             Welcome to the California Public Utilities Commission (CPUC) website 
              for the California Environmental Quality Act (CEQA) review of the 
              proposed Sunrise Powerlink Transmission Line Project. Applications 
              for this project were submitted to the CPUC on December 14, 
              2005 (A.05-12-014) and August 4, 2006 (A.06-08-010). This site 
              provides access to public documents and information relevant to 
              the CEQA and National Environmental Policy Act (NEPA) review processes. 
             Background 
            SDG&E has filed an application with the CPUC to construct the 
              Sunrise Powerlink Project (SRPL). The CPUC is the CEQA lead agency 
              and the U.S. Bureau of Land Management (BLM) is the lead agency 
              under NEPA. This project was approved by the California Independent 
              System Operator on August 3, 2006. The Proponent's Environmental 
              Assessment was filed with the CPUC on August 4, 2006 and is 
              available on SDG&E's 
              project website. 
            The CPUC maintains other webpages for documents related to its 
              proceeding on the SRPL, where it makes available documents filed 
              by parties to that proceeding. The two webpages for Applications 
              A.06-0-8010 
              and A.05-12-014 
              list documents and rulings filed in the proceedings. The CPUC also 
              maintains a page of general 
              information on the SRPL project. 
            The SRPL Project, as proposed by SDG&E, includes a new, approximately 
              90-mile 500 kV line from Imperial Valley Substation (in Imperial 
              County, near the City of El Centro) to a new Central East Substation 
              (in central San Diego County, south of the intersection of County 
              Highways S-22 and S-2). The 500 kV portion 
              would approximately follow the eastern boundary of BLM lands west 
              of El Centro and SR 78, and would pass through Anza-Borrego 
              Desert State Park. 
            The SRPL Project also proposes approximately 60 miles of 230 kV transmission 
            lines from the new Central East Substation to SDG&E's existing 
            Peñasquitos Substation (in the City of San Diego). SDG&E 
            proposes to construct two segments underground (one segment south 
            of Ramona and another in the community of Ranchos Peñasquitos, 
            San Diego). Figure 1 shows 
            an overview of the proposed project route. 
            Data Requests 
            The EIR/EIS Team will submit Data Requests to SDG&E when it 
              needs specific information to support EIR/EIS preparation. These 
              requests will be made available here at the time they are issued. 
              Data requests submitted to SDG&E to date are provided below. 
              Responses to these data requests can be found at SDG&E's 
              website. 
            Data Request No. 1 (September 27, 
              2006) 
              Data Request No. 2 (November 15, 
              2006)  
              Data Request No. 3 (November 21, 
              2006) 
            Public Scoping Meetings 
            On August 31, 2006, the BLM published its Notice 
              of Intent to prepare an Environmental Impact Statement in the 
              Federal Register (Volume 71, No. 169, page 51848). On September 
              15, 2006, the CPUC issued a Notice of 
              Preparation/Notice of Public Scoping Meetings for an Environmental 
              Impact Report/Environmental Impact Statement. In early October 2006, 
              the CPUC and BLM held a series of seven public scoping meetings 
              in Imperial and San Diego Counties to take public comment on the 
              scope and content of the environmental document. Transcripts from 
              the seven scoping meetings are available here: 
             
              El Centro - 4:30 
                p.m. October 2, 2006 
                Ramona - 4:00 p.m. 
                October 3, 2006 
                Ramona - 7:00 p.m. 
                October 3, 2006 
                Borrego Springs - 2:00 
                p.m. October 4, 2006 
                Borrego Springs - 
                6:30 p.m. October 4, 2006 
                San Diego (Mission 
                Valley) - 2:00 p.m. October 5, 2006 
                San Diego 
                (Rancho Peñasquitos) - 6:30 p.m. October 5, 2006  
             
             The scoping comment period ended on October 20, 2006, but 
              additional public meetings will be held in the future to obtain 
              public comment on alternatives. Notices of those meetings and the 
              timeframes during which comments on alternatives will be accepted 
              will be posted here and mailed to all those on the NEPA/CEQA mailing 
              list. A Scoping Report will be prepared, summarizing 
              all comments received (including oral comments made at the Scoping 
              Meetings). This report will be posted on this website and copies 
              will be placed in local document repository sites listed under "Documents 
              Available" below.  
            Documents Available 
            The following documents are available 
              at 18 libraries and offices in the 
              project area. 
               SDG&E's 
              Application and Proponent's Environmental Assessment (August 4, 
              2006). 
                 Notice of Intent 
              (August 31, 2006) 
                 Notice of Preparation 
              (NOP) (September 15, 2006) 
                 
            
               
                | Note: 
                  Some of the files displaying the figures for the NOP (below) 
                  are large and may display slowly. For faster results in displaying 
                  these files, right-click the file's link, click "Save 
                  Target As" to download the file to a folder on your computer, 
                  then browse to that folder and double-click the downloaded file. 
                  Or, if you wish, send an email to sunrise@aspeneg.com 
                  and request a CD containing these figures, which will be promptly 
                  mailed to you. The second option is recommended for anyone with 
                  a dialup connection to the Internet. | 
               
             
            NOP Figure 1. 
              Proposed Project Overview (1.6 MB) 
              NOP Figure 2. Imperial Valley 
              Link (1.8 MB) 
              NOP Figure 3. Anza-Borrego Link 
              (0.5 MB) 
              NOP Figure 4A. Central Link 
              (2.0 MB) 
              NOP Figure 4B. Proposed Central 
              East Substation (0.5 MB) 
              NOP Figure 5A. Inland Valley 
              Link (2.7 MB) 
              NOP Figure 5B. Detail of Ramona 
              Area (2.4 MB) 
              NOP Figure 6A. Coastal Link 
              (2.2 MB) 
              NOP Figure 6B. Rancho Peñasquitos 
              Detail (2.5 MB) 
              NOP Figure 7. SDG&E Alternatives 
              Fully Evaluated and Carried Forward in PEA (1.8 MB) 
              NOP Figure 8. SDG&E Alternatives 
              Considered and Eliminated (2.2 MB) 
            For Additional Information 
            To request additional information or to be added to the mailing 
              list, please contact us by email, fax, or phone, as follows: 
            
            The CPUC's Project Manager is: 
            Billie Blanchard, CPUC Project Manager 
              California Public Utilities Commission 
              505 Van Ness Avenue 
              San Francisco CA 94102 
              Tel. (415) 703-2068 
              Fax (415) 703-2200 
              Email:  bcb@cpuc.ca.gov 
           |