File Code: 2720 Pacific Pipeline
Variance Request No. 22
Date: September 25, 1997
Via FAX 303-792-0227
Dear Mr. Shauers:
This letter constitutes denial of Variance Request No. 22 from Kenneth J. Lord, dated September 19, 1997, regarding the modification of the ANF Fire Protection Plan to allow for specific construction equipment to continue to work beyond the Level IIIb activity restrictions during cleanup and restoration. This denial is based on the following reason:
The potential for sparks during the use of equipment.
This decision is subject to administrative review under 36 CFR 251. Requests for review must comply with that section and be filed with the Forest Supervisor within 45 days.