STATE OF CALIFORNIA 
PUBLIC UTILITIES COMMISSION

Pacific Gas & Electric Company's
Ravenswood–Cooley Landing 115 kV Reconductoring Project

(Application A.17-12-010, filed December 15, 2017)

 

Files linked on this page are in Portable Document Format (PDF). To view them, you will need to download the free Adobe Acrobat Reader if it is not already installed on your PC. Note: For best results in displaying the largest files (see sizes shown in parentheses below for files larger than 5.0 MB), right-click the file's link, click "Save Target As" to download the file to a folder on your hard drive, then browse to that folder and double-click the downloaded file to open it in Acrobat.

 

Welcome to the California Public Utilities Commission (CPUC) web site for the California Environmental Quality Act (CEQA) review of Pacific Gas and Electric's (PG&E's) proposed Ravenswood–Cooley Landing 115 kV Reconducting Project. An application for this project was submitted to the CPUC on December 15, 2017 (A.17-12-010). The CPUC completed the CEQA review process and approved the project on April 4, 2019 (D. 19-03-018). This site provides access to public documents and information relevant to the CEQA review process.

Current Project Status

Construction of the Approved Project

Construction of the approved project is currently scheduled from late 2021 through early 2022.

Mitigation Monitoring

Mitigation Monitoring, Compliance, and Reporting Plan


A Mitigation Monitoring, Compliance, and Reporting Plan (MMCRP) was prepared by the CPUC to ensure compliance with applicant proposed measures and mitigation measures approved in the Final Initial Study/Mitigated Negative Declaration. The MMCRP provides guidelines and procedures for environmental compliance during project implementation. The MMCRP is available here.

Notice to Proceed


PG&E must obtain a Notice to Proceed from the CPUC prior to initiating construction activities in accordance with the procedures outlined in the MMCRP. NTP requests and approvals are provided in the table below:

NTP # Description Date Submitted Date Approved
NTP 1 Initiation of foundation improvement activities at Towers #1 and #9. 07/20/2021; 08/09/2021 (additional materials)
08/18/2021


Background

In order to improve transmission system reliability and ensure safe and reliable electric service to the Southeastern Peninsula Service Area, Pacific Gas and Electric Company (PG&E) is proposing to replace the existing wires (a process called reconductoring) on 1.6 miles of double circuit 115 kV power line (line) supported by nine steel lattice towers (towers) between Ravenswood Substation and Cooley Landing Substation.

Project Overview

The existing line begins at Ravenswood Substation located on the north side of US Highway 84 approximately 0.5 miles west of the Dumbarton Bridge in the City of Menlo Park. The line crosses US Highway 84 and continues south through the Don Edwards Wildlife Refuge and Ravenswood Preserve to Bay Road, then continues east along the south side of Bay Road in the City of Palo Alto Baylands Preserve and terminates at Cooley Landing Substation in the City of East Palo Alto. As part of the reconductoring, foundations will be improved at four towers and approximately 10-foot-tall cage-top extensions will be installed on two towers. An optical ground wire (OPGW) will be installed between Ravenswood Substation and Cooley Landing Substation for electrical relay communications and lightning protection. To support the new OPGW, approximately 4.5-foot-tall lattice steel peaks will be installed on the nine towers supporting the line. Construction is planned to begin in the Fall of 2020, or as soon as possible after permitting is completed, and is planned to be completed in the Winter of 2021, or as soon as possible.

Proponent's Environmental Assessment

PG&E filed an Application (A. 17-12-010) for a PTC which included a Proponent’s Environmental Assessment PEA on December 15, 2017. This document provides a starting point for the environmental review process conducted by the CPUC. On May 11, 2018 PG&E submitted a Project Refinement to the PEA.

Deficiency Report

The CPUC submitted Deficiency Reports to PG&E requesting specific information that was not included with the Application or PEA. PG&E addressed the CPUC's comments and provided material identified in the Deficiency Reports on February 16, 2018.

Data Requests

Data Requests No. 1 were filed with PG&E on February 16, 2018.

Draft IS/MND

On August 31, 2018, the CPUC released a Notice of Intent (NOI) to adopt a Mitigated Negative Declaration (MND) for the Ravenswood-Cooley Landing 115 kV Reconductoring Project. A link to view the Draft IS/MND is provided here.

The Draft IS/MND was circulated on August 31, 2018 with a 30 day public comment period extending through October 1, 2018.

Final IS/MND

The Final Initial Study/Mitigated Negative Declaration for the Ravenswood Project can be review here.

On April 4, 2019, the CPUC issued a decision to adopt the Final IS/MND and grant PG&E a Permit to Construct the project (D. 19-03-018). The CPUC adopted the mitigation measures (MMs) and applicant proposed measures (APMs) identified in the Final IS/MND as conditions of project approval, as well as a Mitigation Monitoring and Reporting Program (MMRP) to ensure compliance with the MMs and APMs pursuant to Public Resources Code § 21081.6 and § 15097 of the CEQA Guidelines. The CPUC's decision is available here.

For Additional Information

To request additional information, ask a question, or be added to the project mailing list, please contact:

Email

michael.rosauer@cpuc.ca.gov

 

CPUC Project Manager Mailing Address

Michael Rosauer, Project Manager
California Public Utilities Commission
505 Van Ness Ave., 4th Floor
San Francisco CA 94102

 

Formal Comment Mailing Address

California Public Utilities Commission

Attn: Ravenswood Project

505 Van Ness Ave., 4th Floor
San Francisco CA 94102



This page is best viewed with Firefox or Internet Explorer. Please report any problems to the Energy Division web coordinator.