|  
             Welcome to the California Public Utilities Commission (CPUC) website 
              for the replacement of steam generators for Units 2 and 3 at Southern 
              California Edison's San Onofre Nuclear Generating Station (SONGS). 
              An application for this project was submitted to the CPUC on February 27, 
              2004. The Project was reviewed under the California Environmental 
              Quality Act (CEQA). A Final Environmental Impact Report (EIR) was 
              issued in September 2005 and the CPUC approved the project in December 
              2005. This site provides access to public documents and information 
              relevant to the CEQA review process and project implementation. 
             Background 
            Southern California Edison Company (SCE) filed an application with 
              the CPUC to: (1) replace the San Onofre Nuclear Generating Station 
              Units 2 and 3 (SONGS 2 & 3) steam generators; (2) 
              establish ratemaking for cost recovery; and (3) address other related 
              steam generator replacement issues. The project will enable SONGS 
              2 & 3 to remain in service until the end of the current terms 
              of the Nuclear Regulatory Commission (NRC) licenses. The current 
              licenses both authorize SONGS 2 & 3 to operate until 2022. 
              However, the existing steam generators have exhibited degradation 
              and they are currently predicted to reach the end of their operating 
              life within the next several years. The original steam generators 
              will eventually reach a state where, under applicable NRC regulations, 
              either the steam generators must be replaced or the units must be 
              shut down. 
            SONGS 2 & 3 went into operation in 1983 and 1984, respectively. 
              SONGS 2 & 3 use four steam generators, two per unit, which 
              are large heat exchangers that convert heat from the reactor into 
              steam to drive the turbine generators and produce electricity. All 
              four will be replaced as part of the project. SONGS 2 & 3 produce 
              a combined nominal 2,150 net megawatts of electric power, enough 
              to power approximately 2.1 million homes. The SONGS facility is 
              located in northwest San Diego County and surrounded by Camp Pendleton, 
              San Onofre State Beach, and Interstate 5. 
            Environmental Review Process 
               
            SCE filed a PEA with the Application in February 2004. This document 
              provided a starting point for the environmental review process conducted 
              by the CPUC. 
            The CPUC on October 1, 2004, issued a Notice 
              of Preparation of an Environmental Impact Report (EIR) for SONGS 
              Steam Generator Replacement Project. Scoping meetings were held 
              in October 2004. Scoping meetings were held in October 2004. 
            The Draft Environmental Impact Report 
              (DEIR) was issued on April 15, 2005. 
            The submittal period for written comments 
              on the Draft EIR ended May 31, 2005. 
            The Final Environmental Impact Report 
              (Final EIR) was issued on September 21, 2005. The Final EIR consists 
              of two volumes: Volume I is the complete EIR showing changes 
              made to the Draft EIR, and Volume II consists of all comments 
              on the Draft EIR and responses to comments. 
            The CPUC found the Final EIR to be adequate and certified the document 
              as compliant with CEQA. The CPUC issued its decision D.05-12-040 
              on December 15, 2005. 
            Project Activities Subsequent 
              to CPUC Approval 
            In December 2008, CPUC issued authorization to SCE to begin the 
              steam generation replacement process which includes the following 
              steps: 
            
              - Replacement steam generator transport
 
              - Replacement steam generator staging and preparation
 
              - Original steam generator removal, staging and disposal
 
              - Replacement steam generator installation and return to service
 
               
             
            Compliance review for pre-construction mitigation measures identified 
              in the Mitigation Monitoring Plan as presented in the Final EIR 
              has been conducted by CPUC. This plan ensures that the approved 
              project will be conducted as defined, and that all adopted mitigation 
              measures and Applicant Proposed Measures will be implemented in 
              order that effects on the environment do not exceed those described 
              in the Final EIR. A CPUC Notice to Proceed was issued after compliance 
              with pre-construction mitigation requirements was satisfied by SCE. 
              A CPUC Environmental Monitor monitored the steam generator 
              replacement activities to ensure that they are conducted in accordance 
              with the approved mitigation measures and permit conditions. Reports 
              documenting this monitoring activity are available here. 
            For Additional Information 
             Requests for additional information should be sent to: 
            Jensen Uchida, CPUC Project Manager 
              c/o Aspen Environmental Group 
              235 Montgomery Street, Suite 935 
              San Francisco, CA 94104 
           |