|  
             Welcome to the California Public Utilities Commission (CPUC) website 
              for the California Environmental Quality Act (CEQA) review of the 
              proposed Sunrise Powerlink Transmission Line Project. Applications 
              for this project were submitted to the CPUC on December 14, 
              2005 (A.05-12-014) and August 4, 2006 (A.06-08-010). This site 
              provides access to public documents and information relevant to 
              the CEQA and National Environmental Policy Act (NEPA) review processes. 
             Background 
            SDG&E has filed an application with the CPUC to construct the 
              Sunrise Powerlink Project (SRPL). The CPUC is the CEQA lead agency 
              and the U.S. Bureau of Land Management (BLM) is the lead agency 
              under NEPA. This project was approved by the California Independent 
              System Operator on August 3, 2006. The Proponent's Environmental 
              Assessment was filed with the CPUC on August 4, 2006 and is 
              available on SDG&E's 
              project website. 
            The CPUC maintains other webpages for documents related to its 
              proceeding on the SRPL, where it makes available documents filed 
              by parties to that proceeding. The two webpages for Applications 
              A.06-0-8010 
              and A.05-12-014 
              list documents and rulings filed in the proceedings. The CPUC also 
              maintains a page of general 
              information on the SRPL project. 
            The SRPL Project, as proposed by SDG&E, includes a new, approximately 
              90-mile 500 kV line from Imperial Valley Substation (in Imperial 
              County, near the City of El Centro) to a new Central East Substation 
              (in central San Diego County, south of the intersection of County 
              Highways S-22 and S-2). The 500 kV portion 
              would approximately follow the eastern boundary of BLM lands west 
              of El Centro and SR 78, and would pass through Anza-Borrego 
              Desert State Park. 
            The SRPL Project also proposes approximately 60 miles of 230 kV transmission 
            lines from the new Central East Substation to SDG&E's existing 
            Peñasquitos Substation (in the City of San Diego). SDG&E 
            proposes to construct two segments underground (one segment south 
            of Ramona and another in the community of Ranchos Peñasquitos, 
            San Diego). Figure 1 shows 
            an overview of the proposed project route. 
            Data Requests 
            The EIR/EIS Team will submit Data Requests to SDG&E when it 
              needs specific information to support EIR/EIS preparation. These 
              requests will be made available here at the time they are issued. 
              Data requests submitted to SDG&E to date are provided below. 
              Responses to these data requests can be found at SDG&E's 
              website. 
            Data Request No. 1 (September 27, 
              2006) 
              Data Request No. 2 (November 15, 
              2006)  
              Data Request No. 3 (November 21, 
              2006) 
            Public Scoping 
            Part 1 of Scoping. On August 31, 2006, the BLM published 
              its Notice of Intent to prepare an 
              Environmental Impact Statement in the Federal Register (Volume 71, 
              No. 169, page 51848). On September 15, 2006, the CPUC 
              issued a Notice of Preparation/Notice 
              of Public Scoping Meetings for an Environmental Impact Report/Environmental 
              Impact Statement. In early October 2006, the CPUC and BLM held a 
              series of seven public scoping meetings in Imperial and San Diego 
              Counties to take public comment on the scope and content of the 
              environmental document. The scoping comment period ended on October 20, 
              2006. 
            A Scoping Report has been prepared 
              and was sent to all repositories on November 29, 2006; see 
              the list of available documents below. The Scoping Report includes 
              a copy of every letter submitted, as well as transcripts of the 
              public scoping meetings and summaries of issues raised during scoping. 
             Part 2 of Scoping. Additional public meetings will be held 
              in early 2007 to obtain public comment on alternatives. Notices 
              of those meetings and the timeframes during which comments on alternatives 
              will be accepted will be posted here and mailed to all those on 
              the NEPA/CEQA mailing list. A second part of the Scoping Report 
              will be prepared to summarize all comments received (including oral 
              comments made at the Scoping Meetings). 
            Documents Available 
            The following documents are available 
              at 26 libraries and offices in the 
              project area. 
              SDG&E's 
              Application and Proponent's Environmental Assessment (August 4, 
              2006). 
              Notice of Intent 
              (August 31, 2006) 
              Notice of Preparation 
              (NOP) (September 15, 2006) 
             
              
                NOP Figure 1. 
                  Proposed Project Overview 
                  NOP Figure 2. Imperial Valley 
                  Link 
                  NOP Figure 3. Anza-Borrego 
                  Link 
                  NOP Figure 4A. Central Link 
                  NOP Figure 4B. Proposed 
                  Central East Substation 
                  NOP Figure 5A. Inland Valley 
                  Link 
                  NOP Figure 5B. Detail of 
                  Ramona Area 
                  NOP Figure 6A. Coastal Link 
                  NOP Figure 6B. Rancho Peñasquitos 
                  Detail 
                  NOP Figure 7. SDG&E Alternatives 
                  Fully Evaluated and Carried Forward in PEA 
                  NOP Figure 8. SDG&E Alternatives 
                  Considered and Eliminated 
               
             
              Scoping Report, Part 1 
            (November 29, 2006) 
            For Additional Information 
            To request additional information or to be added to the mailing 
              list, please contact us by email, fax, or phone, as follows: 
            
            The CPUC's Project Manager is: 
            Billie Blanchard, CPUC Project Manager 
              California Public Utilities Commission 
              505 Van Ness Avenue 
              San Francisco CA 94102 
              Tel. (415) 703-2068 
              Fax (415) 703-2200 
              Email:  bcb@cpuc.ca.gov 
           |