|  
             Welcome to the California Public Utilities Commission (CPUC) website 
              for Pacific Gas and Electric's (PG&E's) proposed Windsor Substation 
              Project. An application for this project was submitted to the CPUC 
              on April 21, 2010 (A.10-04-024). The project was reviewed by 
              CPUC in accordance with the California Environmental Quality Act 
              (CEQA) and a Mitigated Negative Declaration (MND) was prepared. 
             This site provides access to public documents and information relevant 
              to the permitting, CEQA review, and construction of the Windsor 
              Substation Project. 
             PROJECT STATUS 
             The Final MND was adopted by the CPUC on April 3, 2014 in 
              Decision D.14-03-031. In accordance with CEQA, a Mitigation Monitoring, 
              Compliance, and Reporting Plan (MMCRP) was prepared to ensure compliance 
              with the mitigation measures approved in the MND. The MMCRP is available 
              here (6.4MB). 
              PG&E started construction of the Windsor Substation Project 
              in November 2016 and completed construction in June 2018. The Final 
              Monitoring Report can be found here. 
             Pre-construction 
              Compliance 
             Notices to Proceed (NTPs) are being issued by CPUC by subsection 
              of the project as requested by PG&E. NTP #1 for the construction 
              of the substation component of the project was issued by CPUC on 
              June 15, 2016, and is available here. 
              NTP #2 for the reconductoring work along Old Redwood Highway 
              and the Fulton No. 1 line was issued by CPUC on March 30, 2017, 
              and is available here. Issuance of 
              NTPs is contingent upon PG&E's compliance with pre-construction 
              requirements as specified by the approved mitigation measures and 
              responsible agency permitting requirements. 
             Other responsible agency permits required for construction, and 
              their amendments, are listed in the MMCRP (see above). Prior to 
              construction, PG&E was required to submit the following surveys 
              and plans/programs. Surveys were field validated by the CPUC EM: 
             
              - Sensitive Biological Habitat Survey Reports
 
              - Bird Nesting Survey Reports 
 
              - Special-status Bat Survey Reports
 
              - Restoration Plans
 
              - Storm Water Pollution Prevention Plans (SWPPPs)
 
              - Construction Site Monitoring Program (CSMP)
 
              - Worker Environmental Awareness Program Plans
 
             
            Other compliance plans requiring CPUC and/or permit agency review 
              and approval included the following: 
            
              - Landscaping Plan (available here)
 
              - Spill Prevention Control and Countermeasure Plans (available 
                here)
 
              - Hazardous Substance Control and Emergency Response Plan (available 
                here)
 
               
             
            Construction Monitoring 
              and Minor Project Change Review 
            Construction activities began November 2, 2016. CPUC Environmental 
              Monitors are monitoring construction activities to ensure that construction 
              is being conducted in accordance with the approved mitigation measures 
              and permit conditions. Monitoring reports documenting construction 
              and compliance can be viewed here. 
            As final engineering is completed or as construction necessitates, 
              Minor Project Changes (MPCs) are being submitted for the Project. 
              Each of these requests is reviewed by CPUC to ensure that no new 
              impacts or increase in impact severity would result from the requested 
              change. Table 1 provides a summary of the MPCs submitted for 
              the Windsor Substation Project. 
            
               
                 
                    
                    Table 1. Minor Project Changes (MPCs) 
                       
                 | 
               
               
                | MPC No. | 
                 
                   Date 
                    Requested 
                 | 
                 
                   Date  
                    Issued 
                 | 
                Phase | 
                Description | 
               
               
                | MPC #1 | 
                 
                   5/17/16 
                 | 
                 
                   6/15/16 
                    Approved under NTP #1 
                 | 
                Windsor Substation  | 
                Design change to Spill Prevention Control 
                  and Countermeasure (SPCC) retention pond and stormwater flow. 
                  MPC #1 was incorporated into NTP #1. | 
               
               
                |  
                   MPC #2 
                 | 
                 
                   5/17/16 
                 | 
                 
                   6/15/16 
                    Approved under NTP #1 
                 | 
                Windsor Substation  | 
                Use of water truck or driwater 
                  pods instead of irrigation system for landscaping. MPC #2 
                  was incorporated into NTP #1. | 
               
               
                |  
                   MPC #3 
                 | 
                 
                   5/17/16 
                 | 
                 
                   6/15/16 
                    Approved under NTP #1 
                 | 
                Windsor Substation  | 
                Replacement of culverts in existing 
                  roadways entering substation site and Herb Lane. MPC #3 
                  incorporated into NTP #1. | 
               
               
                |  
                   MPC #4 
                 | 
                 
                   8/11/16 
                 | 
                 
                  
                 | 
                Windsor Substation  | 
                Revision of the Conceptual Landscape 
                  Plan based on final design and engineering. | 
               
               
                |  
                   MPC #5 
                 | 
                 
                   2/17/17 
                 | 
                 
                   3/30/17 
                    Approved under NTP #2 
                 | 
                Reconductoring & 12 kV Line 
                  Underbuild | 
                Use of crane staged on SMART tracks 
                  to replace certain poles along the Fulton No. 1 Power Line submitted 
                  with NTP Request #2. | 
               
               
                |  
                   MPC #6 
                 | 
                 
                   2/17/17 
                 | 
                 
                   3/30/17 
                    Approved under NTP #2 
                 | 
                Reconductoring & 12 kV Line 
                  Underbuild | 
                Final design and engineering revision 
                  to the tubular steel pole (TSP) west of the substation submitted 
                  with NTP Request #2. | 
               
               
                |  
                   MPC #7 
                 | 
                 
                   2/17/17 
                 | 
                 
                   3/30/17 
                    Approved under NTP #2 
                 | 
                Reconductoring & 12 kV Line 
                  Underbuild | 
                Changes to tree trimming and removal 
                  due to construction method changes (crane use on SMART tracks) 
                  submitted with NTP Request #2. | 
               
               
                |  
                   MPC #8 
                 | 
                 
                   2/17/17 
                 | 
                 
                   3/30/17 
                    Approved under NTP #2 
                 | 
                Reconductoring & 12 kV Line 
                  Underbuild | 
                Additional pull and tension site located 
                  on Railroad Avenue between Poles a32 and a33 submitted with 
                  NTP Request #2. | 
               
               
                |  
                   MPC #9 
                 | 
                 
                   6/5/17 
                 | 
                 
                  
                 | 
                Reconductoring & 12 kV Line 
                  Underbuild | 
                Reconfiguration of distribution line 
                  crossing of Old Redwood Highway and pole changes. | 
               
               
                |  
                   MPC #10 revised 
                 | 
                 
                   9/11/17 
                 | 
                 
                  
                 | 
                Reconductoring & 12 kV Line 
                  Underbuild | 
                Use of an additional temporary staging 
                  yard. | 
               
               
                |  
                   MPC #11 
                 | 
                 
                   2/1/18 
                 | 
                 
                  
                 | 
                Reconductoring & 12 kV Line 
                  Underbuild | 
                Increase the height of pole a35 on 
                  the Fulton No. 1 60 kV line. | 
               
               
                |  
                   MPC #12 
                 | 
                 
                   2/13/18 
                 | 
                 
                  
                 | 
                Reconductoring & 12 kV Line 
                  Underbuild | 
                Use of drone instead of ground equipment 
                  to facilitate installing the new distribution underbuild on 
                  the Fulton No. 1 60 kV line. | 
               
             
              
              BACKGROUND 
            Project Description 
            The originally proposed Windsor Substation Project site was located 
              on Mitchell Lane in the southern part of the Town of Windsor, Sonoma 
              County, California. Subsequent to its original Application, PG&E 
              amended its Application and submitted a Supplemental PEA for substation 
              sited at a different location. The new site is in the northern part 
              of the Town, on Old Redwood Highway at Herb Road, between Highway 
              101 and the Northwestern Pacific Railroad (NWPRR) right of way. 
            Electrical power would enter the substation by tapping the existing 
              Fulton No. 1 60 kV power line that parallels the west 
              side of the NWPRR right of way. Electrical power would leave the 
              substation as 12 kV via distribution feeder lines, which would 
              interconnect with the distribution network. Construction involves 
              the installation of the following components: 
            
              - Construction of a 3-bank 115/12 kilovolt substation on 2.6 acres 
                of a 4.11-acre parcel on Old Redwood Highway at Herb Road in the 
                Town of Windsor, California. The substation would consist of the 
                following at full buildout: 
 
                 
                
                  - Three 115 kV bus structures
 
                   
                  - Six 115 kV circuit breakers
 
                   
                  - Three 115/12 kV power transformers
 
                   
                  - Eighteen 115 kV disconnecting switches
 
                   
                  - Three 12 kV metal-clad switchgear enclosures
 
                   
                  - Twelve 12 kV distribution circuits
 
                   
                  - Three 30 MVA power transformers
 
                   
                  - Connection of the new substation to on the Fulton No. 1 
                    60 kV power line by way of a new tubular steel pole [TSP] 
                    replacing an existing wood pole
 
                   
                  - Two 42-foot-high dead-end structures within the substation 
                    supporting the 60 kV power line entering and exiting 
                    the substation
 
                     
                   
                 
               - Pole replacement and line work along Old Redwood Highway, Starr 
                Road, Gumview Road, Wilcox Road, Starr Circle, Railroad Avenue 
                and Joni Court.
 
                 
               
              - Underground distribution lines connecting the substation to 
                existing and future infrastructure.
 
                 
               
              - Rebuilding approximately 1.5 miles of the existing Fulton No. 
                1 60 kV power line, requiring replacement 39 wooden poles (with 
                38 wood poles and 1 steel pole) and installation of 2 new wood 
                riser poles.
 
                 
               
              - Reconductoring approximately 1.8 miles of existing distribution 
                line with 12 kV double-circuit conductor along Old Redwood Highway, 
                requiring replacement of 44 wooden poles with taller wood poles 
                and installation of 3 additional wood riser poles.
 
             
            Proponent's Environmental 
              Assessment (PEA) 
            PG&E filed a PEA with the Application 
              in April 2010. A Supplemental PEA 
              was submitted in May 2011. The PEA provides a starting point for 
              the independent environmental review process conducted by the CPUC. 
              In addition, PG&E's Notice of an Application for a Permit to 
              Construct can be found here. 
            Environmental 
              Review Process 
            PG&E's Application and PEA were deemed complete for review 
              by the CPUC on May 20, 2010. However, the PEA was replaced 
              by the Supplemental PEA, submitted in 2011. The CPUC evaluated the 
              substation site and related project elements identified in the Supplemental 
              PEA. 
            The CPUC determined that an Initial Study/Mitigated Negative Declaration 
              (IS/MND) appeared to be the appropriate CEQA document to prepare 
              for this project. After it was prepared, the Draft IS/MND was published 
              and the public and agencies had an opportunity to comment on the 
              document. Based on the Draft IS/MND, CPUC determined that an EIR 
              was not required. 
            Draft Initial 
              Study/Mitigated Negative Declaration 
            On July 15, 2013, the CPUC released a Notice of Intent to Adopt 
              a Mitigated Negative Declaration for the Windsor Substation Project 
              showing that the Proposed Project, as mitigated, would not have 
              any significant effects on the environment. The Draft Mitigated 
              Negative Declaration and Supporting Initial Study (IS/MND) can be 
              viewed here. 
            The Draft IS/MND underwent a public review period from July 15, 
              2013 through August 14, 2013. 
            Final Initial 
              Study/Mitigated Negative Declaration 
            After the close of the comment period, CPUC prepared a Final Mitigated 
              Negative Declaration for the Windsor Substation Project. The Final 
              IS/MND can be viewed here. The study 
              showed that the Proposed Project, as mitigated, would not have any 
              significant effects on the environment. The Final MND provides details 
              on the Proposed Project, evaluates and describes its potential environmental 
              impacts, identifies those impacts that could be significant, and 
              presents mitigation measures to avoid or minimize these impacts. 
            Public Information Meeting 
            The CPUC Energy Division held a public information meeting on August 16, 
              2010, to describe the then-proposed project, describe the CEQA process, 
              and receive public comments on the proposal. Written comments were 
              submitted at this meeting. Subsequent to the meeting, PG&E identified 
              its alternate site and submitted a supplemental PEA. 
            For Additional 
              Information 
            To request additional information, please contact: 
            Eric Chiang, Project Manager 
              California Public Utilities Commission 
              c/o Aspen Environmental Group 
              235 Montgomery Street, Suite 935 
              San Francisco, CA 94104-3002 
           |