|  
             Welcome to the California Public Utilities Commission (CPUC) website 
              for the California Environmental Quality Act (CEQA) review of the 
              proposed construction of Lodi Gas Storage LLC's Kirby Hills Natural 
              Gas Storage Facility and proposed additional facilities. An application 
              for construction of the original project was submitted to the CPUC 
              on July 25, 2005 (Application A.05-07-018). The CPUC published 
              a final Mitigated Negative Declaration 
              (MND) in February 2006 and the project was approved on March 2, 
              2006. A subsequent application for the construction and operation 
              of additional facilities was submitted to the CPUC on May 8, 2007 
              (Application A.07-05-009). This site provides access to public documents 
              and information relevant to the CEQA environmental reviews conducted 
              for each project. Information regarding the original application 
              is provided below (identified as Phase I) followed by information 
              regarding the subsequent application (identified as Phase II). 
             Phase I
            Project Documents Available
            
            Background
            Lodi Gas Storage LLC (LGS) proposed to use a depleted natural gas 
              reservoir in the Kirby Hills gas field as a storage facility for 
              natural gas transported to the site by its customers. The total 
              storage capacity of the reservoir is approximately 7 billion cubic 
              feet (BCF) and the project will have a maximum injection and withdrawal 
              capability of 100 million cubic feet per day (MMcf/day) of natural 
              gas. Project operations would involve tapping into the PG&E 
              400 pipeline near mile 286.65, constructing facilities to convey 
              natural gas from the PG&E 400 pipeline approximately seven miles 
              to the Kirby Hills gas field, storing the gas in the existing natural 
              reservoir, withdrawing the stored gas on demand from LGS customers, 
              and conveying the withdrawn gas to the PG&E 400 pipeline for 
              delivery to those customers. 
            The proposed project is comprised the following six primary components 
              (see Project Facilities Map): 
             
            
              -  Metering station 
              
 - Gas pipeline 
              
 - Compressor station 
              
 - Flow line 
              
 - Injection/withdrawal wells 
              
 - Temporary gas injection system 
 
             
            In accordance with Public Utilities Code Section 1001, LGS received 
              a Certificate of Public Convenience and Necessity (CPCN) from the 
              CPUC to construct and operate the project on March 2, 2006. 
             
            Project Location
            The project site is located in a rural agricultural area in the 
              Montezuma Hills of southeastern Solano County, California, immediately 
              north of the Sacramento–San Joaquin River Delta. The site is approximately 
              six miles west of Rio Vista and eight miles southeast of Fairfield 
              (see Regional Location Map). 
            The proposed project contains two major component locations, connected 
              by an approximately six-mile east-west pipeline corridor (see Project 
              Location Map). The eastern project component is a natural gas 
              receiving/metering station site, located west of Bird's Landing 
              Road, one mile south of its intersection with State Route 12. 
              The western project component is the natural gas storage/withdrawal 
              site located in the Kirby Hills between Montezuma/Nurse Slough on 
              the west and Shiloh road on the east. The western portion of the 
              project area is also located within the Suisun Marsh Secondary Management 
              Area.  
            CPUC's Application Review
            The CPUC is responsible for the review and approval of any natural 
              gas storage facility in California. In proposals such as this, the 
              CPUC has a two-part review process to evaluate economic and environmental 
              impacts. The CPUC conducts a legal proceeding before an administrative 
              law judge to examine the economic and public utility issues, including 
              impacts to utility ratepayers. At the same time, the CPUC conducts 
              an environmental review consistent with CEQA. The ultimate result 
              of the two reviews is a decision by the Commission whether to grant 
              a CPCN for the project.  
            Mitigated Negative Declaration
            The CPUC published a final Mitigated Negative 
              Declaration (MND) in February 2006. The Draft MND underwent 
              a 30-day public comment period between January 17 and February 16, 
              2006. 
             CPUC Actions After Final MND Publication
            The CPUC adopted the Mitigated Negative Declaration in accordance 
              with CEQA and granted a Certification of Public Convenience and 
              Necessity (CPCN) on March 2, 2006. 
            Project construction started on May 22, 2006, and was monitored 
              by a CPUC Environmental Monitor. The CPUC implemented the Mitigation 
              Monitoring Plan as presented in Section C of the MND. This plan 
              ensured that the approved project was constructed as defined, and 
              that all adopted mitigation measures and Applicant Proposed Measures 
              were implemented in order that effects on the environment would 
              not exceed those described in the MND. Weekly 
              reports were prepared that documented construction and compliance 
              activities. Construction of Phase I was completed in March 
              2007. The Final Report documents 
              construction and compliance activities for Phase I. 
            Phase II
            Project Documents Available
            
            Background
            LGS proposed to construct and operate Kirby Hills II in the northern 
              portion of the existing property. The underground storage reservoir 
              and proposed additional associated surface infrastructure would 
              be located primarily on the Kirby Property. The total storage capacity 
              of the reservoir is approximately 12 bcf and the project would have 
              a maximum injection and withdrawal capability of 350 MMcf per day 
              of natural gas. 
            The surface infrastructure associated with Kirby Hills II would 
              consist of the following five components (see Project 
              Facilities map): 
            
              - Three new well pad sites containing 15 injection and withdrawal 
                wells
 
               
                
              - Conversion of four abandoned wells to observation wells
 
               
                
              - A 12-inch-diameter, approximately 3,700-foot pipeline (flow 
                line) connecting the wells to the existing compressor station
 
               
                
              - A new compressor enclosure and additional dehydration equipment 
                at the existing compressor station site
 
               
                
              - An expanded PG&E interconnection at the existing meter station.
 
             
            Project Location
            The project site is located in a rural agricultural area in the 
              Montezuma Hills of southeastern Solano County, California, immediately 
              north of the SacramentoSan Joaquin River Delta. The site is 
              approximately six miles west of Rio Vista and 16 miles southeast 
              of Fairfield (see Regional Location 
              Map). 
            The proposed project contains two major component locations, connected 
              by an existing approximately six-mile east-west pipeline corridor 
              (see Project Location Map). 
              The eastern project component is an expanded pipeline interconnection 
              at the existing natural gas receiving/metering station site, located 
              west of Bird's Landing Road, one mile south of its intersection 
              with State Route 12. The western project component is the natural 
              gas storage/withdrawal site located in the Kirby Hills between Montezuma/Nurse 
              Slough on the west and Shiloh Road on the east. The western portion 
              of the project area is also located within the Suisun Marsh Secondary 
              Management Area. 
            CPUC's Application Review
            The CPUC application review process described above also applied 
              to the review of the Phase II application. 
            Mitigated Negative Declaration
            The CPUC published a Draft Subsequent Mitigated Negative Declaration 
              (MND) in August 2007. The Draft MND underwent a 30-day public comment 
              period (beginning August 24, 2007 and ending September 24, 
              2007). 
            CPUC Actions After Final MND Publication
            The CPUC adopted the Subsequent Mitigated Negative Declaration 
              in accordance with CEQA and granted a Certification of Public Convenience 
              and Necessity (CPCN) on February 28, 2008. Construction began 
              in Spring 2008 and is being monitored by a CPUC Environmental Monitor 
              in accordance with the project's Mitigation Monitoring, Compliance, 
              and Reporting Program. Weekly reports 
              were prepared to document construction and compliance activities. 
              Construction of Phase II was completed in August 2009. The 
              Final Report documents construction 
              and compliance activities for Phase II. 
            Public Comment
            Should you have questions regarding the Kirby Hills Phase I 
              and Phase II projects, you may contact: 
            Junaid Rahman, Regulatory Analyst 
              California Public Utilities Commission 
              505 Van Ness Avenue 
              San Francisco, CA 94102 
             
           |