|
|
STATE OF CALIFORNIA
|
![]() |
These files are in Portable Document Format (PDF). To view them, you will need to download the free Adobe Acrobat Reader if it is not already installed on your PC. Note: For best results in displaying the largest files (see sizes shown in parentheses below for files larger than 5 MB), right-click the file's link, click "Save Target As" to download the file to a folder on your hard drive, then browse to that folder and double-click the downloaded file to open it in Acrobat. |
|
This page was last updated: May 2026
The proposed Project will be reviewed under the California Environmental Quality Act (CEQA). The CPUC will prepare a CEQA environmental document as the CEQA lead agency. This website provides access to public documents and information relevant to the CEQA environmental review process. An overview of the proposed Project is provided below: CPUC Review Process Following receipt of a complete application, the California Public Utilities Commission (CPUC) conducts two parallel processes when considering development proposed by a regulated utility: (1) an application process, in which the CPUC reviews the utility’s proposal and considers whether the project is needed and is in the public interest; and (2) an environmental review process pursuant to CEQA. Under CPUC General Order (GO) 131-E, which supersedes GO 131-D, proposed project proponents that require a Permit to Construct (PTC) from the CPUC may now elect to prepare a draft version of a negative declaration, mitigated negative declaration, EIR, addendum or analysis on the applicability of an exemption from CEQA in lieu of a PEA. Click here for more information about the CPUC’s decision and review process. Click here for information and documents associated with the CPUC’s proceedings for the Project.
Introduction and Background SDG&E, in its CPUC application (A.26-05-005) filed on May 8, 2026, requests a PTC for the Suncrest 230 kV Loop-In Project (Project). The CPUC conducts an efficient and thorough Environmental Review process under GO 131-E. The CPUC's GO 131-E outlines rules for the permitting and construction of electrical transmission lines, power lines, distribution lines, substations, and electric generation facilities in California. The Project would consist of construction of an approximately 14.5-mile-long, double-circuit 230 kV transmission line consisting of overhead and underground segments to interconnect SDG&E’s existing Transmission Line (TL) 23021 into the existing Suncrest Substation. The proposed 230 kV transmission line would create a loop for system reliability. The Project would also include modifications to the existing Suncrest Substation, including (1) installation of a 500/230 kV transformer bank and associated tertiary reactors, circuit breakers, disconnects, and communication equipment and (2) construction of a 230 kV bay to accommodate the loop-in of TL 23021 to the existing Suncrest Substation. The Proposed Project would cross unincorporated communities within San Diego County, California, including Crest and Harbison Canyon. Figure 1 shows the proposed route. The California Independent System Operator (CAISO) 2022-2023 Transmission Plan identified the need for the Proposed Project to upgrade the California electric grid to accommodate load growth. The Proposed Project would:
Environmental Review As the CEQA Lead Agency, the CPUC will prepare an Environment Impact Report (EIR) to evaluate the environmental effects of the Proposed Project. The following table includes milestones and anticipated dates for the CEQA review process.
Documents Available for Review Public documents related to the Project and Draft EIR for the Suncrest 230 kV Loop-In Project can be found here: SDG&E Project Application (May 8, 2026) Proponent’s Administrative Draft Version of an EIR (May 8, 2026) For Additional Information The CPUC Energy Division is managing the environmental review of the Project. The CPUC's Project Manager is: Tharon Wright
California Public Utilities Commission Energy Division, CEQA and Energy Permitting Section 300 Capitol Mall, Suite 500 Sacramento, CA 95814 Email: tharon.wright@cpuc.ca.gov |
|||||||||||
|
This page contains tables and is best viewed with Firefox or Internet Explorer. Please report any problems to the Energy Division web coordinator. |
|||||||||||
|
Project Home Page - CPUC
Environmental Information - CPUC Home
|
|||||||||||