6. PROCEDURES FOR FIELD MONITORING
[Field Monitoring Manual for
Environmental Monitors]
6.1 Description of the Pacific Pipeline
Project and Master References
6.1.1 Description
of the Pacific Pipeline Project
The Pacific Pipeline will carry up to 130,000
barrels per day (BPD) of crude oil from Emidio (in southern Kern
County) to refineries in the Los Angeles area. In addition to
construction of about 132 miles of 20-inch insulated pipeline,
PPSI will construct a new pump station at Emidio (adjacent to an
existing Texaco pump station), a pump station at Grapevine, a
pressure relief station at the Templin Highway (Whitaker
Station), and several scraper traps (e.g., at the Lynwood
Junction). Construction is expected to begin in January of 1997,
and take about 10 months to complete.
Approximately 33% of the crude oil shipped in
the pipeline will be produced offshore Santa Barbara County in
Federal waters (called OCS, or Outer Continental Shelf crude),
and about 67% of the crude will be produced in the San Joaquin
Valley (SJV). The OCS crude will be shipped to Emidio through the
All American Pipeline (AAPL) from Santa Barbara County to AAPL's
Pentland Station, where it will be shipped through Texaco
pipelines to Texaco's Emidio Station. SJV crude will be shipped
to the Emidio Station through a variety of gathering lines
existing in the valley.
The Pacific Pipeline is a complex and
controversial project. The environmental review of the different
phases of this project began in 1991, and the two major
environmental documents prepared by the Lead Agencies exceed
3,000 pages. The project has evoked intense public and agency
involvement. More than 2,700 public comments were received on
different phases of the project and more than 50 articles on the
project have been published in major southern California
newspapers.
The pipeline traverses two counties, 15
municipalities (including many communities within the City of Los
Angeles, and a number of unincorporated communities), and can be
divided into three distinct segments for the purpose of
describing construction environments.
The first 33 miles of the pipeline are in the
rural areas of southern Kern County and northern Los Angeles
counties. In this segment, the pipeline originates in the
relatively flat area of southern Kern County and enters the I-5
corridor at Grapevine Canyon. It then traverses the Castac
Valley, reaches its highest point at Tejon Pass and crosses the
Peace Valley and the San Andreas Fault zone before it enters the
Angeles National Forest (ANF). In this segment the pipeline is
primarily within existing roads or pipeline Rights-of-Way (ROW).
Potential impacts and associated mitigation measures are in the
issue areas of biology (potential endangered/threatened species),
air quality (heaters at Emidio Station), geology (landslide areas
and fault crossings in I-5 corridor).
The second segment of the pipeline extends
through about 20 miles of very rugged terrain in the Angeles
National Forest (Saugus Ranger District), mostly within an
existing pipeline ROW. It is within this segment of the pipeline
route that it crosses a number of streams that are tributaries to
the Castaic Lake and Pyramid Lake State Water Project reservoirs,
two important water resources for hundreds of thousands of people
in the Los Angeles Basin area. Potential impacts include effects
on hydrologic resources, and effects on cultural and
paleontological resources.
The third segment of the pipeline emerges out
of the ANF and after passing Violin Canyon, enters the urban
portion of the greater Los Angeles area. This stretch of the
pipeline (all the way to Wilmington and El Segundo), which at 70
miles in length is the longest of the three segments, would be
mostly within existing railroad ROWs, and thus, mostly traverses
industrial zones of several cities within two major
transportation corridors, the San Fernando Road Corridor, and the
Alameda Corridor. However, thousands of people reside within
1,000 feet of the centerline of the project. The pipeline would
be bored under all major street crossings and would be laid in
some of the existing streets in central Los Angeles and in the
south Alameda Corridor. Within this segment of the pipeline there
are many communities with high percentages of minorities and
low-income populations. The pipeline in this segment would also
cross some of the major railroad maintenance yards, some of them
containing hazardous wastes (for example, the Taylor Yard which
has been designated as a State Superfund cleanup site). The issue
areas of importance include system safety, traffic, noise, land
use, socioeconomics, environmental justice, and environmental
contamination.
PPSI proposes to construct the pipeline in five
"pipeline spreads" which will be working on different
segments of the pipeline, usually concurrently. They intend to
use two types of pipelaying spreads, referred to as "urban
spreads" and "rural spreads". The "urban
spreads" are more constricted than the "rural
spreads" on which construction would move more quickly and
usually traverse wider ROWs. In addition to the pipeline itself,
construction will include two pump stations, one pressure
reduction station, and numerous block and check valves to be
installed along the pipeline route. Each boring or directional
drilling site will require a work area of approximately 100 x 200
feet that will also be disturbed. The spreads proposed to be used
by PPSI are defined in Exhibit 3.
Exhibit 3 Pipeline Construction Segments (per PPSI, 4/8/97)
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
It should be noted that construction
segments 1, 2, and 4 will each have two separate construction
spreads within them, so it is likely that there will be occasions
when as many as 7 or 8 separate spreads are operating along the
ROW.
Exhibit 4 lists the numbers of mitigation
measures proposed in the EIS/SEIR and EIR, and the approximate
number of measures proposed by PPSI to reduce impact (these
"Applicant Proposed Measures" are incorporated as part
of PPSI's project description, and their implementation must also
be ensured by this program). Appendix A includes the full text of
each measure or proposal, including performance criteria and
timing.
Exhibit 4 Mitigation Measures and Applicant-Proposed Measures Per Environmental Issue Area1
|
|
|
|
Air Quality |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
1 Includes all mitigation measures from EIS/SEIR and relevant mitigation measures from 1993 EIR.
6.1.2 Master
References
All field monitors are expected to be
thoroughly familiar with the project history and with the
environmental documents that have been prepared. The documents
that guide the field monitoring efforts, and which will serve as
essential references, include the following:
Pacific Pipeline Project Final Environmental Impact Report, September 1993
Pacific Pipeline Project Final Environmental Impact Statement and Subsequent Environmental Impact Report, January 1996
Final/approved construction plans (detailed photo alignment sheets including notations of sensitive resources)
Appendices to this Manual, including:
Appendix A Mitigation measures, applicant-proposed measures and project parameters; definition of impacts, performance and effectiveness criteria
Appendix B Responsible and Cooperating Agencies
Appendix C Applicable Laws, Regulations, and Standards
Appendix D Computer System Manual (attached for
EMs only)
6.2 Roles, Responsibilities, and
Authority of Field Monitors
Third Party Monitoring
The Aspen Monitoring Team consists of third
party monitors who are conducting the MMCRP on behalf of the CPUC
and ANF and are accountable to them. As third party monitors,
they are responsible for ensuring that all measures are
implemented successfully by PPSI. PPSI is responsible for
constructing and operating the project in a cost-effective manner
while complying with the mitigation measures, applicant-proposed
measures and project parameters, and permit conditions. It should
be noted that only PPSI can commit project resources and direct
construction contractors. The joint goal of the third party
monitors and PPSI is to ensure successful completion of the
project while minimizing environmental impacts and citizen
complaints.
Monitoring Philosophy
The goal in implementing the MMCRP is to ensure
complete compliance with mitigation measures, applicant-proposed
measures, approved plans, and permit conditions and requirements
in a non-threatening manner using open and honest communication.
It should always be remembered that the project was approved by
the Lead Agencies assuming the achievement of the impact
reductions defined in the environmental documents through
implementation of these measures. The methods and procedures
presented in this document are intended to assure the completion
of an effective monitoring program, consistent with the
requirements of the CPUC and CEQA, and in compliance with
National Forest System, ANF, and NEPA requirements.
Aspen's team is committed to the conscientious
monitoring of the mitigation measures and associated conditions
under which PPSI will operate. In accordance with this
philosophy, Aspen is also committed to avoiding or minimizing any
impacts that could result from our monitoring activities
themselves. In all instances where feasible, based on the
monitoring requirements of each activity and location, Aspen will
comply with the same types of restrictions placed on PPSI to
reduce the potential impacts that could result from this
construction project.
Environmental Monitors
Qualifications. The
LEM will have earned a minimum of a Bachelor's degree in one of
the environmental sciences, engineering, or related field and
have at least 5 years of monitoring experience. In addition, the
LEM will have field experience managing field crews; knowledge of
pipeline construction techniques; the ability to read and
understand construction specifications, drawings, plans, and
designs; strong interpersonal abilities; be computer literate;
and possess excellent communication skills.
The EMs will have earned a minimum of a
Bachelor's degree in one of the environmental sciences,
engineering, or related field. The EMs will have experience in
field monitoring for construction and restoration procedures or
permit compliance; the ability to read and understand
construction specifications, drawings, plans, and designs; be
computer literate; and possess excellent communication skills.
Role. The role of the
LEM is to provide training, field coordination, scheduling, and
management of the EMs at each construction spread; coordinate
with Aspen's Program Management Team regarding the need for
Technical Experts in the field; be an on-site resource for EMs
and project personnel; and to be a liaison between field
personnel and the Program Manager. The LEM will provide specific
briefings for agency personnel regarding the status of the
project, if it is required. The LEM can be contacted by cellular
phone, PPSI radio, or pager. The LEM reports directly to the
Program Manager.
The role of an EM is to watch, check, and keep
track of the field and construction activities and progress of
the construction crews and document/report to help ensure that
the required mitigation measures and other
conditions/requirements are met. The EMs will assist and report
to the LEM.
See Section 6.11 for the role of the LEM and
EMs in responding to variance requests.
Monitoring Responsibility. Environmental
monitors (LEM and EMs) are responsible for documenting that the
required mitigation measures, applicant-proposed measures,
approved plans, and permit conditions and requirements are
implemented according to the performance criteria and that
mitigated environmental impacts meet the standards set by these
criteria in the Mitigation Monitoring Plan (see Appendix A). The
monitor will use the computer tracking system to assure that all
measures to be implemented in any particular location is checked
and categorized as either accepted or not in compliance.
Each workday morning, before going into the
field, the EM will meet with the PPSI Spread Superintendent (or
his designee) for his/her assigned construction spread to discuss
the planned construction activities for the day. When in the
field, the first priority of the EM is to inspect active
construction sites. The time spent monitoring an activity will
depend upon a combination of the activity occurring (e.g.,
clearing and grading may require more inspection than welding)
and the location of the activity (e.g., stream crossings versus
roadways). The EM will utilize a laptop computer and the computer
tracking system to record his/her monitoring and compliance
activities for each site. Before leaving the site, the EM will
notify the appropriate PPSI inspector if there is a problem or if
a non-compliance event has occurred. If a non-compliance is
recorded, the EM will follow the steps outlined in Section 6.9.3
of this document.
Reporting Responsibility. Environmental
monitors (LEM and EMs) are responsible for documenting the
implementation of mitigation measures, applicant-proposed
measures, approved plans, and permit conditions and requirements
using Aspen's computerized reporting system. Follow-up reports on
any non-compliance will be prepared until the situation is
remedied (see Section 6.8 for more details).
Enforcement Responsibility. Environmental
monitors (LEM and EMs) have overall authority to enforce permit
compliance on behalf of, and in full consultation with the Lead
Agencies). Implementation problems or non-compliances related to
mitigation measures, applicant-proposed measures, approved plans,
and permit conditions and requirements will be recorded and
reported to the LEM, who will notify the Program Manager. Such
events will also be reported in the daily report modemed to
Aspen's central computer server, and will be included in the
daily fax report to Lead Agencies. The Program Manager, or his
designee, will contact the CPUC and/or ANF, as well as
appropriate agencies or individuals, as necessary, and will
discuss the suggested enforcement actions associated with each
non-compliance.
Authority. Environmental
monitors (LEM and EMs) have the authority (after proper
consultation with the Program Manager and, through him, with the
Lead Agencies) to require PPSI to halt any construction,
operation, or maintenance activity associated with the Pacific
Pipeline Project if the monitor determines that the activity is a
deviation from the approved project description or adopted
mitigation measures, applicant-proposed measures, approved plans,
or permit conditions and requirements. The decision on cessation
of construction activity will depend on the level of the
violation and the PPSI response to warnings, if these warnings
were issued. (Please see the discussions of dispute resolution
and variance processes later in this section).
Mitigation Compliance
Responsibility
PPSI is responsible for successfully
implementing all the mitigation measures in the Mitigation
Monitoring, Compliance and Reporting Plan (MMCRP), including
mitigation requirements established by cooperating and
responsible agencies through the permit process and in specific
plans. PPSI is also responsible for implementing
applicant-proposed measures/project parameters, approved plans,
and all aspects of the Project Description as described in the
EIS/SEIR and the EIR. Successful implementation of the mitigation
measures is dependent on performance criteria outlined in
Appendix A. Successful implementation of each measure in actual
achievement of reduction intended should be measured by the
detailed "Effectiveness Criteria" of the Mitigation
Monitoring Plan defined in Appendix A.
PPSI shall inform the CPUC and ANF in writing
of any aspect of a mitigation measure or project parameter that
are not or cannot be successfully implemented. The CPUC and ANF
or its designee will assess whether alternative mitigation is
appropriate and specify to PPSI the subsequent actions required.
Any waiver of a mitigation measure, condition, or requirement
will be documented as a "Variance" (see Section 6.11).
6.3 Roles and Responsibilities of
Technical Experts in the Field
Qualifications. Technical
Experts will have a minimum of a Bachelor's degree in a relevant
discipline and 10 years of experience. The Technical Experts will
have professional certificates (where applicable), specific
expertise in the project subject, and experience in pipeline
construction and restoration procedures or permit compliance.
Role. The role of the
Technical Expert in the field is to provide, at the request of
Aspen's Program Management Team, expert analysis or quick and
innovative approaches for specialized field problems or
situations, often with very little notice. Technical Expert might
be required to actually monitor, in the field, aspects of the
mitigation measures that require specific experience.
Responsibility. Technical Experts are responsible for responding promptly to inquiries from Aspen. They will be available to report to a field site of being notified that their services are needed. They will be available to participate in the MMT program and will periodically review the monitoring activities for thoroughness and technical accuracy, as required. When in the field, the Technical Experts shall contact the LEM on a daily basis to report their activities, findings, and recommendations, in order that the LEM can include those reports in her daily report. The Technical Experts shall also submit a brief summary of each day's field activities to the Aspen office (via fax) to document their time spent and tasks performed.
Exhibit 5 lists the technical experts on the
Aspen team.
Exhibit 5 Technical Experts
Name of Technical Expert, Firm | Telephone No. | Issue Area(s) |
Mari Schroeder, Chambers Group Inc. | (714) 261-5414 | Wildlife Biology |
Phil Lowe, Simons Li & Associates | (714) 513-1280 | Hydrology |
Neal Mace, Geotechnical Consultants Inc. | (415) 777-4870 | Geology, Soils |
Jim Thurber, Geotechnical Consultants Inc. | (714) 547-5413 | Environmental Contamination |
Roberta Greenwood, Greenwood & Assoc. | (310) 454-3091 | Cultural Resources |
Bruce Lander, Paleo Environmental Assoc. | (818) 797-9895 | Paleontology |
Richard Garland, Stevens/Garland Assoc. | (714) 840-9742 | Traffic, Transportation |
Jay Sheth, Robert Brown Engineers | (213) 770-3630 | System Safety, Pipeline Engineering |
Michael Clayton, Michael Clayton & Assoc. | (415) 883-9211 | Visual Resources |
Vicki Hill, V Hill Env. Planning Consultants | (707) 935-9496 | Land Use, Recreation |
Genoveva Arellano, Arellano Associates | (909) 627-2974 | Public Access, Environmental Justice |
Howard Wolff, Butte Canyon Research Assoc. | (916) 896-1715 | Computerized Reporting System |
6.4 Agency Jurisdictions
Following, in Exhibit 6, is a list that
includes all Federal, State, and local agencies with jurisdiction
over the project. The list includes a contact name and phone
number for each agency with jurisdiction over the project. The
list also indicates which construction spread or spreads are
within the jurisdiction of that agency.
Exhibit 6 Agency Jurisdiction List
6.5 Interaction with PPSI and
Construction Contractor Personnel
The goals of all interactions between EMs and
PPSI or Contractor personnel are:
To obtain full cooperation in assuring that all required mitigation measures and proposed project parameters are successfully implemented
To avoid even the appearance of impropriety
To be professional at all times
To establish and maintain vital levels of communication and coordination
To distribute information among all parties in
a timely manner.
Each active construction spread shall have at
least one EM assigned to it each workday. The LEM shall visit
field sites at the site. The EM will communicate and coordinate
with the PPSI Spread Superintendent and/or his designee. When
there is a problem or non-compliance, the EM shall notify the
appropriate PPSI Inspector directly in order to hasten corrective
actions. The LEM shall also be notified promptly. If a PPSI
Inspector or the PPSI Spread Superintendent cannot be located or
contacted, the EM shall notify the contractor foreman. The EM
shall not direct the work of the Inspector, the contractor, or
subcontractor. The EM shall document all observations and
communications in his/her Daily Inspection Record.
6.5.1 Communication
Channels
The LEM will meet with the individual EMs
during the work week to distribute paperwork, coordinate
activities, and discuss concerns, problems, resolutions, and
laudatory activities. The LEM and EMs will meet at least every
two weeks to share and up-date information. To ensure that PPSI
and contractor concerns are addressed promptly and efficiently,
the LEM will meet with Spread Superintendents as needed. Meetings
between the PPSI Environmental Coordinator and the LEM will occur
on a daily basis so PPSI's environmental staff and Aspen's field
staff will have an open exchange of information and a
professional working relationship.
Each EM will meet with PPSI Spread
Superintendent (or his designee) for his/her assigned
construction spread every morning to be briefed on the activities
of the day and to discuss the potential problems for particular
locations or activities. The LEM and EMs will coordinate with
PPSI to identify sensitive areas before construction reaches
those locations.
Every night the LEM will contact each EM to
discuss the plans and assignments for the next workday.
6.6 Coordination and Field Assignments
In consultation with Program Manager and the
other Deputy Program Manager, the LEM will coordinate the field
assignments of the EMs based upon construction activities and
schedules that are provided by PPSI at morning meetings and in
weekly up-dates. Environmental monitoring priorities and the use
of Technical Experts will be based upon planned activities and
scientific expertise appropriate to specific sensitive areas or
construction activity (for example, stream or fault crossings,
sensitive habitats, traffic issues) and coordinated with Aspen's
Program Management Team. Field assignments may also be influenced
by specific requests made by PPSI. The Program Manager and LEM
shall be notified of any changes in construction activities or
schedules at least 24 hours before the change is to occur so as
to have time to arrange field assignments, as needed.
Field assignments for Technical Experts will be
on an 'as-needed' basis and coordinated by Aspen's Program
Management Team.
6.7 Communication Protocols (Agencies,
Monitors, PPSI, Others)
The following communication protocol has been
developed to facilitate efficient communication between
environmental monitors and agencies, PPSI, the contractor, and
subcontractors:
The LEM and EMs will not directly contact the contractors or subcontractors. Contact will be made through PPSI, unless there is an emergency situation.
Environmental monitors will not directly contact PPSI management or agencies without prior instructions from the LEM or Aspen's Program Management Team.
The LEM will not directly contact PPSI management or agencies without consulting Aspen's Program Management Team.
Aspen's Program Management Team will be the primary contact for PPSI management and agency inquiries.
Correspondence for the LEM and EMs will be sent to the Aspen main office.
Environmental monitors will submit written
memoranda through the LEM.
Exhibit 1 (repeated on the following page from
Section 3) shows communication pathways between Aspen personnel,
the Lead Agencies, and PPSI.
6.7.1 Media
Contact
This section will ensure that all parties are
aware of who should and should not talk to the media, and that
the CPUC or ANF representatives are authorized to talk to the
media. Any media inquiries presented to Environmental Monitors or
Technical Experts should be reported immediately to the Lead
Environmental Monitor. The LEM shall refer all media requests to
Aspen Program Management Team: Dr. Hamid Rastegar, and the Lead
Agencies' focal point of contact.
When approached by a member of the media, the
EM should:
Identify him/herself
Be calm and truthful
Tell them that, by the virtue of Aspen's
contract, it is required that all inquiries be referred to the
appropriate Lead Agency representatives.
6.7.2 Public
Contact
When approached by a member of the public, the
LEM or EM should remain polite at all times, but should not offer
solutions or make promises. Depending on the problem or question,
the public should be referred to either the PPSI Inspector
on-site or to Aspen's Program Manager. At all times, whether
on-site or off-site, Aspen's environmental monitors shall
remember that they represent the Lead Agencies and shall consider
project-related information confidential until instructed
otherwise by Aspen's Program Management Team.
6.8 Documentation and Reporting
Documentation and Reporting
Requirements. The documentation and reporting
requirements are intended to (1) chronicle PPSI's compliance with
the MMCRP, including evaluation of environmental impacts and the
effectiveness of mitigation efforts, and (2) report on
construction progress and compliance both internally to Aspen's
Program Management Team and field personnel, and externally to
Lead Agencies, PPSI, other agencies, and the public.
Documentation Procedures.
Every work day, each EM will maintain a Daily Inspection Record
(in the Data Management System, Aspen's computer tracking system)
to track all procedures required for each mitigation measure and
ensure that the timing specified for the procedures is adhered to
for their assigned construction spreads.
At the end of every work day, Technical Experts
will submit an activity record by fax to the Aspen office. They
shall also call the LEM and briefly report on their activities.
The written report shall include a description of the work done
and any problems that occurred. Both the LEM and the Aspen office
(DPM for Expert Reviewers) must be aware of the progress and
activities will record and track the activities of the Technical
Experts on a daily basis.
Field personnel (LEM, EMs, and Technical
Experts) are expected to document construction activities with
photographs and, in some cases, video photography. Color, print,
35 mm photographs will be taken to help document a reported
non-compliance. If appropriate, photos should also be taken to
document the steps taken to remedy the non-compliance. Aspen
monitors are encouraged to take photographs to record
construction activities and progress. Photographs will be logged
on a photograph record sheet. Each photograph shall be properly
labeled (photographer, photo identification number, date of
photo, time photo taken, construction spread, estimated milepost,
description of activity) and then submitted with negatives to the
Aspen corporate office. Aspen's Program Management Team may
provide a video camera and request that specific construction
activities be recorded. If this occurs, specific instructions
will be provided by Aspen's Management Team.
Reporting Requirements. Daily
Inspection Records will be sent (via modem) to the Central
Computer Server at Aspen's corporate office at the end of each
work day. The CPUC and ANF will receive daily reports generated
by the Data Management System from Aspen's Program Management
Team. The reports will indicate activities at each construction
spread, variances that were requested and/or approved, and
non-compliances that were reported and their status.
Aspen's Program Management Team will provide
the CPUC and ANF with Weekly Summary Reports and Monthly
Compliance Reports based on the Daily Inspection Records and
project correspondence.
PPSI will provide the CPUC and ANF with written
quarterly reports of the project that shall include progress of
construction, resulting impacts, mitigation implemented, and all
other noteworthy elements of the project.
6.8.1 Recordkeeping
Requirements
All records generated by Aspen personnel will
be kept at Aspen's corporate office. The field office will have
copies of the Daily Inspection Records, the Weekly Summary
Reports, and the Monthly Compliance Reports. The field office
will also have copies of all master references.
6.8.2 Data
Reporting/Computer Tracking System Input
The EMs will have portable computers available
to them upon which to enter their Daily Inspection Records on a
daily basis. The information will be sent via modem to the
central server in the Aspen corporate office at the close of each
work day (see Appendix D, Computer System Manual). The
information included in the Daily Inspection Records will
include, at a minimum:
Compliance status for each applicable mitigation measure and requirement
Deadline for Correction of Non-Compliance
Weekly Summary Reports shall be prepared by
Aspen's Program Management Team. The Weekly Summary Reports will
provide not only information about the activities of the week
(including construction progress and status of non-compliances
that have occurred) but also planned construction activities for
the coming week.
The Monthly Compliance Reports shall be
prepared by Aspen's Program Management Team and will provide
detailed information on the mitigation measures that have been
completed, types of non-compliances that have occurred, remedial
actions that have been proposed, the progress of construction, or
other pertinent information.
6.8.3 Expense and
Time Reporting
Expense and time reporting by LEM and EMs will
be done on a weekly basis. Time Sheets and Expense Reports
(Exhibit 7 and Exhibit 8) shall be submitted to the Aspen
Corporate office every Monday before 10:00 a.m. If expense
reports are sent by facsimile, legible copies of all receipts
shall be included. Original receipts shall be submitted within 5
days. Time sheets and expense reports will be available at both
Aspen's corporate and field offices. Guidelines for expense
reports will be provided; these guidelines are based on
California State allowable limits due to Aspen's contract with
the CPUC. Additional guidance and sample forms will be provided
during the MMT.
Aspen's corporate office will provide supplies.
The purchase of materials not available from the Aspen corporate
office must be approved by the Aspen Program Management Team
prior to purchase in order to be considered for reimbursement.
6.9 Compliance Evaluation
The purpose and goal of compliance evaluation
is to ensure that the specific performance criteria for each
mitigation measure, applicant-proposed measure, permit
requirement or condition, approved plan, or other project
stipulation are met in order to minimize or eliminate potential
significant impacts and to protect environmental resources.
6.9.1 Process for
Determining Compliance Status
Each active construction spread will have at least one EM assigned to it each workday who will make field observations. The EM will check to see if the observed activity meets the relevant "Performance Criteria" (see Appendices) for (1) mitigation measures, (2) applicant-proposed measures and project parameters, (3) permit conditions and requirements, (4) approved plans, or (5) other project stipulations. If the activity meets the performance criteria, the activity will be recorded as "Acceptable." If the activity does not meet the performance criteria, the activity will be recorded as "Non-compliance," and the level of non-compliance will be determined.
6.9.2 Description
of Compliance Levels
Acceptable:
Activities comply with performance criteria set
for all applicable mitigation measures, applicant proposed
measures, permit requirements or conditions, approved plans, or
other project stipulations.
Non-Compliance:
Any deviation from applicable mitigation
measures, applicant proposed measures and project parameters,
permit conditions or requirements, and approved plans.
Violation levels are defined as follows:
Level 1 One of the performance
criteria has not been complied with resulting in only partial
implementation of a Mitigation Measure but no significant impact.
A written warning shall be submitted to PPSI
and corrective action shall be required within a stated maximum
period (24 hrs to 3 days, to be determined by CPUC/ANF designee).
If corrective action is not taken within the
stated period, a second written notice will inform PPSI that
unless the situation is rectified, a cessation of all
construction activities will be required within 24 hours.
Construction activities may be shut down until PPSI satisfies the
CPUC/ANF designees (Program Manager and the LEM) that the
situation has been remedied.
Level 2 One or more of the
performance criteria have not been complied with, making the
mitigation ineffective and resulting in minor impacts. If allowed
to continue, this non-compliance could result in significant
impact over-time.
An oral warning followed by a written notice
shall be submitted to PPSI. Corrective action shall begin by the
next construction day.
If corrective action is not begun by the next construction day, a cessation of all construction activities may be required. Construction activities may be shut down until PPSI satisfies the CPUC/ANF designees (Program Manager and the LEM) that the situation has been remedied.
Level 3 One or more of the
performance criteria are not complied with and the implementation
of a mitigation measure is deficient or non-existent, resulting
in significant impact(s), or there is immediate threat of major,
irreversible environmental damage or property loss.
An oral warning followed by written notice
shall be submitted to PPSI. Correction action shall begin
immediately.
Construction activities for the entire
construction spread may be shut down until PPSI satisfies the
CPUC/ANF, the CPUC/ANF designee (Program Manager), and other
involved agencies/parties that the situation has been remedied.
A pattern of repeated Level 1 or Level 2 non-compliances may also be reason to shut down construction activities until PPSI satisfies the CPUC/ANF and the CPUC/ANF designee (Program Manager), that the situation has been remedied.
6.9.3 Procedures
for Addressing Non-Compliance Events
Level 1 Non-Compliance Procedures.
The EM will promptly notify the LEM and will give the PPSI Spread
Superintendent, or his designee, a copy of the non-compliance
report the day the non-compliance is observed. If the EM is
unable to give the written report to the PPSI Spread
Superintendent, or his designee, the non-compliance will be
reported to the PPSI Spread Superintendent or his designee by
telephone and the report will be left in the PPSI Spread
Superintendent's office. In order to hasten corrective actions,
the EM may notify the appropriate PPSI Inspector directly. The
PPSI Spread Superintendent is responsible for ensuring that
remedial action is taken. The EM shall document all observations
and communications and conduct follow-up observations within 3
days. The LEM will notify Aspen's Program Management Team.
Level 2 Non-Compliance Procedures.
The EM will promptly notify the LEM and the PPSI Spread
Superintendent, or his designee, of the non-compliance. In order
to hasten corrective actions, the EM may notify the appropriate
PPSI Inspector directly. The EM will provide a copy of the
non-compliance report to the PPSI Spread Superintendent, or his
designee, the day the noncompliance is observed. The PPSI Spread
Superintendent is responsible for ensuring that remedial action
is taken. The EM will conduct follow-up observations within 24
hours. The LEM will notify Aspen's Program Management Team, who
will make the necessary agency notifications.
Level 3 Non-Compliance Procedures.
The EM will immediately notify the LEM and the PPSI Spread
Superintendent, or his designee, of the non-compliance. In order
to hasten corrective actions, the EM will notify the appropriate
PPSI Inspector directly. If a PPSI Inspector or the PPSI Spread
Superintendent cannot be located or contacted, the EM will notify
the contractor foreman. The EM shall not direct the work of the
Inspector, the contractor, or subcontractor. The EM shall
document all observations and communications in his/her Daily
Inspection Record. The LEM will notify Aspen's Program Management
Team, who will make the necessary agency notifications.
6.10 Dispute Resolution
PPSI will review the performance criteria set
by this document and before construction initiation and should
inform CPUC/ANF if they have any questions or disagreements with
performance criteria and violation levels stated in Appendices.
Upon agreement with the criteria, there should be few occasions
that PPSI and the monitors have a dispute. However, disputes may
arise and a process for their resolution is required.
Separate dispute resolution procedures shall be
followed for locations outside Angeles National Forest and
locations inside Angeles National Forest. These procedures shall
be used by Aspen team members, PPSI and its contractors and/or
subcontractors, other agencies, or the public regarding
mitigation compliance requirements.
6.10.1 Dispute
Resolution Outside of the Angeles National Forest
Should a dispute arise on interpretation of the
criteria, the following steps will be used for properties outside
of the Angeles National Forest:
Step 1 Disputes and complaints
(including those of the public) should be directed first to
CPUC's designated MMCRP Program Manager, Dr. Hamid Rastegar. Dr.
Rastegar, in consultation with CPUC/ANF will attempt to resolve
the dispute.
Step 2 Should this informal
process fail, the CPUC Project Manager, Martha Sullivan, may
initiate enforcement or compliance action to address deviations
from the Proposed Project or adopted Mitigation Monitoring
Program.
Step 3 If a dispute or
complaint regarding the implementation or evaluation of the
Program or the mitigation measures cannot be resolved informally
or though enforcement or compliance action by the CPUC, any
affected participant in the dispute or complaint may file a
written "Notice of Dispute" with the CPUC's Executive
Director. This notice should be filed in order to resolve the
dispute in a timely manner, with copies concurrently served on
other affected participants. Within 10 days of receipt, the
Executive Director or designee(s) shall meet or confer with the
filer and other affected participants for purposes of resolving
the dispute. The Executive Director shall issue an Executive
Resolution describing his/her decision, and serve it on the filer
and other affected participants.
Step 4 If one or more of the
affected parties is not satisfied with the decision as described
in the Resolution, such party(ies) may appeal it to the
Commission via a procedure to be specified by the Commission at
the time that a Final Mitigation Monitoring Program is adopted.
Parties may also seek review by the Commission
through existing procedures specified in the Commission's Rules
of Practice and Procedure, although a good faith effort should
first be made to use the foregoing procedure.
6.10.2 Dispute
Resolution Within the Angeles National Forest
Should a dispute arise on interpretation of the
criteria, the following steps will be used for properties inside
of the Angeles National Forest:
Step 1 Disputes and complaints
(including those of the public) should be directed first to ANF's
designated MMCRP Program Manager, Dr. Hamid Rastegar. Dr.
Rastegar, in consultation with CPUC/ANF will attempt to resolve
the dispute.
Step 2 Should this informal
process fail, the ANF District Ranger may initiate enforcement or
compliance action to address deviations from the Proposed Project
or adopted Mitigation Monitoring Program through enforcement of
the Special Use Permit.
Step 3 Written decisions of
the District Ranger related to the administration of the Special
Use Permit may be appealed (36CFR251 Subpart C) by PPSI.
6.11 Variance Procedures
Definition: A variance is (1)
any deviation from the description of the project as proposed in
the EIR or EIS/SEIR, or (2) a construction activity or practice
that is not carried out in accordance with approved construction
plans, mitigation measures, or other conditions of approval. Two
types of variances are addressed herein:
(1) Route and construction changes or
non-compliance with all specific mitigation measure requirements
proposed by PPSI prior to the start of construction, and
(2) Changes proposed by PPSI after construction
has started.
The CPUC and/or ANF or a designee (Aspen team
in consultation with Agencies, under authority of the MMCRP and
on behalf of the Agencies) has the authority to halt any
construction activity associated with the Pacific Pipeline
Project if the activity is determined to be a deviation from the
approved project or adopted mitigation measures and permit
conditions. Any deviation from the procedures identified in the
MMCRP must be approved in advance by CPUC and/or ANF or a
designee.
Environmental Monitors shall immediately report
any unapproved variances to the Lead Environmental Monitor (LEM).
The LEM will notify Aspen's Program Management Team, who will
contact the CPUC and/or ANF or a designee. Variances cannot be
approved by the LEM or Environmental Monitors (EM).
Procedure to Request Variance
Pre-Construction Variances.
When PPSI identifies a project change [including: route change;
change in description of the project (such as location of
valves); change in methods of compliance with mitigation measures
and other requirements (such as use of 500-year flood for
hydrologic mitigation measures studies); or proposed change in
construction methods (such as boring or directional drilling
instead of trenching at stream crossing)] a written request shall
be prepared and submitted to CPUC/ANF according to the procedure
defined in Exhibit 9 below, and as further described in Exhibit
10 on the following page.
Exhibit 9 MMCRP Procedures for Addressing Project or Mitigation Measure Changes
Type of Change or Action | Action Needed ** |
|
|
|
|
3. A measure cannot be successfully implemented (reference EIS/SEIR Section F.3.4, 2nd paragraph) | CPUC/ANF/Aspen staff to assess alternative mitigation and tell PPSI what is required in order to effectively address the impact identified |
4. Change to adopted mitigation measure (if the measure itself requires modification) [considered an official variance by CPUC] | CPUC:
PPSI must file a Petition to Modify (requiring service to
all parties; 20-30 day comment period; ALJ review;
possible evidentiary hearings; Commission decision) ANF: Depending on issue/severity, might require Supplemental EIS and/or new ROD |
** Potentially applicable to all issues: CPUC Dispute Resolution process (see F.3.3 of EIS/SEIR)
The proposed change, its location and/or
nature, shall be completely described. This explanation shall
refer to where the item to be changed was previously documented
(such as the page number of PEA, FEIS/SEIR, the milepost on the
original maps, and on latest submitted construction alignment
sheets, etc.). The original maps used as a basis for
identification of impacts in the 1993 FEIR and the 1996 FEIS/SEIR
are:
- 1993 FEIR. Drawings PPAR-1
to 68 and PPAR-ES1 to ES5, checked by RG and Dated 5-20-92.
- 1996 FEIS/SEIR. Drawings 117M-001 to 052, Job No. 93117, Revision A, Dated 5-25-94.
The reason and necessity for this proposed
deviation/change shall be fully described. An analysis shall be
presented to evaluate whether the proposed change would result
in:
- Any new significant impact
- An incremental increase in an identified impact
- A reduction in efficiency, nature, or
geographical location of a mitigation measure
This written request will be reviewed by the
Agency(ies) and a written determination on approval or rejection
of the proposed variance will be made.
Exhibit
10 FLOW CHART FOR PROJECT DESCR CHANGES
Note that this flow chart needs some edits - get them from Susan before sending out!
Variances Requested During
Construction. PPSI will review the Final Implementation
Plan approved by CPUC/ANF and will be aware of all performance
criteria outlined in this Plan. Any disagreement with these
requirements shall be discussed with CPUC/ANF at least 30 days
before the start of the construction. However, on rare occasions
and due to the site-specific conditions that could not be
anticipated in pre-construction phase, variances might be
required during the construction phase. In non-emergency cases,
at least 14 days prior to the specific construction activity or
implementation of mitigation measure for which a variance is
required, PPSI will submit to the CPUC and/or ANF (with a copy to
Aspen's Program Management Team) a written request for a
variance. The request will contain the following information:
Date of request
Location the variance will affect (spread, estimated milepost, and general description)
Which mitigation measure, applicant proposed measure, permit condition or requirement, approved plan, or other project stipulation the variance is being requested for, and a reference to the approved documents
An explanation of the necessity for the variance and the reason it was not anticipated in pre-construction phase or in project description
Discussion of any previous variances of a similar nature
An analysis that evaluates the occurrence of:
- New significant impact(s)
- Incremental increase in an identified impact
- Reduction in efficiency, nature, or geographical location of a mitigation measure
Date of expected construction at the variance
site.
In emergency cases the above information shall
be communicated as soon as possible to the LEM. The LEM and the
Aspen team will review these changes as soon as possible and
inform PPSI of their determination. Each short-notice variance
must be presented by PPSI in the manner described above; each
request will be considered on a case-by-case basis and responded
to as promptly as possible by Aspen, with recommendations made to
the Lead Agencies, as appropriate. If the variance is associated
with an immediate safety threat to human life or sensitive
resources (i.e., an imminent and immediate hazard ) and
EM/LEM/Program Manager cannot be contacted immediately, PPSI
shall take the appropriate action to preserve life, protect the
resource, and remove immediate hazard with minimum impacts on
other significant environmental resources. A full report on such
action shall be filed with the LEM within 72 hours.
6.12 Monitoring Criteria
Appendix A includes the full text of mitigation
measures and applicant-proposed measures, as well as the specific
criteria for monitoring the implementation of these measures and
requirements. Appendix B lists other agencies with responsibility
for permit issuance along the ROW.
6.12.1 General
Approach to Field Monitoring; Philosophy and Strategy
Monitoring Philosophy:
The proposed Pacific Pipeline Project went through an extensive
environmental review process managed by State and Federal lead
agencies. The major focus of the environmental review processes
was the identification of significant environmental impacts.
These impacts then, were assumed to be reduced by numerous
measures either recommended by the agencies or committed to by
the Applicant. After careful review of the analysis conducted in
these processes and documented in the more than 2000 page
EIS/SEIR and EIR, the Agencies' decision makers approved these
project subject to successful implementation of recommended
mitigation which was adopted as conditions for issuance of
appropriate permits. Thus, it is imperative that these adopted
conditions be implemented and that they achieve the reductions
they were designed for which were assumed in the final decisions.
The purpose of the monitoring program is to ensure compliance
with mitigation measures, applicant-proposed measures, approved
plans, and permit conditions and requirements in a
non-threatening manner using open and honest communication.
Monitoring Strategy.
Environmental monitors will be in the field every work day
monitoring construction activities. Emphasis will be placed on
sensitive sites (stream or fault crossings, sensitive habitats,
etc.) or activities (traffic control, for example). The strategy
is:
1. Through careful planning, and to the maximum
extent possible, anticipate potential scenarios that could cause
confusion or conflict, and attempt to reserve these problems in
the preconstruction phase of the project
2. Through training and communication, convey
the importance of this program to all parties involved.
3. Be very specific about the criteria that
would determine the full compliance with the intent of the
mitigation measures.
4. Use the flexibility, speed, storage
capacity, and communication capabilities of modern hardware and
software to track, manage, and document our activity as
systematically as possible.
5. Use experienced and trained monitors so that
they provide both an assurance of meeting the intent and spirit
of every mitigation and mature experience to deal with the progmation
required at the field and handling every changing circumstances.
6.12.2 Description
of Mitigation Measures from 1993 EIR and 1996 EIS/SEIR
As described in Section 6.1 (the history of the
Pacific Pipeline Project), two separate environmental documents
were prepared for this project, as necessitated by the
modifications to the project. The Final EIR, issued in 1993,
recommended numerous mitigation measures that covered the full
length of the pipeline from Santa Barbara County (the original
starting point of the project) to the refineries in Los Angeles.
However, based on the relocation of the origination point of the
project from Santa Barbara County to Emidio in south Kern County,
the mitigation measures specifically referring to impacts on
resources in Santa Barbara and Ventura County, are no longer
relevant, because the pipeline (as modified) would not traverse
these areas. However, the mitigation measures recommended in this
FEIR that are associated with the last 65 miles of the pipeline
(from the Castaic Junction to refineries) will remain in effect.
The FEIS/SEIR issued in January of 1996 focuses on that part of
the pipeline located between Emidio (the new origination point)
and the Castaic Junction, where the newly proposed segment will
join the originally proposed pipeline. Thus, the majority of the
mitigation measures proposed in this EIS/SEIR are associated with
this northern segment of the pipeline. However, based on some new
information or regulatory requirements (such as President's
Executive Order No. 12989), the EIS/SEIR also recommended
additional mitigation measures for the Castaic to refinery
segment of the pipeline. Appendix A of this Implementation Plan
has combined the two sets of the mitigation measures from both
documents, now addressing the full length of the modified
pipeline, from Emidio to refineries in Los Angeles area.
6.12.3 Approach to
Monitoring of Environmental Justice Mitigation Measures
This project is one of the first major projects
that has adopted mitigation measures to respond to the
President's Executive Order requiring that "Environmental
Justice" be addressed in an EIS. Most of these mitigation
measures will not be implemented at the construction site, but
throughout the areas with high-minority and low-income
populations that might be affected by pipeline construction and
operation. The LEM and EMs will be aware of the mitigation
monitoring efforts that will be occurring separate from
construction activities, so they can inform the public, agencies,
or PPSI/Contractor personnel, as appropriate. This section
describes those activities that will result from monitoring the
mitigation measures related to Environmental Justice (Section
C.16 of the EIS/SEIR).
Through the Public Access Program, Aspen will
maintain an active, visible, and flexible involvement with the
overall community outreach efforts for the project to ensure
monitoring of all activity in a representative and fair manner.
For example, the student intern group will be used, as
appropriate, to test the effectiveness of Environmental Justice
Mitigation Measures ML-1 through ML-8. Specific strategies
involved in monitoring these mitigation measures are as follows:
Community Outreach and Communications Program (ML-1). Aspen will request to be placed on PPSI's master community database for receipt of any public notices and mail-outs sent by PPSI for the Pacific Pipeline Project to ascertain whether notices and mail-outs provide comprehensive information and are appropriate. We will attend Community Liaison Group meetings periodically and on a random basis to assess community participation, provision of adequate communication services and project information, and overall community understanding and relationship with the project.
Community Partnership Program
(ML-2). Community organizations will be randomly
selected to assess their participation in the Community
Partnership Program, including job training, job opportunities
and overall receipt of project educational information. Ideally,
the CBO Survey described in Section 3.5, will include some of the
community organizations involved in this program. The online
Community Partnership Network will be tested periodically to
ensure that accurate and adequate project information is being
provided to the public. This includes testing the network at one
of the ten designated locations set up for access by PPSI.
Local Community and Minority-Owned Business Enterprise Hiring Program (ML-3). Quarterly reports will be obtained to assess PPSI's hiring practices as they relate to the surrounding minority and low-income communities, and whether those practices are representative of surrounding ethnic communities. Data in the reports would include residence of workers, ethnicity, socioeconomic data, types of jobs, and a list of construction unions including their involvement with Minority-Owned Business Enterprise (MBE) programs for the Pacific Pipeline Project. These quarterly reports will also include data on contracting of local (within 5 miles) and MBE firms for goods and services to reach a goal of 40%.
Attractive Landscaping in Open
Areas (ML-4). Aspen will review PPSI's landscaping
plans prior to implementation and provide appropriate input.
Construction and planting activities will be monitored to ensure
that PPSI is following the approved landscaping plan. Also,
periodic drive-throughs of the project area will be conducted for
appropriate buffering of project construction activity from
surrounding neighborhoods.
Communication of Potential
Emergencies to Non-English Speaking Populations (ML-5).
The demographic and language analysis of the surrounding
neighborhoods, prepared by PPSI, will be reviewed to determine
appropriate languages required for emergency communications. We
will verify the identification of communications specialists to
be consulted for development of emergency communications plans.
Aspen will also review media lists and translators lists,
identified by PPSI, to be used in the event of a and emergency.
For the operational phase of the project, Aspen
will request to be included on the emergency communications list
for any call-outs to the community in the event of and emergency.
Furthermore, community organizations will be randomly surveyed in
post-emergency situations to assess communication quality,
timeliness, and responsiveness.
Support of the Business Impact
Mitigation Plan (ML-6). Local businesses, impacted
by project construction, will be randomly surveyed to assess
their areas of concern. Also, the survey will include an
evaluation of what these businesses feel about the effectiveness
of local transit systems.
Oil Spill Response Equipment
(ML-7). Aspen will review PPSI's proposed placement
of oil spill response equipment in relation to population density
statistics to evaluate appropriate locations and sufficient
provision of response capabilities (operation phase).
Equal Application of Mitigation
Measures (ML-8). Aspen will observe the application
of mitigation measures across neighborhoods to ensure equity,
regardless of the particular visual or land use character of a
neighborhood.
6.12.4 Applicant-Proposed
Measures and Project Parameters from 1993 EIR and 1996 EIS/SEIR
In addition to the recommended (and
subsequently adopted) mitigation measures in both the FEIR (1993)
and FEIS/SEIR (1996), PPSI has proposed and committed themselves
to a number of measures that would mitigate potential impacts
associated with the project. Since these measures were proposed
by PPSI, they were assumed during preparation of the
environmental documents to be part of the Proposed Project. Thus,
the analysis of the impacts in both above documents was based on
full implementation of these measures and proposals. In order to
insure these measures are successfully implemented as proposed,
the Aspen team needs to monitor them as other mitigation
measures. These measures, and associated performance criteria,
are listed under each issue area in Appendix A.
Further, the project parameters (such as
thickness of the pipes, number/type/location of proposed valves)
affects the determination and analysis of potential impacts from
the project. The analysis and the identified impacts (and the
recommended mitigations) are all based on the assumptions that
the project will be built as described in the above two
documents. In order to insure that this assumption, upon which
the project was subsequently approved, remains true, we need also
to monitor the implementation of the major project parameters
described in the final document. These parameters are also listed
in Appendix A and will be monitored by the EMs and during the
plan review phase (pre-construction).
6.12.5 Responsible
and Cooperating Agencies
The two Lead Agencies (CPUC and ANF) have
adopted the mitigation measures recommended in the FEIR (1993)
and FEIS/SEIR (1996) as conditions for their approval decision
and attached them to their respective permits. Other responsible
agencies who have issued permits (or will issue permits in the
future) for this project (such as Franchise Permits issued by a
few cities) might stipulate certain conditions in their approval
processes. Aspen will coordinate our monitoring efforts with
these agencies by providing this Implementation Plan to them so
they are aware of the MMCRP requirements. The agencies issuing
these other permits are listed in Appendix B.
6.12.6 Other
Regulatory Requirements
The project will be built in compliance with
all applicable rules, regulations and policies of the agencies
which have jurisdiction over the project. These regulations and
laws were generally considered under each issue area in the
FEIS/SEIR and FEIR. For example, the Clean Air Act, which is the
most significant federal law protecting the quality of the air,
has been considered in the Air Quality issue area. The
requirements of this law are implemented by Federal, State, and
regional agencies. In very rare occasions, there might be other
environmental laws applicable to this project which are not
considered in the three categories of measures above (i.e.,
Mitigation Measures, Applicant Proposed Measures, Permit
Conditions) and were required by any agency during the
construction. The EMs will coordinate these requirements with
PPSI, the agency involved, and the Lead Agencies. These laws and
regulations are summarized in Appendix C for use as a reference
by the EMs.
6.13 Safety
Philosophy: Our team will take
all necessary steps to conduct this program with minimum risk and
to prevent potential safety hazards.
Responsibilities. Each
Environmental Monitor (including the LEM) is responsible for
his/her own safety and working safely is a condition of
employment. EMs are responsible for the timely and accurate
reporting of all reportable accidents or injuries (requiring more
than first aid) to their immediate supervisor.
Consumption of drugs and alcohol is strictly
prohibited during work hours. All Aspen employees have signed
their understanding of the Aspen's Drug-Free Policy. If an EM is
taking prescription medication, the LEM must be notified. This
information will be kept confidential unless the EM is involved
in a accident or injured and testing is required.
PPSI and the Contractor are responsible for
providing the training, tools and work environment to ensure that
EMs can perform their tasks safely. This includes teaching
compliance with all federal, state, local and company policies
and procedures. EMs are responsible for utilizing the tools and
training to perform their tasks safely.
Safety Equipment
The following safety equipment will be issued
to Environmental Monitors, installed in field vehicles, or stored
at the field office:
Personnel safety items:
Field Office:
first aid kit
Vehicle-related items:
Each EM/LEM is responsible for providing her/his own:
Environmental Monitors are expected to care for
the equipment that is assigned to them and to return all
equipment to Aspen at the conclusion of either their employment
or their task, whichever comes first. If required by Aspen
Managers, all equipment will be returned to Aspen immediately
upon request, at any stage of work or project.
Emergency Action Response
Initial emergency action response is the
responsibility of PPSI and the Contractor. The responsibility of
the Environmental Monitor is to assist as requested by PPSI or
the Contractor. PPSI or the Contractor will make all necessary
contacts.
If an Environmental Monitor is alone and
encounters an emergency situation, the following protocol
applies:
Call for help and provide the following information:
Attend to the injured person. If you do not have a current Red Cross certificate, only comfort the victim until trained help arrives.