Welcome
to the California Public Utilities Commission (CPUC) website for the
California Environmental Quality Act (CEQA) review of LS Power Grid
California, LLC’s (LSPGC) Collinsville 500/230 Kilovolt (kV) Substation
Project (Project). LSPGC filed an application for a Certificate of
Public Convenience and Necessity (CPCN) for the Project on July 29,
2024 (Application No. A2407018). A summary of the Proposed Project is
provided in the following section.  
 
This website provides access to public documents and information
relevant to the CEQA review process. Information about each project
review phase
will be provided in the following sections once available. 
 
 
      Summary of the Proposed Project 
      
      The California Independent System Operators (CAISO) 2021-2022 Transmission Plan identified the Proposed Project as a needed upgrade to the California electric grid. The Proposed Project is located in Solano, Sacramento, Alameda, and Contra Costa counties within an existing regional transmission system that provides electricity to the northern Greater Bay Area. The main components of the Proposed Project include the following:       
      
        - Constructing a new 500/230 kV substation ("Collinsville Substation"). The proposed substation site is located adjacent to Stratton Lane and approximately 0.8-mile northeast of the unincorporated community of Collinsville. 
 
- Constructing two self-supporting segments of new 500 kV conductor and  structures roughly parallel along the approximately 1.2-mile interconnection  route (or “loop”) between the proposed LSPGC Collinsville Substation and  Pacific Gas and Electric Company’s (PG&E) existing Vaca Dixon-Tesla 500 kV  Transmission Line, resulting in the addition of approximately 2.5 miles of new  500 kV transmission lines. In addition, PG&E would install and/or modify transposition structures at four locations along  PG&E’s existing Vaca Dixon-Tesla 500 kV  Transmission Line. 
 
- Constructing a new approximately 6-mile-long, double-circuit 230 kV transmission line that would connect the proposed LSPGC Collinsville Substation to PG&E’s existing Pittsburg Substation; approximately 1.0 mile would be installed overhead, approximately 4.5 miles would be installed beneath the Sacramento-San Joaquin River Delta waterways (6 to 15 feet below the sediment surface), and approximately 0.6 mile would be installed underground. 
 
- Extending and connecting an existing PG&E 12 kV distribution line to the proposed substation (approximately 0.9 mile along and parallel to the Stratton Lane). 
 
- Constructing new telecommunications lines collocated with the new 230 kV transmission line and extending into the City of Pittsburg (approximately 1.2 miles) and constructing a new microwave tower immediately adjacent to the proposed substation. 
 
- Modifying PG&E’s existing Pittsburg, Vaca Dixon, and Tesla substations, to support the new substation interconnection. All PG&E substation modifications would occur within the existing substation footprints. 
 
 
      
      Environmental Review Process 
      
      Application and
Proponent's Environmental Assessment 
      LSPGC
        filed Application No. A2407018 and Proponent's Environmental Assessment
        (PEA) for the Proposed Project on July 29, 2024. The application is available at the CPUC Proceeding webpage. The PEA and other supporting materials are available here.  
         
      Application Review (Deficiency Reports and Data Requests) 
       
      The CPUC submitted deficiency reports and data requests to LSPGC regarding their application information.  CPUC requests and LSPGC responses are
available here. LSPGC's application was deemed complete on December 11, 2024. A copy of the letter deeming their application complete is available here. 
      In addition, the CPUC also submitted data requests to PG&E regarding portions of the project that would be constructed by
PG&E. CPUC requests and responses are available here. 
        
       
      Scoping 
 
        The CPUC is soliciting scoping comments regarding environmental impacts  to address in the EIR and potential project alternatives to consider. The  scoping comment period is for 30 days from January 7, 2025, through February 6,  2025. The comment period closes on February 6, 2025 at 5:00pm. The NOP is available here and includes methods for submitting scoping comments.  The CPUC conducted a virtual public scoping  meeting on January 21, 2025. The scoping meeting presentation is available for  viewing here. 
      All scoping comments received during the scoping period are available for viewing here. A copy of the Scoping Report is available here. 
      Environmental Impact Report 
 
The
CPUC released the Draft  Environmental Impact
Report (DEIR) for public review on November 4, 2025. A  copy of the Notice of Availability is available here. The Draft EIR and supporting materials are available here. 
Written comments on the Draft EIR will be accepted for 45 days. Comments must be submitted by 5:00 p.m. on December 19, 2025. Include your name, address, and phone number or email address so we may contact you for clarification if necessary. Send written comments via email to collinsville@panoramaenv.com or via U.S. mail to: 
 
California Public Utilities Commission 
Collinsville 500/230 Kilovolt Substation Project
c/o Panorama Environmental, Inc.
717 Market Street, #400, San Francisco, CA 94103
Virtual Public Meeting.  In order for members of the public and regulatory agencies to have an opportunity to submit verbal comments on the Draft EIR, a virtual public metting will be held on Tuesday, November 18, 2025 from 3:00-5:00 p.m. via Zoom webinar. Meeting attendance information is provided as follows: 
Date: Tuesday, November 18, 2025 
  Time: 3:00 p.m. - 5:00 p.m. 
  Webinar link: https://us02web.zoom.us/j/84704287366 
  Telephone Call-in Option: (669) 444-9171 
  Webinar ID: 847 0428 7366 
ADDITIONAL INFORMATION 
 
The
CPUC, through its Environmental Review Team, is managing the
environmental review of the Proposed Project. To request additional
information or to be added to the CEQA contact list, please contact us
at: 
Email:
collinsville@panoramaenv.com 
Phone: (650)
290-7213   
 
The CPUC Project Manager is: 
 
Connie Chen, Public Utilities Regulatory Analyst 
California Public Utilities Commission, Energy Division 
505 Van Ness Avenue, San Francisco, CA 94102 
 
 
 
Email:
connie.chen@cpuc.ca.gov 
 
Phone: (415) 703-2124 
 
  | 
 
 
 |