50    General

 

The Following Rules cover certain special details for the construction of supply lines. These rules are supplemented, in certain cases, by rules in other sections.  See Section VII for the special rules applicable to Class T circuits; see Section IX for special rules applicable to supply lines on poles jointly used; see Section X for special rules applicable to line crossings or conflicts; see Section XI for special rules applicable to line crossing railroad.

 

Strikeout and Underline Version

Rule 50

 

50    General

 

The Following Rules cover certain special details for the construction of supply lines.  These rules do not apply to Class E circuits, except where provisions are made for in Section VI.  These rules are supplemented, in certain cases, by rules in other sections.  See Section VII for the special rules applicable to Class T circuits; see Section IX for special rules applicable to supply lines on poles jointly used; see Section X for special rules applicable to line crossings or conflicts; see Section XI for special rules applicable to line crossing railroad.

 

Final Version

Rule 50

 

50    General

 

The Following Rules cover certain special details for the construction of supply lines.  These rules do not apply to Class E circuits, except where provisions are made for in Section VI.  These rules are supplemented, in certain cases, by rules in other sections.  See Section VII for the special rules applicable to Class T circuits; see Section IX for special rules applicable to supply lines on poles jointly used; see Section X for special rules applicable to line crossings or conflicts; see Section XI for special rules applicable to line crossing railroad.