NTP request not yet submitted1 | 
               
               
                | Segment 4 | 
                Mountain Springs Grade to Jade (MP23.2 to 
                  MP30.3)  | 
                500 kV Overhead | 
                NTP request not yet submitted1 | 
               
               
                | Segment 5 | 
                Jade to I-8 (McCain Valley) (MP30.3 to MP39.7) 
                   | 
                500 kV Overhead | 
                NTP request not yet submitted1 | 
               
               
                | Segment 6 | 
                I-8 (McCain Valley) to USFS (MP39.7 to MP52.5) 
                   | 
                500 kV Overhead | 
                NTP request not yet submitted1 | 
               
               
                | Segment 7 | 
                USFS East (MP52.5 to MP61.3)  | 
                500 kV Overhead | 
                NTP request not yet submitted1 | 
               
               
                | Segment 8 | 
                USFS East to Cameron Substation (MP61.3 to 
                  MP65.4)  | 
                500 kV Overhead | 
                NTP request not yet submitted1 | 
               
               
                | Segment 9 | 
                MP65.4 to MP70.9 | 
                500 kV Overhead | 
                NTP request not yet submitted1 | 
               
               
                | Segment 10 | 
                MP70.9 to MP74.8 | 
                500 kV Overhead | 
                NTP request not yet submitted1 | 
               
               
                | Segment 11 | 
                MP74.8 to MP77.6 | 
                500 kV Overhead | 
                NTP request not yet submitted1 | 
               
               
                | Segment 12 | 
                MP77.6 to MP90.0 | 
                500 kV Overhead | 
                NTP request not yet submitted1 | 
               
               
                | Segment 13 | 
                Suncrest Substation (Modified Route D Substation) | 
                New 500/230 kV Substation | 
                NTP request not yet submitted1 | 
               
               
                | Segment 14 | 
                Suncrest Substation to Alpine Boulevard (MP90.0 
                  to MP92.8)  | 
                230 kV Overhead | 
                NTP request not yet submitted1 | 
               
               
                | Segment 15 | 
                Alpine Boulevard Underground (MP92.8 to MP99.0) 
                   | 
                230 kV Underground | 
                NTP request not yet submitted1 | 
               
               
                | Segment 16 | 
                Peutz Valley to El Monte Valley (MP99.0 to 
                  MP105.5)  | 
                230 kV Overhead | 
                NTP request not yet submitted1 | 
               
               
                | Segment 17 | 
                El Monte Valley to Highway 67 (MP105.5 to 
                  MP112.7)  | 
                230 kV Overhead | 
                NTP request not yet submitted1 | 
               
               
                | Segment 18 | 
                Highway 67 to Sycamore Canyon Substation (MP112.7 
                  to MP118.1)   | 
                230 kV Overhead | 
                NTP request not yet submitted1 | 
               
               
                | Segment 19 | 
                Sycamore Canyon Substation | 
                Substation Upgrades 
                 | NTP request not yet submitted1 
               |  
               
                | Segment 20 | 
                Sycamore to Elliot 69 kV Reconductor | 
                69 kV Reconductoring | 
                NTP request not yet submitted1 | 
               
               
                | Segment 21 | 
                Sycamore to Scripps 69 kV Reconductor | 
                69 kV Reconductoring | 
                NTP request not yet submitted1 | 
               
               
                | Segment 22 | 
                Sycamore to Pomerado 69 kV Reconductor | 
                69 kV Reconductoring | 
                NTP request not yet submitted1 | 
               
               
                | Segment 23 | 
                South Bay Substation Upgrades | 
                Substation Upgrades | 
                NTP 
                  #2 issued 4/29/10 | 
               
               
                | Segment 24 | 
                Encina Substation Upgrades | 
                Substation Upgrades | 
                NTP request not yet submitted1 | 
               
               
                | Segment 25 | 
                San Luis Rey Substation Upgrades | 
                Substation Upgrades | 
                NTP 
                  #1 issued 4/28/10 | 
               
               
                |  
                   Construction Yards and Other Workspace 
                 | 
               
               
                | Alpine Yard 18, Town of Alpine | 
                Construction Yard | 
                NTP 
                  #3 issued 5/20/10 | 
               
               
                | Alpine Yard 18A, Town of Alpine | 
                Construction Yard | 
                NTP request submitted2 | 
               
               
                | Rough Acres Phase I Yard, 
                  Boulevard area, San Diego County | 
                Construction Yard | 
                NTP request submitted2 | 
               
             
            1 - No NTP request submitted as of May 20, 2010. 
            2 - No NTP issued by CPUC as of May 20, 2010.  
            The CPUC, in conjunction with SDG&E, BLM, USFS and other Responsible 
              Agencies, drafted a Mitigation Monitoring Compliance and Reporting 
              Program (MMCRP) to ensure compliance with mitigation measures approved 
              in the Final EIR/EIS, as well as with the terms and conditions associated 
              with the BLM right-of-way. Although changes may be made to the document 
              as construction progresses, a current final version of the MMCRP 
              document and attachments, including a map 
              of the approved route with segments, is found here. 
             A CPUC Environmental Monitor will be monitoring construction activities 
              to ensure that they are conducted in accordance with the approved 
              mitigation measures and permit conditions. Once construction begins, 
              this site will hold all weekly reports documenting this monitoring 
              activity. Reports on construction status and activities are posted 
              here. 
            Final EIR/EIS 
            The Final EIR/EIS was released to the public on October 13, 
              2008. The Final EIR/EIS is available here 
              and is also available at numerous area libraries 
              and government offices. Copies of the Executive Summary of the 
              Final EIR/EIS along with a DVD of the complete document may be requested. 
              CPUC and BLM also have a limited number of copies of the complete 
              four-volume Final EIR/EIS document available to the public. Requests 
              for documents should be made to (866) 711-3106 (phone or fax) or 
              via email to sunrise@aspeneg.com. 
            The Notice of Availability provides 
              further information on the approval processes for CPUC and BLM. 
              Pursuant to NEPA requirements, the Final EIR/EIS and Proposed Land 
              Use Plan Amendment will be available for review for 30 calendar 
              days from the date the Environmental Protection Agency (EPA) publishes 
              the Notice of Availability (NOA) in the Federal Register, which 
              is expected to occur on October 17, 2008. The review period 
              would end on November 15, 2008. 
             
            Copies of the Executive Summary of the Final EIR/EIS along with 
              a DVD of the complete document may be requested. CPUC and BLM also 
              have a limited number of copies of the complete four-volume Final 
              EIR/EIS document available to the public. Requests for documents 
              should be made to (866) 711-3106 (phone or fax) or via email to 
              sunrise@aspeneg.com. 
            Draft EIR/EIS 
             CPUC and BLM published the Draft EIR/EIS in January 2008. Please 
              note that the Final EIR/EIS (described above) includes the entire 
              text of the Draft EIR/EIS, modified where necessary in response 
              to comments on the Draft EIR/EIS. The original text of the Draft 
              EIR/EIS document is available here. 
            EIR/EIS Alternatives 
            Throughout 2007, CPUC and BLM gathered information on alternatives 
              to the proposed Sunrise Powerlink Project through an extensive public 
              involvement process. Information and documents from that process 
              are available here. 
            Documents Available 
            In addition to the EIR/EIS, other documents that were published 
              during the CEQA and NEPA processes are available here. 
              Documents and letters that were compiled following publication of 
              the Final EIR/EIS, such as SDG&E Biological Assessment, USFWS 
              Biological Opinion, BLM Section 106 Programmatic Agreement, and 
              appeals to the BLM Interior Board of Land Appeals, are also included. 
             
            In response to concerns from the Lakeside community, a fact sheet 
              that summarizes past public notification and consideration of alternative 
              routes in the community of Lakeside is available here 
              (posted February 24, 2009). A similar fact sheet on public 
              notification was prepared for the Town of Alpine in January 2010 
              and is available here. 
            
            Data Requests 
            The EIR/EIS Team submits Data Requests to SDG&E and other entities 
              when it needs specific information to support EIR/EIS preparation. 
              These requests are available here at 
              the time they are issued. 
            Requests for Technical Information 
              Related to the Draft EIR/EIS 
            During the 90-day public comment period on the Draft EIR/EIS, various 
              parties submitted requests for technical information related to 
              that document. The information provided has available here. 
             
            For Additional Information 
            To request additional information or to be added to the mailing 
              list, please contact us by email, fax, or phone, as follows: 
            
            The CPUC's Project Manager is: 
            Billie Blanchard, CPUC Project Manager 
              California Public Utilities Commission 
              505 Van Ness Avenue 
              San Francisco CA 94102 
              Tel. (415) 703-2068 
              Fax (415) 703-2200 
              Email:  bcb@cpuc.ca.gov
             
           |