General Order 95
Section VII
Detailed Construction Requirements for Trolley and Electric Railway
Contact and Feeder Conductors and Their Supporting Messengers,
Span Wires, Etc. (Class T Circuits)
79.1 General Provisions
Third rail construction or reconstruction shall be permitted
only for rapid transit passenger lines located in subways, on elevated structures
or within completely fenced rights–of–way, or a combination thereof.
In no event shall the third rail railroad cross at grade any
other railroad, or public way, road, street, thoroughfare or highway, whether
for use by pedestrians or vehicles.
Third rail construction shall be designed, installed and
maintained in such manner as will secure safety to patrons and employees
of the rapid transit line and to the public in general.