STATE OF CALIFORNIA, PETE WILSON, Governor

PUBLIC UTILITES COMMISSION
505 VAN NESS AVENUE
SAN FRANCISCO, CA 94102-3298

 

June 26, 1997

 

Dean Shauers, Project Manager
Pacific Pipeline System, Inc.
12201 E. Arapahoe Road, C10
Englewood, CO 80112

RE: Variance Requests Number 1, 2, and 3

 

Dear Mr. Shauers:

We have reviewed the above-referenced requests, and our decisions follow. In addition, we have been informed that the Angeles National Forest concurs with our decisions.

Variance Request Number 1. - Amended 6/17/97: Change in construction time

Approved for modifying the construction start hour from 7:00 a.m. to 5:00 a.m. for those days the Forest Service determines that construction after 1:00 p.m. is prohibited. In addition, the following PPSI-proposed conditions should be implemented:

Variance Request Number 2. - Amended 6/20/97: Change in requirement for watering ANF ROW

Denied for the following reasons:

MP 40.85 to 41.75
MP 45.05 to 45.75
MP 48.75 to 49.25

Variance Request Number 3. - Amended 6/18/97: Correction to alignment sheets at West Liebre

Denied for the following reasons:

Sincerely,

 

Martha J. Sullivan
Project Manager

 

cc: R. Borden, ANF
H. Rastegar, Aspen

 

Back to Variances Pages