CPUC Request 
             
             | 
            LSPGC Response 
             | 
            Response Attachments 
             | 
          
          
              
                
                
                
                
              CPUC Deficiency Review #1 (August 28, 2024)  | 
            LSPGC Response #1 to Deficiency Report #1 (September 30, 2024) 
           | 
            Attachment A: PG&E Preliminary Scope 
Attachment B: PG&E Substation Locations (Confidential Data Witheld) 
            Attachment C: Vegetation Clearance Table 
Attachment D: Ultimate Substation Buildout GIS Files (Confidential Data Withheld) 
            Attachment E: FAA Determinations 
Attachment F: Substation Grading GIS Files (Confidential Data Withheld) 
Attachment G: Montezuma Gas Pipeline KMZ (Confidential Data Withheld) 
            Attachment H: High Resolution Images 
            Attachment I: O&M Trim Information 
            Attachment J: Revised Noise and Vibration Impact Assessment 
            Attachment K: Transition Structure Lighting Example 
            Attachment L: Revised Figure 3-4 | 
          
          
            LSPGC Response #2 (October 18, 2024) 
             | 
            Aquatic Resources Technical Report 
             | 
          
          
            LSPGC Response #3 (October 31, 2024) 
             | 
            Attachment A: Revised Visual Resources Technical Report (including updated simulations and high resolution photos) 
            Attachment B: Collinsville Substation Health Risk Assessment 
Attachment C: Updated Cultural Resources Technical Report, including GIS data (Confidential Data Withheld) 
            Attachment D: Substation Fence and Driveway Profile Diagram and Fencing Information 
             | 
          
          
            LSPGC Response #4 (November 15, 2024) 
             | 
            DOD Clearinghouse Response Letter 
            Sediment Dispersion Modeling 
             | 
          
          
            | LSPGC Response #5 (January  30, 2025) | 
            Attachment A: Geotechnical Factual Report 
              Attachment B: Collinsville to Pittsburg Submarine Cable Sedbed Morpohology Analysis 
              Deficiency and Data Request Tracker | 
          
          
            | LSPGC Response #6 (July 8, 2025) | 
            Attachment A: Collinsville-Pittsburg 230kV - DRAFT_Collinsville Onshore Geotech Report-1 July 2025 
            Attachment B: NA245123 500 kV Collinsville Substation Geotechnical Engineering Report DRAFT | 
          
          
            | CPUC Deficiency Review #2 (November 14, 2024) | 
            LSPGC Response #1 (December 4, 2024)
  | 
            Attachment DR 1a: Collinsville_Project_Components_EditedLSP_12-02-2024 (Confidential Data Withheld) 
              Attachment DR 1b: Collinsville_Project_Components_EditedLSP_12-17-2024 (Confidential Data Withheld) | 
          
          
            | LSPGC Response #2 (December 23, 2024) | 
            Attachment DR-2a:_Updated Table 3-8 and Table 3-9 
              Attachment DR-2c:_Grading Elevations 
              Attachment DR-6:_Revised AQ Tables | 
          
          
            CPUC Data Request #1 (December 4, 2024) 
               | 
            LSPGC Response #1 (January 3, 2025) 
               | 
             
               | 
          
          
            | LSPGC Response #2 (February 19, 2025) | 
            Attachment A: Wire Frame Diagram 
              Attachment B: Updated Visual Simulation 
              Attachment C: Updated HRA | 
          
          
            | CPUC Data Request #2 (March 7, 2025) | 
            LSPGC Response #1 (March 18, 2025) | 
            Revised CV Vis Sim_V2 - Plaza Marina 20250314S 
              Revised CV Vis Sim_V3 - Collinsville Road 20250318S 
              Revised CV Vis Sim_V3 - Stratton Lane 20250318S 
              Reducing Avian Collisions with Powerlines 
              Suggested Practices for Avian Protection On Power Lines: The State of the Art in 2006 
              LSP_2023_Bathymetry (Confidential Data Withheld) 
              PG&E Transposition Structures_Update_031325 (Confidential Data Withheld) 
              Updated Figure 2-6 Proposed LSPGC Collinsville Substation Grading Plan 
              Updated Figure 2-12 Diagram of Typical Underground Duct Bank | 
          
          
            | LSPGC Response #2 (March 20, 2025) | 
            Active Mining Lease (Confidential Data Withheld) 
              USACE Channels (Confidential Data Withheld) | 
          
          
            | LSPGC Response #3 (April 2, 2025) | 
            Attachment A: Submarine Depths (Confidential Data Withheld) 
              Attachment B: Land Use GIS (Confidential Data Withheld) 
              Attachment C: Alternative Substation Site Analysis (Confidential Data Withheld) 
              Attachment D: Landing Location Selection (Confidential Data Withheld) 
              Attachment E: Land Ownership Parcel Data (Confidential Data Withheld) 
              Attachment F: Submarine Installation Methods (Confidential Data Withheld) | 
          
          
            | PG&E Response #1 (March 7, 2025) | 
              | 
          
          
            | CPUC Data Request #3 (April 10, 2025) | 
            PG&E Response #1 (April 24,2025) | 
            Attachment A: LSP CV Substation Components 20250424S (Confidential Data Withheld) 
              Attachment B: LSPGC Induction Study Report 
              Attachment C: Jet Sled Hydroplow Technology 
              Attachment D-1: DR-8 Wind Turbine Throw Distances 
              Attachment D-2: DR-8 Wind Turbine Throw Distances GIS (Confidential Data Withheld) 
              Attachment E: DR-10_Shoreline Trenching Narrative | 
          
          
            | LSPGC Response #1 (April 24, 2025) | 
          
          
            | LSPGC Response #2 (June 19, 2025) | 
            24-99 Collinsville Substation HRA_0619255 
              Collinsville HRA_Attachment A 
              Collinsville HRA_Attachment B 
              Collinsville HRA_Attachment C 
              Collinsville HRA_Attachment D 
              Collinsville HRA_Attachment E 
              Collinsville HRA_Attachment F | 
          
          
            | CPUC Data Request #4 (May 9, 2025) | 
            LSPGC Response #1 (May 23, 2025) | 
            Attachment A: Submarine Cable Installation using Vertical Injector Technology 
              Attachment B-1: Staging Areas (Confidential Data Withheld) 
              Attachment B-2: Substation Property (Confidential Data Withheld) 
              Attachment C: Alternative 230 kV Submarine Segment Alignment (Confidential Data Withheld) 
            Attachment D: Alternative 230 kV Overhead Segment Alignment (Confidential Data Withheld) 
            Attachment E-1: Horizontal Directional Drilling Description 
Attachment E-2: HDD Work Areas (Confidential Data Withheld) 
Attachment F: Kirby Hills Fault Research Paper 
Attachment G: Nearby Infrastructure  | 
          
          
            | PG&E Response #1 (May 23, 2025) | 
          
          
            | LSPGC Response #2 (June 6, 2025) | 
            Attachment A: CV Project Description Schedule and Equipment Updates 
              Attachment 1.3-A: FINAL LSP CV Design Update 1_3-A AQ and GHG Calcs 20250606S | 
          
          
            | LSPGC Response #3 (June 19, 2025) | 
            California Historical Resources Information System Cultural Resource Information (Confidential Data Withheld) | 
          
          
            | PG&E Response #3 (June 23, 2025) | 
            Attachment A: Collinsville Loop - 500kv Monopole Example - DELTA SUSP.POL | 
          
          
            | PG&E Response #4 (July 2, 2025) | 
            Attachment A: Collinsville Bumble Bee Habitat Assessment 2025 | 
          
          
            | PG&E Response #5 (July 7, 2025) | 
            Attachment A: SMUD 3.3_Biological Resources 
              Attachment B: Attachment B 2024_SPUT_SMUD_Incident Spreadsheet_2024 Annual Report (USFWS form 3-202-17)_2 
              Attachment C: Attachment B SMUD Solano SPUT 11th Annual Report_2024.01.08 
              Attachment D: Attachment B Solano SPUT_SMUD 9th Annual Report_2021 
              Attachment E: Attachment B SPUT_SMUD 8th Annual Report_2021.01.05 
              Attachment F: SMUD 2022 Annual SPUT Report (MB189818-0)_Cover Letter 
              Attachment G: SMUD 2024 Annual SPUT Report (MB189818-0)_Cover Letter | 
          
          
            | LSPGC Response #6 (September 10, 2025) | 
            Attachment A: FINAL LSP CV Cultural Resources Alt Site Eval Memo -  Public 20250910S (Confidential Data Withheld) | 
          
          
            | CPUC Data Request #5 | 
            LSPGC Response #1 (June 20, 2025) | 
            Attachment A: Alternative Site A Potential Interference with SMUD Microwave Tower 
              Attachment B: ADLS Radar Tower Location 
              Attachment C: Grading and Activity Level for Alternative Substation Sites  
              2025-06-13_Collinsville Rare Plant Survey Info + GIS (Confidential Data Withheld) 
  | 
          
          
            | PG&E Response #1 (June 20, 2025) | 
              | 
          
          
            | CPUC Data Request #6 | 
            LSPGC Response #1 (June 27, 2025) | 
            Attachment A: Waterline GIS (Confidential Data Withheld) 
              Attachment B: FINAL LSP CV Design Update 1_3-A AQ and GHG Calcs 20250627S 
              Attachmemt C: CV Project Description Schedule and Equipment Updates_06272025 
              Attachment D: Alternative Submarine Route Dredge Impact (Confidential Data Withheld) 
              Attachment E: Collinsville_Alt Submarine Installation Narrative_06272025 | 
          
          
            | CPUC Data Request #7 | 
            LSPGC Response #1 (July 15, 2025) | 
            Attachment A: FINAL LSP CV Attach 1_3-A AQ and GHG Calcs 20250711S 
              Attachment B: Collinsville Substation HRA_Clean_071125 | 
          
          
            | CPUC Data Request #8 | 
            LSPGC Response #1 (August 1, 2025)  | 
            Attachment A: Alternative 12kV Distribution Structures (Confidential Data Withheld) 
Attachment B: Road Usage (Confidential Data Withheld) 
Attachment C: Alternative Staging Yards (Confidential Data Withheld) | 
          
          
            PG&E Response #1 (August 4, 2025)  | 
          
          
            | CPUC Data Request #9 | 
            LSPGC Response #1 (August 11, 2025) | 
              | 
          
          
            | CPUC Data Request #10 | 
            LSPGC Response #1 (August 22, 2025) | 
            Attachment A - Alt AQ Assumptions (Confidential Data Withheld) 
              Attachment B - Underground Alternative A 
              Attachment C - Underground Alternative B (Confidential Data Withheld) | 
          
          
            | CPUC Data Request #11 | 
            PG&E Response #1 (September 2, 2025) | 
            Attachment A - AQ Assumptions (Confidential Data Withheld) 
              Attachment B - Alt 4 Revision (Confidential Data Withheld) 
              Attachment C - HRA Revision  
              Attachment D - Notification List Contact Information (Confidential Data Withheld) | 
          
          
            | LSPGC Response #1 (September 5, 2025) | 
          
          
            | CPUC Data Request #12 | 
            PG&E  Response #1 (September 12, 2025) 
              LSPGC Response #1 (September 12, 2025) | 
            Attachment A - FINAL LSP Collinsville Updated BRTR 20250916S 
              Attachment B - LSPGC Collinsville Updated ARTR 20250912S | 
          
          
            | CPUC Data Request #13 | 
            PG&E Response #1 (September 24, 2025) 
              LSPGC Response #1 (October 3, 2025)  | 
            Attachment A - Alt 1 & 2 Sub Size (Confidential Data Withheld) 
              Attachment B - Alt 1 & 2 Sub Size (Confidential Data Withheld) 
              Attachment C - FAA Screening Tool Results |