4. PRECONSTRUCTION PLANS REQUIRED BY MITIGATION MEASURES

4.1 List of Plans Required and Submission/Review Schedule

PPSI is required by the terms of the mitigation measures and the permitting requirements of various other regulating agencies to prepare numerous plans and permits for approval prior to construction. Copies of these plans are retained in Aspen's office, and additional copies of the plans most relevant to field monitoring responsibilities will be kept at Aspen's field office. All plans are listed in Exhibit 2.

Exhibit 2 Plans Required to be Submitted by PPSI

* Construction Contract Document
* Final Construction Plans
* Lead Agencies' Approval of Technical Specialists
* Erosion Control, Revegetation, and Landscape Plan
* Storm Water Pollution Prevention Plan
* PPSI's Construction Monitoring Plan
* Transportation Management Plan
* Sensitive Botanical Resources Mapping
* Pre-Construction Wildlife Surveys; Bird Surveys; Plans for Capture/ Keeping Frogs/Turtles/Snakes
* Grapevine Creek Snail Surveys; Construction contingency plan
* List of Operators Sharing Common Corridor
* Cultural Resources Management Plan
* Management Plan for Old Ridge Route
* Native American Contract
* Construction Contingency Plan for Discovery of Unexpected Contamination
* Voluntary Cleanup Program Application
* Revised Draft, Pacific Pipeline, Sampling and Analysis Plan for Pre-Construction Testing for Environmental Contamination
* CDFG Application for Streambed Alteration Agreement
* List of Stream Crossings and Photographic Records
* U.S. Army Corps of Engineers Request for Verification
* Bridge Crossing Permit
* Abandonment Plan
* Oil Spill Contingency Plan
* Fire Protection Plan (Operational Phase)
* HAZOP Study
* Inspection and Maintenance Program
* Site-Specific Health and Safety Plan
* Oil Well Location Report
* Geotechnical Reports
* Hydrologic Engineering Reports
* Ground Water Wells Report
* Plan for Notification to Residents/Property Owners
* Public Liaison Plan
* Storm Water Pollution and Prevention Plan
* Paleontological Resources Monitoring Plan
* Water Management Plan
* Business Impact and Notification Mitigation Plan
* Local Employment Hiring Plan
* Salvage and Recycling Plan
* Utility Protection Plan
* Fire Protection Plan (for construction): General and ANF
* Hazardous Materials Management Plan
* Community Outreach & Communications Program/Plan
* Community Partnership Program
* Local Community and MBE Hiring Program

 

Many of the plans listed in Exhibit 2 have been submitted and approved as of April 1997. It should be noted that several permit documents have also been submitted to Aspen by PPSI (as also listed in the exhibit). While these documents are being reviewed by the approving agencies, these plans are also being reviewed for compliance with mitigation measures where such measures recommended that specific information be included in submittals to responsible agencies.

As also shown in the Exhibit 2, some plans are not required to be approved prior to construction, but will likely be submitted during the construction phase. They will be reviewed within 60 days of Aspen's receipt of the completed submittal.

4.2 Required Reviews; Review Guidelines; Deliverables

The Aspen team, including Program Management staff and the Expert Technical Reviewers, will review and provide comments on mitigation plans submitted as required by permit conditions. Comments will be provided to PPSI on the mitigation plans in order that they are both effective and accomplish the intended reduction in impacts, including assurance that objective performance (success) criteria are in place before monitoring begins.

The management and technical review team will review each plan prior to the start of construction, providing comments to PPSI regarding the adequacy of each plan with respect to the following:

* Compliance with all provisions of the mitigation measures and Applicant proposed measures
* Consistency with the FEIR and EIS/SEIR mitigation requirements
* Adequacy of mitigation and recommended modifications
* Adequacy of performance standards and recommended modifications
* Adequacy of field verification methods and recommended modifications
* Review of any hierarchical relationships/work charts presented by PPSI.

Deliverables will include a report on each plan or permit reviewed, in addition to a copy of the plan itself with marginal notes or comments, if appropriate.