Approved Variances Summary Table Sorted by Variance No. (descending order)
|
|
|
Variance 130A | Allow for electrical testing seven days a week at valve locations along Segments 1 and 3. | 01/15/99 |
Variance 130 | Allow for electrical testing seven days a week at valve locations along Segments 2, 4, and 5 | 01/06/99 |
Variance 126-129 | Allow for extended construction hours along Segment 1, Kern County. | 12/17/98 |
Variance 124 + Clearance 76 | Variance 124 - Allow for above ground installation of the pipeline at
the Los Angeles Aqueduct High Speed Channel and construction of a 200 foot concrete cover,
instead of a bore installation as originally proposed, City of Los Angeles (Segment 3). Clearance #76 - Request for an extra work space along San Fernando Road for the subject installation and concrete cover, City of Los Angeles (Segment 3). |
11/08/98 |
Variance 122 | Allow for Sunday construction at the Emidio and Grapevine Pump Stations (Segment 1), El Segundo Station (Segment 4B), and Wilmington Station (Segment 5) | 11/08/98 |
Variance 121 | Allow for 24-hour completion testing activities (scraper testing, geometry inspection, hydrotesting, etc.), seven days a week, at specific locations along Segments 4 and 5. | 10/18/98 |
Variance 120 | To install temporary fill and dewater lines to be used during hydrostatic testing operations for portions of Segment 4. | 10/05/98 |
Variance 119 | To extend the construction start time from 7:00 a.m. to 6:00 a.m. for Segment 1 construction activities between the Emidio Pump Station (station number 00+00) and Gorman (station number 1334+89), Kern County. | 10/05/98 |
Variance 118 | allow for 24-hour hydrotesting activities on Sundays at the hydrotest locations identified in approved Variance Request #86. | 10/05/98 |
Variance 117 | Allow for Sunday construction on the Tejon Bench (between station numbers 873+32 and 1057+33), Kern County (Segment 1). | 10/05/98 |
Variance 116B | Sunday construction on the ANF from Copco Road south to Templin Highway (Segment 2A) | 09/17/98 |
Variance 116A | Allow for open cut trenching (instead of boring) of College Street, immediately east of Alameda Street in the Chinatown District of downtown Los Angeles, (Segment 4A). | 09/23/98 |
Variance 115 | Modify the stipulation to smart pig the pipeline prior to operation as required by Applicant proposed Mitigation Measure SS-49 | 12/17/98 |
Variance 113 | Reduce the refueling distance requirements (0.25 miles) stipulated by Mitigation Measure B-AQ-1) at Grapevine Creek, Pacoima Wash, and Tujunga Wash, Segment 3. | 10/18/98 |
Variance 112 | Install the project fiber optic conduit under the Santa Clara River via directional drill, Segment 2B. | 09/23/98 |
Variance 111 | Installation of a temporary 8-inch water line for hydrostatic testing, Segment 1. | 09/10/98 |
Variance 110 | Allow for Sunday construction on Segment 2C (Templin Highway to southern ANF boundary) and 24-hour construction at the Whitaker Pressure Relief Station during concrete work (also included within Segment 2C). | 08/27/98 |
Variance 109 | Extension of the project pipeline to serve the Huntway Refinery (a distance of approximately 1,600 feet), Carson, Segment 5. | 10/18/98 |
Variance 107+108 | Allow for nighttime construction within the City of Burbank, Segment 3. | 08/13/98 |
Variance 106 | Allow for nighttime construction (9:00 p.m. to 7:00 a.m.) along The Old Road and San Fernando Road between Weldon Canyon Road to beyond the Balboa Boulevard overpass (station numbers 3785+65 to 3904+61), Segment 2B. | 08/26/98 |
Variance 105 | Allow for open cut trenching (instead of boring) of Grandview Avenue, City of Glendale (Segment 3). | 08/11/98 |
Variance 104 | Reduce the refueling distance requirements (0.25 miles) stipulated by Mitigation Measure B-AQ-1)for stream courses along The Old Road and San Fernando Road, Segment 2B. | 08/11/98 |
Variance 101 | Extension of the project pipeline to serve the Edison Pipeline and Terminal Company (EPTC) (a distance of 250 feet), Los Angeles County, Segment 5. | 10/05/98 |
Variance 100 | Relocation of the project pipeline from station numbers 2686+84 to 2708+88 south of Templin Highway (a distance of 2204 feet), Los Angeles County and Angeles National Forest (ANF), Segment 2C. | 07/30/98 |
Variance 99 | Relocate the PPSI Pipeline Control Center from Taylor Yard to the ARCO Pipe Line Company Hynes facility, 5900 Cherry Avenue, Long Beach. | 12/23/98 |
Variance 98 | Relocation of the pipeline alignment between station numbers 4859+48 to 4862+51, from the west side of San Fernando Road to the east side of the roadway, City of Glendale (Segment 3). | 08/13/98 |
Variance 96 | Allow for nighttime construction at the Tuxford Avenue crossing, City of Los Angeles, Segment 3. | 07/30/98 |
Variance 94 | Modify the construction start time from 7:00 a.m. to 5:00 a.m. during the "High Fire Danger Season" on rural lands between Valencia Boulevard and McBean Parkway, Los Angeles County (Segment 2B). | 07/30/98 |
Variance 93 | Reduce the refueling distance requirements (0.25 miles) stipulated by Mitigation Measure B-AQ-1 at the Towsley Canyon bore (Stream Crossing #60), Segment 2B. | 07/30/98 |
Variance 92 | Relocation of the project pipeline from station numbers 2918+09 to 2953+89 north of Castaic (a distance of 3,580 feet), Los Angeles County, Segment 2C. | 07/31/98 |
Variance 91 | Allow for open cut trenching (instead of boring) of Lebec Road near the Tejon Ranch Headquarters, Kern County (Segment 1). | 07/02/98 |
Variance 90 | Reduce the refueling distance requirements (0.25 miles) stipulated by Mitigation Measure B-AQ-1 at the Compton Creek bore, City of Los Angeles, Segment 4B. | 06/29/98 |
Variance 89 | Relocation of the project pipeline from station numbers 767+60 to 777+54 through Tejon Ranch and CalTrans property in Kern County (a distance of 994 feet), Segment 1. | 07/31/98 |
Variance 88 | Relocation of 2457 feet of fiber optic conduit from the east side to the west side of the Metropolitan Transportation Authority (MTA) right-of-way between the Burbank Dog Pound exit location (station number 4646+96) and West Olive Avenue (station number 4671+53), Segment 3, City of Burbank. | 07/01/98 |
Variance 87 | Request to not use reclaimed water during nighttime construction activities at the Taylor Yard, Segment 3B. | 06/18/98 |
Variance 86 | Allow for 24-hour operations during hydrostatic testing activities on Segments 1, 2, and 3. | 06/6/98 |
Variance 85 | Extend the construction hours on the Angeles National Forest (ANF) to 5:00 a.m. to 8:00 p.m. between Mileposts (MP) 33 and 56.8, Monday through Saturday (Segment 2A) | 05/22/98 |
Variance 83-84 | Reduce the refueling distance requirements (0.25 miles) stipulated by Mitigation Measure B-AQ-1 at the Los Angeles River, Segment 3B. | 06/17/98 |
Variance 81 | Relocation of the project pipeline from the Alameda Corridor right-of-way to West Alameda Street, between Zoe Avenue (north of Florence) and just south of Southern Avenue (or 92nd Street) (a distance of approximately 9,726 feet), Segment 4. | 05/13/98 |
Variance 77 | Relocate the fiber optic conduit from the project right-of-way to the northbound lane of The Old Road, between station numbers 3227+20 to 3248+92, Segment 2B. | 06/17/98 |
Variance 76 | 24-hour construction and Sunday at the Interstate 105/110 (I-105/110) directional drill during the pull back operations. | 05/13/98 |
Variance 74 | Extend construction hours to 5:00 a.m. to 8:00 p.m., Saturdays and Sundays, at the Cornfield Yards, City of Los Angeles (Segment 3). | 05/01/98 |
Variance 73 | Reduce the refueling distance requirements (0.25 miles) stipulated by Mitigation Measure B-AQ-1 at the Los Angeles River, Segment 3. | 05/01/98 |
Variance 72 | Variance Request #72 (Resubmittal) - Allow for open cut trenching (instead of boring) of Polk Street, City of Los Angeles, (Segment 3). | 09/23/98 |
Variance 71 | Variance Request #71 (Resubmittal) - Allow for open cut trenching (instead of boring) of Bledsoe Street, City of Los Angeles, (Segment 3). | 10/05/98 |
Allow for open cut trenching of Ramona Avenue to install a High Density Polyethylene (HDPE) geomembrane to protect a new well within the City of Glendale along San Fernando Road (Segment 3). | 05/13/98 |
|
Variances 66+82 | Conducting a directional drill at the Cuddy Canyon Creek and Cuddy Canyon Tributary crossings | 05/16/98 |
Reduce the refueling distance requirements (0.25 miles) stipulated by Mitigation Measure B-AQ-1 at designated locations along the northern portion of Segment 1. | 05/13/98 |
|
Request for nighttime (7:00 pm to 7:00 am) construction at the Old Road and Magic Mtn. Parkway. | 04/09/98 |
|
Reduce the refueling distance requirements (0.25 miles) stipulated by Mitigation Measure B-AQ-1 at the California Aqueduct and Verdugo Wash, Segment 3. | 05/16/98 |
|
Modification to Mitigation Measure A-7 concerning two-minute idling of project vehicles. | 04/06/98 |
|
Request for route change across Newhall Land & Farming between stations #'s 3441+62 and 3498+33. | 04/23/98 |
|
Request for nighttime (5:30 pm to 6:00 am) and Sunday construction within MTA Taylor Yards. | 04/06/98 |
|
Request for 24-hour construction, including Sunday construction, at the "Dog Pound" directional drill, City of Burbank. | 03/25/98 |
|
Allow for construction seven days a week at the Gorman Slide directional drill sites and 24-hour construction during the pull back operation, Segment 1 | 03/30/98 |
|
Refueling within 0.25 miles of Dominguez Channel, Segment 4B. | 03/31/98 |
|
Relocate pipeline to accommodate railway changes required by the Alameda Corridor Project and improve entry point to Tosco Refinery. | 03/10/98 |
|
Pipeline realignment along Lebec Road near I-5 crossing to provide stable boring location, Segment 1. | 03/19/98 |
|
Refueling within 0.25 miles of streams along Peace Valley Road - two additional locations requested (see Variance Requests #32 and 43), Segment 1. | 03/13/98 |
|
Open cutting of Tuxford Street, City of Los Angeles, Segment 3. | 03/13/98 |
|
Open cutting of Birch Avenue, City of Hawthorne. | 02/19/98 |
|
Relocate pipeline to accommodate the Alameda Corridor Project. | 03/11/98 |
|
Refueling within 0.25 miles of streams along Peace Valley Road - additional location requested (see Variance Requests #32 & 43). | 02/11/98 |
|
Allow for overnight storage of construction and excavated materials with the right-of-way, Segment 4B. | 03/19/98 |
|
Open trench Ramona Avenue to install HDPE geomembrane protection. | 01/27/98 |
|
Relocated check & block valve at Dominguez Channel crossing, Segment 5. | 03/06/98 |
|
Relocate check valve from station #3240+81 to 3243+53 (Castaic Creek). | 01/29/98 |
|