Last Update: October 2025 
            ** Public Scoping closed on April 30, 2025. CPUC is currently preparing the draft CEQA document. ** 
            Welcome to the California Public Utilities Commission (CPUC) website 
              for the environmental review and monitoring of Southern California Gas Company (SoCalGas)'s Ventura Compressor  Modernization  Project (the  Proposed Project). The CPUC is the lead agency under the California  Environmental Quality Act (CEQA) for the Proposed Project and is therefore  responsible for evaluating the Proposed Project’s potential environmental  impacts. 
             
                
              
            CPUC Review Process
            Following  receipt of a complete application for a Certificate of Public Convenience and  Necessity (CPCN), the CPUC conducts two parallel processes when considering  development proposed by a regulated utility: an application process, in which  the CPUC reviews the utility’s proposal and considers whether the project is  needed and is in the public interest; and an environmental review process  pursuant to CEQA. The CPCN application process focuses on utility ratepayer and  public benefit issues and is undertaken by the CPUC’s Administrative Law Judges  Division. The CEQA process for utility applications is led by the CPUC’s Energy  Division. The CPUC will use the CEQA document in conjunction with other  information prepared for the CPUC’s formal record to act on SoCalGas’s  application. 
               
              Click here for more information about the CPUC’s decision and review process for natural gas infrastructure. 
               
              Click here for information and documents associated with the CPUC’s Proceeding for the project. 
  
            Project Overview 
            The Proposed Project would  modernize the Ventura Compressor Station, located at 1555 North Olive Street in  the City of Ventura. The scope of the Proposed Project includes:  
            
              (1) replacing  three existing 1,100 horsepower (HP) natural-gas-driven compressors (natural  gas compressors) with two new 1,900 HP natural gas compressors, equipped with  state-of-the art emission control technology to meet Best Available Control  Technology (BACT) standards, and two new 2,500 nominal HP (estimated  horsepower), electric-motor-driven compressors (electric compressors), with  zero nitrogen oxide (NOx) emissions, resulting in a “hybrid” compressor  station;  
              (2) erecting a new 10,458-square-foot compressor building;  
              (3)  erecting a new 4,641-square-foot permanent office building;  
              (4) erecting a new  5,459-square-foot warehouse;  
              (5) installing a new 8-foot-tall perimeter block  wall to replace the existing west and south chain-link fence/block wall; and   
              (6) implementing other ancillary site improvements, such as piping  interconnection and storage tanks.  
             
            The existing compressor equipment and  temporary office facilities would be decommissioned approximately one year after  the new facility has become fully operational.  
            Proponent's Environmental Assessment 
            A  Proponent's Environmental Assessment (PEA) was submitted by SoCalGas  concurrently with the application (A.23-08-019), dated August 24, 2023. 
            CPUC  Staff Review of PEA 
            CPUC General  Order (GO) 177 for Gas Infrastructure requires the CPUC Energy Division  CEQA Unit Staff to determine if the PEA meets the requirements of GO 177, which  are defined in the CPUC’s 2019 Guidelines for Energy Project Applications  Requiring CEQA Compliance: Pre-filing and Proponent’s Environmental  Assessments, including a PEA Checklist. CEQA Unit Staff and contractor, Aspen  Environmental Group reviewed the PEA and identified deficiencies in two reports. If necessary, the CPUC will issue additional data requests and post them here. 
            
            The CPUC Energy  Division CEQA staff found the PEA to be complete on October  30, 2024. 
            Project Scoping
The CPUC released a Notice  of Preparation (NOP) of an EIR for the Project to solicit agency and  public input on the scope of the EIR. The typical 30-day scoping period,  beginning February 28, 2025, was extended to close on April 30, 2025. All  interested parties, including responsible and trustee agencies, groups, and the  public, were invited to provide input on the scope and content of the EIR. 
Lea el aviso en español: aquí. 
The CPUC held one virtual public scoping meeting on March  11, 2025 and one in-person meeting on April 15, 2025.  The slides for  the April 15, 2025, scoping  meeting presentation  are available: here. 
An audio recording of the April 15, 2025, scoping meeting  presentation is available: here. 
Transcripts of the recorded scoping meetings are available:  here. 
Written scoping comments submitted to CPUC are available:  here. 
The Scoping Report is available: here. 
Preparation of the CEQA Environmental Document
The environmental  review process for the Ventura Compressor Modernization Project is underway,  and the CEQA document is being drafted. The CPUC plans to publish the CEQA  environmental document in late-2025. 
The CPUC Project Manager for the  CEQA review process is: 
John E. Forsythe, CPUC Project Manager  
  California Public Utilities Commission (CPUC) 
  Energy Division  
  CEQA and Energy Permitting Section 
  300 Capitol Mall, Suite 518  
  Sacramento, CA 95814 
  Email:  john.forsythe@cpuc.ca.gov 
Comments & Questions  
To comment on the environmental review or to be added to the mailing  list for future environmental documents and notices, please contact us at:
 
   |