|  
             Welcome to the California Public Utilities Commission (CPUC) website 
              for the California Environmental Quality Act (CEQA) review of the 
              proposed Sunrise Powerlink Transmission Line Project. Applications 
              for this project were submitted to the CPUC on December 14, 
              2005 (A.05-12-014) and August 4, 2006 (A.06-08-010). This site 
              provides access to public documents and information relevant to 
              the CEQA and National Environmental Policy Act (NEPA) review processes. 
             Background 
            SDG&E has filed an application with the CPUC to construct the 
              Sunrise Powerlink Project (SRPL). The CPUC is the CEQA lead agency 
              and the U.S. Bureau of Land Management (BLM) is the lead agency 
              under NEPA. This project was approved by the California Independent 
              System Operator on August 3, 2006. The Proponent's Environmental 
              Assessment was filed with the CPUC on August 4, 2006 and is 
              available on SDG&E's 
              project website. 
            The CPUC maintains other web pages for documents related to its 
              proceeding on the SRPL, where it makes available documents filed 
              by parties to that proceeding. The web page for Application A.06-08-010 
              incorporates the earlier filing, and lists documents and rulings 
              filed in the proceedings. The CPUC also maintains a page of general 
              information on the SRPL project. 
            The SRPL Project, as proposed by SDG&E, includes a new, approximately 
              90-mile, 500 kV line from Imperial Valley Substation (in Imperial 
              County, near the City of El Centro) to a new Central East Substation 
              (in central San Diego County, south of the intersection of County 
              Highways S22 and S2). The 500 kV portion would 
              approximately follow the eastern boundary of BLM lands west of El 
              Centro and SR 78, and would pass through Anza-Borrego Desert 
              State Park. 
            The SRPL Project also proposes approximately 60 miles of 230 kV 
              transmission lines from the new Central East Substation to SDG&E's 
              existing Peñasquitos Substation (in the City of San 
              Diego). SDG&E proposes to construct two segments underground 
              (one segment south of Ramona and another in the community of Ranchos 
              Peñasquitos, San Diego). Figure 1 
              shows an overview of the proposed project route.  
            EIR/EIS Scoping 
            On August 31, 2006, the BLM published its Notice 
              of Intent to prepare an Environmental Impact Statement in the 
              Federal Register (Volume 71, No. 169, page 51848). On 
              September 15, 2006, the CPUC issued a Notice 
              of Preparation/Notice of Public Scoping Meetings for an Environmental 
              Impact Report/Environmental Impact Statement. In early October 2006, 
              the CPUC and BLM held a series of seven public scoping meetings 
              in Imperial and San Diego Counties to take public comment on the 
              scope and content of the environmental document. The scoping comment 
              period ended on October 20, 2006. 
            A Scoping Report (Part 1) was prepared 
              and was sent to all repositories on November 29, 2006; see the list 
              of available documents below. The Scoping Report includes a copy 
              of every letter submitted, as well as transcripts of the public 
              scoping meetings and summaries of issues raised during scoping. 
            Decisions on EIR/EIS Alternatives 
            January 2007 Notice of Second Round of Scoping Meetings on Alternatives 
              to the Proposed Sunrise Powerlink Project. The CPUC and BLM 
              held a second scoping period during January and February 2007 in 
              order to hear input on alternatives to the Sunrise Powerlink Project. 
              The comment period ended on February 24, 2007. A second 
              Scoping Report was prepared that documents all comments received 
              during the second scoping period, including copies of all comment 
              letters and transcripts of oral comments made at the February 5-9, 
              2007 Public Meetings on Alternatives. The Scoping Report (Part 2) 
              is included in the document list below and copies have been placed 
              in local document repository sites. 
             
            March 2007 Notice on Alternatives Conclusions. The CPUC/BLM 
              Notice Regarding Conclusions on EIR/EIS Alternatives to the Proposed 
              Sunrise Powerlink Project was mailed to everyone on the project 
              mailing list during the week of March 19, 2007. The Notice 
              and the seven maps referenced in it may be viewed at the links presented 
              below under "Documents Available." 
            May 2007 Notice on Modified Route D Alternative. The conclusions 
              presented in the March Notice referenced above were based on the 
              feedback received from the public and agencies, along with research 
              conducted by the EIR/EIS team. Following the publication of that 
              Notice, additional input was received from the Cleveland National 
              Forest (Forest), including Forest's request that an alternative 
              be fully analyzed in the EIR/EIS that would not require an amendment 
              to the Forest's 2005 Land Management Plan. As a result, portions 
              of the Route D Alternative that were previously considered 
              and eliminated have been combined with new route segments, and will 
              be analyzed in the EIR/EIS. The CPUC/BLM 
              Notice Regarding an Additional EIR/EIS Alternative to the Proposed 
              Sunrise Powerlink Project was mailed in mid-May to announce 
              this change. 
            The May Notice announced a third 30-day public comment period that 
              ended in mid-June 2007. The comment letters 
              that were received during May and June 2007 are available for review. 
            From mid-June through September 2007, the EIR/EIS Team reviewed 
              comments on the Modified Route D Alternative and evaluated 
              suggested route changes. Public comments were accepted into early 
              October 2007, in order to allow concerns about this alternative 
              to be reviewed by the EIR/EIS team. The comment 
              letters that were received between mid-June and October 2007 
              are available for review. 
            Documents Available 
            Except as noted with an asterisk (*), 
              the following documents are available at 28 
              libraries and offices in the project area. 
              Comment letters received 
              on the Modified Route D Alternative from mid-June to October 2007 
              Comment letters received in 
              response to the May 16, 2007 Notice on the Modified Route D 
              Alternative* 
              CPUC/BLM Notice Regarding 
              an Additional EIR/EIS Alternative to the Proposed Sunrise Powerlink 
              Project (May 16, 2007) 
              Scoping Report, Part 2 
              (April 2, 2007) 
              Notice Regarding 
              Conclusions on EIR/EIS Alternatives to the Proposed Sunrise Powerlink 
              Project (March 16, 2007) 
             
               
                Figure 
                  1. Imperial Valley Link Alternatives 
                  Figure 2. 
                  Anza-Borrego Link Alternatives  
                  Figure 3. Central 
                  Link Alternatives 
                  Figure 4. 
                  Inland Valley Link Alternatives 
                  Figure 
                  5. Coastal Link Alternatives Retained 
                  Figure 
                  6. Coastal Link Alternatives Eliminated 
                  Figure 
                  7. Southwest Powerlink Alternatives 
               
             
              Notice of Second 
              Round of Scoping Meetings on Alternatives to the Proposed Sunrise 
              Powerlink Project (January 22, 2007) 
             
               
                Figure 1. 
                  Sunrise Powerlink Project Overview 
                  Figure 2. Imperial Valley 
                  Link Alternatives 
                  Figure 3. Anza-Borrego Link 
                  Alternatives  
                  Figure 4. Central Link Alternatives 
                  Figure 5. Inland Valley Link 
                  Alternatives 
                  Figure 6. Coastal Link Alternatives 
                  Retained 
                  Figure 7. Coastal Link Alternatives 
                  Eliminated 
                  Figure 8. Southwest Powerlink 
                  Alternatives 
                  Figure 9. Non-Wires Alternatives 
                  Figure 10. System Alternatives 
                   
               
             
              Scoping Report, Part 1 
              (November 29, 2006) 
              Notice of Preparation 
              (NOP) (September 15, 2006) 
             
               
                Figure 1. 
                  Proposed Project Overview 
                  Figure 2. Imperial Valley 
                  Link 
                  Figure 3. Anza-Borrego Link 
                  Figure 4A. Central Link 
                  Figure 4B. Proposed Central 
                  East Substation 
                  Figure 5A. Inland Valley 
                  Link 
                  Figure 5B. Detail of Ramona 
                  Area 
                  Figure 6A. Coastal Link 
                  Figure 6B. Rancho Peñasquitos 
                  Detail 
                  Figure 7. SDG&E Alternatives 
                  Fully Evaluated and Carried Forward in PEA 
                  Figure 8. SDG&E Alternatives 
                  Considered and Eliminated 
               
             
              Notice of Intent 
              (August 31, 2006) 
              SDG&E's 
              Application and Proponent's Environmental Assessment (August 4, 
              2006). 
            Data Requests 
            The EIR/EIS Team will submit Data Requests to SDG&E when it 
              needs specific information to support EIR/EIS preparation. These 
              requests will be made available here at the time they are issued. 
              Data requests submitted to SDG&E to date are provided below. 
              Responses to these data requests can be found at SDG&E's 
              website. 
             
              Data Request No. 1 (September 
                27, 2006) 
                Data Request No. 2 (November 15, 
                2006)  
                Data Request No. 3 (November 21, 
                2006) 
                Data Request No. 4 (December 6, 
                2006) 
                Data Request No. 5 (January 8, 
                2007) 
                Data Request No. 6 (January 26, 
                2007) 
                Data Request No. 7 (February 1, 
                2007) 
                Data Request No. 8 (February 16, 
                2007) 
                Data Request No. 9 (March 27, 2007) 
                Data Request No. 10 (April 23, 
                2007) 
                Data Request No. 11 (May 7, 2007) 
                Data Request No. 12 - original 
                (May 15, 2007) 
                Data Request No. 12 - modified 
                (June 27, 2007)  
                Data Request No. 13 (May 21, 2007) 
                Data Request No. 14 (June 1, 2007) 
                Data Request No. 15 - original 
                (June 27, 2007) 
                Data Request No. 15 - modified 
                (July 27), 2007) 
                Data Request No. 16 (July 6, 2007) 
                Data Request No. 17 (July 27, 
                2007) 
             
            For Additional Information 
            To request additional information or to be added to the mailing 
              list, please contact us by email, fax, or phone, as follows: 
            
            The CPUC's Project Manager is: 
            Billie Blanchard, CPUC Project Manager 
              California Public Utilities Commission 
              505 Van Ness Avenue 
              San Francisco CA 94102 
              Tel. (415) 703-2068 
              Fax (415) 703-2200 
              Email:  bcb@cpuc.ca.gov 
           |