U.S.D.A. Forest Service
Saugust Ranger District
30800 Bouquet Canyon Road
Saugus, CA 91350
(805) 296-9710

 

File Code: 2720 Pacific Pipeline

Variance Request No. 18

Date: September 23, 1997

 

Dean Shauers, Project Manager
Pacific Pipeline System, Inc.
12201 E. Arapahoe Road, C10
Englewood, CO 80112

Via FAX 303-792-0227

Dear Mr. Shauers:

This letter will approve revised Variance Request No. 18 from Kenneth J. Lord, dated September 22, 1997, to allow for Sunday construction on the ANF through October 31, 1997. This approval is subject to the following conditions:

This decision is subject to administrative review under 36 CFR 251. Requests for review must comply with that section and be filed with the Forest Supervisor within 45 days.

 

MIKE WICKMAN
District Ranger
 
cc: M. Sullivan, 415-703-1184
H. Rastegar, 818-597-8001
R. Borden, 818-574-5233
H. Sarkissian, 818-556-2749
K. Lord 714-540-4881

Back to Variances Pages

Back to MMCRP Home Page