STATE OF CALIFORNIA, PETE WILSON, Governor
January 6, 1999
RE: Variance Request #130 - Allow for electrical testing seven days a week at valve locations along Segments 2, 4, and 5.
Dear Mr. Shauers:
We have reviewed the above-referenced variance request, and approve your request based on the following factors:
In accordance with Mitigation Measure N-1, pipeline construction activities shall occur between 7:00 a.m. and 7:00 p.m., Monday through Saturday (or for a shorter period if stipulated by applicable noise ordinance).
Extended construction hours have been requested by PPSI to facilitate the completion of loop and point-to-point electrical testing between the valve sites and the SCADA Control Center.
Electrical testing would be conducted by crews of 3 to 5 personnel, plus a PPSI inspector. No motorized equipment other than pickups and small generators would be necessary.
The measures noted below shall be implemented:
- All applicable mitigation measures shall be implemented during electrical testing, including noise abatement.
- As proposed, traffic controls shall be implemented in accordance with approved Traffic Plans and Watchbook requirements.
- No electrical testing shall occur at valve sites located within 300 feet of residences on Sundays.
- Implementation of this variance in accordance with the provisions noted above shall be verified on a random basis by a CPUC/ANF Environmental Monitor.
Sincerely,