STATE OF CALIFORNIA, PETE WILSON, Governor

PUBLIC UTILITES COMMISSION
505 VAN NESS AVENUE
SAN FRANCISCO, CA 94102-3298

October 5, 1998

Dean Shauers, Project Manager
Pacific Pipeline System, Inc.
12201 E. Arapahoe Road, C10
Englewood, CO 80112

RE: Variance Request #117 - Allow for Sunday construction on the Tejon Bench (between station numbers 873+32 and 1057+33), Kern County (Segment 1).

Dear Mr. Shauers:

The CPUC has reviewed the above-referenced request and approves your request, based on the following factors:

- All applicable mitigation measures for the project shall be implemented at the subject location.

- Prior to the commencement of Sunday construction, written land owner approval shall be provided to the CPUC Environmental Monitor.

- 48-hour notice shall be provided to the CPUC Lead Environmental Monitor prior to the commencement of Sunday construction.

- Implementation of this variance approval in accordance with the provisions noted above shall be verified on a random basis by a CPUC/ANF Environmental Monitor.

Sincerely,

Andrew Barnsdale
Project Manager