STATE OF CALIFORNIA, PETE WILSON, Governor
June 26, 1997
RE: Variance Requests Number 1, 2, and 3
Dear Mr. Shauers:
We have reviewed the above-referenced requests, and our decisions follow. In addition, we have been informed that the Angeles National Forest concurs with our decisions.
Variance Request Number 1. - Amended 6/17/97: Change in construction time
Approved for modifying the construction start hour from 7:00 a.m. to 5:00 a.m. for those days the Forest Service determines that construction after 1:00 p.m. is prohibited. In addition, the following PPSI-proposed conditions should be implemented:
Pipe trucks and equipment trucks shall not use Old Ridge Route access before 7:00 a.m.
Signs to notify the public of construction activities will be posted close to the Paradise Ranch Development at least two weeks prior to construction in the area. Signs shall have a contact phone number for PPSI.
Construction activities shall be limited to 7:00 a.m. to 7:00 p.m. between Old Ridge Route (Milepost 49) and the Templin Highway crossing (Milepost 50.9).
Variance Request Number 2. - Amended 6/20/97: Change in requirement for watering ANF ROW
Denied for the following reasons:
- MP 40.85 to 41.75
- MP 45.05 to 45.75
- MP 48.75 to 49.25
Variance Request Number 3. - Amended 6/18/97: Correction to alignment sheets at West Liebre
Denied for the following reasons:
Sincerely,