Welcome to the California Public Utilities Commission (CPUC) website
for the environmental review and monitoring of Southern California
Edison's (SCE's) Eldorado-Lugo-Mohave Series Capacitor Project (ELM
Project). SCE submitted an application for the proposed Project
to the CPUC on May 2, 2018 (Application A.18-05-007). The CPUC
is the California Environmental Quality Act (CEQA) lead agency and
on August 12, 2019, the CPUC published a Draft Initial Study/Mitigated
Negative Declaration (IS/MND) for the Proposed Project. The CPUC
approved a Certificate of Public Convenience
and Necessity for the Project on August 27, 2020 (Decision
D.20-08-032).
This website provides access to public documents and information
relevant to the CEQA review process and mitigation monitoring.
QUICK LINKS
Application
A.18-05.007
Proponent's Environmental Assessment
Amended
Application
Decision
D.20-08-032
Final Initial
Study/Mitigated Negative Declaration
Draft Initial Study/Mitigated Negative Declaration
DESCRIPTION OF PROPOSED
PROJECT
The ELM Project consists of the following major
components:
- Construct 2 new 500 kV mid-line series capacitors (i.e., the
proposed Newberry Springs Series Capacitor and Ludlow Series Capacitor)
and associated equipment.
- Provide 2 communication paths between the series capacitor sites:
- Install approximately 2 miles of overhead and 500 feet of
underground telecommunications facilities as one path to connect
the proposed series capacitors to SCE's existing communication
system.
- Install approximately 2 miles of underground telecommunications
facilities as a second communication path to connect the series
capacitors to SCE's existing communication system.
- Provide station light and power to the proposed series capacitors
by extending and/or rerouting existing lines to create approximately
2 miles of overhead and 700 feet of underground 12 kV distribution
circuits. (The new distribution poles would support overhead telecommunication
facilities as well as the electric distribution lines.)
- Construct 3 new fiber optic repeater facilities (Barstow, Kelbaker,
and Lanfair) within the Lugo-Mohave ROW.
- Install distribution lines for light and power at the 3 proposed
fiber optic repeater sites.
- Install underground telecommunications facilities from existing
transmission structures to the Barstow, Kelbaker, and Lanfair
fiber optic repeater sites.
- Address 16 potential overhead clearance discrepancies at 14
locations by:
- Relocating, replacing, or modifying existing transmission,
subtransmission, and distribution facilities at approximately
12 locations along the Eldorado-Lugo, Eldorado-Mohave, and
Lugo-Mohave 500 kV Transmission Lines to address 14 of the
overhead clearance discrepancies. Tower modifications would
include raising 9 towers approximately 18.5 feet by inserting
new lattice-steel sections in tower bodies.
- Performing minor grading at 2 locations along the Lugo-Mohave
500 kV Transmission Line to address 2 of the overhead clearance
discrepancies.
- Install approximately 235 miles of optical ground wire (OPGW)
(approximately 59 miles on the Eldorado-Mohave Transmission Line
and approximately 173 miles on the Lugo-Mohave Transmission Line,
including approximately 3 miles of underground telecommunications
facilities in the vicinity of the Mohave Substation).
- Modify and strengthen the ground wire peak of existing suspension
towers where OPGW splices would occur (some of these towers would
also require minor modifications to the steel in the tower body).
- Install approximately 2,000 feet of underground telecommunications
facilities within the existing Lugo, Mohave, and Eldorado Substations.
- Within Lugo Substation, perform modifications on the existing
series capacitors and install new terminating equipment and remove
2 existing tubular steel poles (TSPs) and install 2 new TSPs on
the Eldorado-Lugo and Lugo-Mohave 500 kV Transmission Lines.
- Within the Eldorado Substation, perform modifications on the
existing series capacitors and upgrade the terminal equipment
on the Eldorado-Lugo 500 kV Transmission Line.
- Within the Mohave Substation, replace existing series capacitors
on the Lugo-Mohave 500 kV Transmission Line and install new terminal
equipment on the Eldorado-Mohave and Lugo-Mohave 500 kV Transmission
Lines.
- Within LADWP's McCullough Substation, replace 5 existing 500
kV 50 kA circuit breakers with 5 new 500 kV 63 kA circuit breakers.
- Install (if necessary) cathodic protection on approximately
60 miles of SoCalGas's natural gas pipelines parallel to SCE's
Lugo-Mohave 500 kV Transmission Line.
Construction Status and
Mitigation Monitoring
The CPUC and SCE have prepared a Mitigation Monitoring, Compliance,
and Reporting Plan (MMCRP), which is available here (7MB).
The MMCRP ensures compliance with the mitigation measures adopted
in the Final IS/MND. The MMCRP provides for Environmental Monitors
and defines the reporting relationships, roles and responsibilities,
and procedures for environmental compliance on the Project. The
MMCRP will be updated to reflect schedule changes and other revisions
as needed.
Notices to Proceed (NTPs) are reviewed and will be issued by CPUC
by subsection of the project as requested by SCE. Issuance of NTPs
is contingent upon SCE's compliance with pre-construction requirements
as specified by the approved mitigation measures and responsible
agency permitting requirements. Table 1 below summarizes the
NTPs issued by CPUC and BLM.
Approved plans are available here. Limited
construction activities began in January 2021.
CPUC Environmental Monitors are present to monitor construction
activities and verify that the proper implementation of project
mitigation measures and permit and compliance plan requirements
during construction is occurring. Monitoring reports documenting
construction and compliance activities are available here.
As final engineering is completed or as construction necessitates,
Minor Project Refinements (MPRs) will be submitted for the Project.
Each of these requests will be reviewed by CPUC to ensure that no
new impacts or increase in impact severity would result from the
requested change. MPRs approved for the project are summarized below.
Table 2. Minor Project
Refinements |
MPR #
|
MPR Request Submittal
Date
|
Description
|
Date Approved
|
#1
|
|
Additional work areas for five locations to support
construction. |
September 8,
2021 |
#2
|
|
New work areas for OPGW work along Lugo-Mohave
Transmission Line |
September 30,
2021 |
#3
|
|
Continued use of a water source to support construction |
October 21,
2021 |
#4
|
|
Addition of work areas to support distribution
line work along Deep Creek Road |
October 21,
2021 |
#5
|
|
Additional work areas and water source |
October 15,
2021 |
#6
|
|
Work area for grounding activities |
January 11,
2022 |
#7
|
|
Daggett water source |
January 26,
2022 |
BACKGROUND
The CPUC is the California Environmental Quality Act
(CEQA) lead agency and the Bureau of Land Management (BLM) is the
National Environmental Policy Act (NEPA) lead agency, with the National
Park Service (Mojave National Preserve) as a Cooperating Agency
under NEPA.
Application: SCE submitted an application for a Permit to
Construct (PTC) for the Project to the CPUC on May 2, 2018
(Application A.18-05-007).
The Application was accompanied by a Proponent's
Environmental Assessment. On January 9, 2019, the CPUC
directed SCE to amend it application and to refile it as an application
for a Certificate of Public Convenience and Necessity (CPCN), rather
than for a PTC. SCE submitted its amended
application for a CPCN (6MB)
on April 19, 2019.
CEQA Review: The CPUC has reviewed the proposed project
under CEQA. On August 12, 2019, the CPUC published a Draft
Initial Study/Mitigated Negative Declaration (IS/MND) for the
Proposed Project. The 30-day public review and comment period for
the IS/MND closed on September 13, 2019. Comment
letters were received from 11 parties. The letters, CPUC's responses,
and text revisions to the Draft IS/MND are included in the Final
IS/MND.
The project is located in San Bernardino County, California; Clark
County, Nevada; the cities of Hesperia, California, and Boulder
City, Nevada; the unincorporated community of Lucerne Valley in
California; and the unincorporated communities of Searchlight and
Laughlin in Nevada. A map is provided here.
An overview of the Proposed Project is provided below.
COMMENTS & QUESTIONS?
If you have comments or questions regarding the project,
please contact us using the CPUC's project email or voicemail, as
follows:
|