General Order 165
Opinion
IV. Review and Modification of Inspection Standards
ORA recommends that the Commission specify the forum in which
we will review and modify, where appropriate, inspection standards. The utilities
propose that we include the new rules in existing General Order (G.O.) 95
and G.O.128 and employ the decision-making process already in place for those
General Orders when considering modifications to the rules we adopt today.
That decision-making process involves negotiations between members of a committee
and modifications by way of Commission resolution.
We decline to employ the existing procedures for changing G.O. 95 and G.O.
128, as the utilities suggest. The Committee process used for G.O. 95 and
G.O. 128 is appropriate where rules must apply to all utilities. By contrast,
any deviations from inspection standards ought to be tailored to the conditions
facing each utility, based on that utility's climate, operating experience,
equipment and maintenance data, and other factors, based on cost-effectiveness
analysis. We believe a highly public and visible process is required here,
considering the introduction of competition and the heightened interest of
the public and California legislature in matters relating to distribution
system performance. Any proposals to change adopted standards should be based
on data and analysis available to all parties.
We intend that this rulemaking be the forum for all such action in the future,
as ORA proposes. We will reconsider the standards we adopt here, and related
findings regarding maintenance of electric utility distribution systems,
on our own motion or the motion of a party if it appears that circumstances
have changed or the standards we adopt are inadequate.