STATE OF CALIFORNIA
PUBLIC UTILITIES COMMISSION

Southern California Edison's
West of Devers Upgrade Project

(Application A.13-10-020, filed October 25, 2013)


Files linked on this page in Portable Document Format (PDF). To view them, you will need to download the free Adobe Acrobat Reader if it is not already installed on your PC. Note: For best results in displaying the largest files (see sizes shown in parentheses below for files larger than 5 MB), right-click the file's link, click "Save Target As" to download the file to a folder on your hard drive, then browse to that folder and double-click the downloaded file to open it in Acrobat.
Presiona aquí para ver información en español.


Welcome to the California Public Utilities Commission (CPUC) website for the environmental review and monitoring of Southern California Edison's (SCE's) West of Devers Upgrade Project (WOD Project). The project is located in incorporated and unincorporated portions of Riverside and San Bernardino Counties, California; a map is provided here. SCE submitted a Certificate for Public Convenience and Necessity (CPCN) application for the Project to the CPUC on October 25, 2013 (Application A.13-10-020). The Proposed Project has been reviewed under both the California Environmental Quality Act (CEQA) and the National Environmental Policy Act (NEPA). The CPUC approved the project in Decision D.16-08-017, including two alternatives, on August 18, 2016. The BLM approved the project with its Record of Decision on December 27, 2016

The CPUC is the CEQA lead agency and the Bureau of Land Management (BLM) is the NEPA lead agency. This website provides access to public documents and information relevant to the CEQA review processes and mitigation monitoring. The BLM project website can be accessed here. An overview of the approved Project, construction and monitoring status, and previous CEQA/NEPA review is provided below.

DESCRIPTION OF APPROVED PROJECT

SCE filed a CPCN application for the West of Devers Upgrade Project with the CPUC and filed a Plan of Development with the BLM.

According to SCE, the Project is needed to facilitate the full deliverability of new electric generation resources being developed in eastern Riverside County. As renewable energy generating facilities come on-line in eastern Riverside County, the WOD Project will allow the transfer of this electricity into the Los Angeles area. The Project will facilitate progress towards meeting California's Renewable Portfolio Standard goals requiring utilities to produce 33% of their electricity sales from renewable energy sources by 2020.

The Project includes the following major components:

  • Removal and upgrade of existing 220 kV transmission lines. Upgrades would occur on 30 miles of the Devers–El Casco line, 14 miles of the El Casco–San Bernardino line, 43 miles of the Devers–San Bernardino line, 45 miles of the Devers-Vista No. 1 and No. 2 lines, 3.5 miles of the Etiwanda–San Bernardino line, and 3.5 miles of the San Bernardino-Vista line.

  • Upgrade substation equipment at Devers, El Casco, Etiwanda, San Bernardino, and Vista Substations to accommodate increased power transfer on 220 kV lines.

  • Upgrade Timoteo and Tennessee 66/12 kV substations to accommodate 66 kV subtransmission line relocations.

  • Removal and relocation of 2 miles of two existing 66 kV subtransmission lines.

  • Removal and relocation of 4 miles of existing 12 kV distribution lines.

  • Installation of telecommunication lines and equipment for the protection, monitoring, and control of transmission lines and substation equipment.

The Project will be located within the existing West of Devers right-of way corridor in incorporated and unincorporated areas of Riverside and San Bernardino Counties. The ROW passes through the reservation trust land of the Morongo Band of Mission Indians and the cities of Banning, Beaumont, Calimesa, Colton, Grand Terrace, Loma Linda, Palm Springs, Rancho Cucamonga, Redlands, San Bernardino, and Yucaipa (see project map). SCE anticipates that the WOD Project will be operational by 2022.

The Project as originally proposed by SCE was modified in several locations by two alternatives adopted by the CPUC and the BLM: The Tower Relocation Alternative and the Iowa Street Underground Alternative.

CONSTRUCTION STATUS AND MITIGATION MONITORING

The CPUC, BLM, and SCE have prepared a Mitigation Monitoring, Compliance, and Reporting Plan (MMCRP), which is posted here (13.0MB). The MMCRP ensures compliance with the mitigation measures adopted in the Final EIR and Final EIS. The MMCRP provides for Environmental Monitors and defines the reporting relationships, roles and responsibilities, and procedures for environmental compliance on the Project. The MMCRP will be updated to reflect schedule changes and other revisions, as needed.

Notices to Proceed (NTPs) were reviewed and issued by CPUC or BLM, as applicable, by subsection of the project as requested by SCE. Issuance of NTPs was contingent upon SCE's compliance with pre-construction requirements as specified by the approved mitigation measures and responsible agency permitting requirements. Table 1 below summarizes the NTPs issued by CPUC and BLM.

Table 1. Construction NTPs
NTP No.
Description Status
1
Contractor Yards (10 total) Issued by CPUC 06/29/17
2
Substation Upgrades Issued by CPUC 06/29/17
3
Subtransmission, Distribution, Telecom, Issued by CPUC 08/10/17
4
Transmission Line Issued by CPUC 09/05/17
5
Transmission Line, BLM Lands Only Issued by BLM 03/29/18 (8.0MB)

SCE has completed final engineering and the preparation of compliance plans and ancillary permit acquisition required for construction. The plans describe specific actions to be taken by SCE and its contractors to address various impacts or issues. Final plans approved to date are available here..

Construction on the West of Devers Upgrade Project began October 2, 2017, with the start of substation upgrades and telecommunication improvements. Establishment of laydown yards started in February 2018. Subtransmission, distribution, and remaining telecom started in April 2018. Construction of the approved transmission system upgrades began in May 2018, with completion scheduled for four years later, in 2022. Substation upgrades will continue intermittently during this period, as well as subtransmission and distribution improvements.

CPUC Environmental Monitors are in the field to verify the proper implementation of project mitigation measures, and permit and compliance plan requirements during construction. Monitoring reports documenting construction and compliance activities are available here.

As final engineering is completed or as construction necessitates, Minor Project Refinements (MPRs) are submitted for the Project. Each of these requests is reviewed by CPUC to ensure that no new impacts or increase in impact severity would result from the requested change. MPRs approved for the project are summarized below.

Table 2. Minor Project Refinements
MPR #
MPR Request Submittal Date
Description
Date Approved
#1
Minor modifications of Maraschino telecom route. November 22, 2017
#2
Additional work space for Maraschino Telecom construction. December 14, 2017
#3
Adjustment to the Oak Valley Telecom alignment. December 28, 2017
#4
Continued use of 2 hydrants for Telecom construction. January 3, 2018
#5
Access paths for Telecom construction. January 22, 2018
#6
2/8/18
Ten water sources to support construction activities February 12, 2018
#7
Extension of temporary water and power lines to the Poultry Material Yard. February 28, 2018
#8
New splice location for telecom work and a new pole location for transmission line work. March 2, 2018
#9
Use of the existing access road, three additional work areas, and walking paths for the Telecom work near the El Casco Substation. March 27, 2018
#10
Modification to some work areas approved under NTP #1 and NTP #3. April 9, 2018
#11
Relocation of 5 subtransmission structures from the east side to the west side of Nevada Street. May 8, 2018
#12
Additional work area in the City of Redlands in support of activities approved under NTP #3. May 17, 2018
#13
5/23/18 (5.4MB)
18 additional water sources to support construction activities. May 25, 2018
#14
Modification of four approved sub transmission work areas in the cities of Redlands and Loma Linda in support of NTP #3 activities. May 31, 2018
#15
Paving the Poultry Material Yard access road and parking/staging area. June 5, 2018
#16
Realignment of the Smith Creek HDD and new access paths required for Devers-Valley OPGW stringing along Coyote Trail. June 13, 2018
#17
Additional work areas and location adjustments of the distribution and subtransmission alignment approved under NTP #3. June 23, 2018
#18
Additional work area for subtransmission vault installation and use of a potable water hydrant to support transmission line activities. August 7, 2018
#19
Additional work areas in Segment 4 to support transmission line activities approved under NTP #4. August 20, 2018
#20
Use of an unpaved public road to provide construction access to Smith Creek Telecom Crossing work area to support telecom activities approved under NTP #3. August 27, 2018
#21
Use of existing water source locations, a temporary water tower installation, an access road north of Supersite 3X46-N, and expansion of Supersite WSS-4-4N64-MPR-19 to support transmission line activities approved under NTP #4 October 10, 2018
#22
Minor changes to the San Bernardino-Redlands-Timoteo 66-kV Subtransmission Circuit Cutover and the Devers-Vista OPGW Connection November 20, 2018
#23
Additional work areas in Segment 3 to support transmission line activities approved under NTP #4. December 21, 2018
#24
Additional work area in Loma Linda to support wire stringing activities associated with construction at San Bernardino Junction approved under NTP #4. January 28, 2019
#25
Additional work area west of Supersite 3X55 to facilitate tower construction and stringing activities in Colton approved under NTP #4. March 14, 2019
#26
Use of Prado Lane access road (Segment 2) and two existing hydrants (Segment 6). April 5, 2019
#27
Use of 2 existing water hydrants (Segment 1), temporary above-ground water tank installation (Segment 2), and temporary helicopter hook-up area at El Casco Substation (Segment 3) May 1, 2019
#28
Extra work space areas, including helicopter landing zones and access roads, on Segments 1, 2, and 6. June 6, 2019
#29
Extra work space areas for equipment/material staging, wire stringing, and telecom work, on Segments 3, 4, and 6. July 3, 2019
#30
Extra work space areas to facilitate underground and overhead cable removal on Segments 4 and 6. August 6, 2019
#31
Extra workspace areas and access road to facilitate Segments 2 and 4 transmission line work. October 8, 2019
#32
Extra workspace areas and access road to facilitate Segments 4 and 6 transmission line work. November 27, 2019
#33
Construction of a temporary artificial nest stand to facilitate the relocation of a red tail hawk nest. January 9, 2020
#34
Extra workspace areas to facilitate Segments 1, 3, and 4 wire stringing and wreck-out. New access road to the Matich Material Yard, Segment 5. March 2, 2020
#35
New Segment 2, 4, and 6 work areas to facilitate wire stringing and wreck-out activities, improve management of stormwater, and add a helicopter landing zone. April 15, 2020
#36
New Segment 6 work area for guard pole installation. May 8, 2020
#37
6/3/20 (5.6MB)
Installation of scour protection measures at seven Segment 6 tower sites and three new temporary work areas (Vista Substation and Segment 3). June 8, 2020
#38
Additional work areas for material/equipment staging, installation of McCarthy drains, and erosion repairs, Segments 2, 3, and 4. July 7, 2020
#39
Additional work areas for wire stringing and wreck-out activities, Segment 3, 4, and 6. July 23, 2020
#40
Additional MAC drains on Segments 2 and 3, additional wire stringing work area at Construction Aream 4S56, and a fire hydrant on Segment 2. September 18, 2020
#41
Additional MAC drains at Segment 3 Supersite 3X64. October 16, 2020
#42
Additional work area for wire stringing and wreck-out activities in Segment 3. November 12, 2020
#43
Replacement of several McCarthy drains, the installation of a retaining wall, and for two permanent nest platforms. January 4, 2021
#44
Temporary work area to support wire wreck-out activities in Segment 3. February 17, 2021
#45
Work areas in Segments 3, 4, and 6 for guard sites, drains, and wire site. March 16, 2021
#46
Work areas, McCarthy drains, VR-3a exemption. April 13, 2021
#47
Rip rap installation, extra work area, and VR-3a exemption at 5 locations. May 21, 2021
#48
Expanded work area to accommodate the relocation of a retaining wall June 4, 2021
#49
Transfer of materials to Beaumont–Cherry Valley Recreation and Park District July 7, 2021
#50
Additional work area for McCarthy drain installation. August 25, 2021
#51
Exclusion of 95 work areas from restoration requirements due to non-project related continued disturbances. October 21, 2021
#52
Additional work to complete erosion repairs. January 9, 2022
#53
Slope stabilization at one location. February 11, 2022
#54
Erosion repairs at five locations. March 23, 2022


ENVIRONMENTAL REVIEW AND PROJECT APPROVAL

Proponent's Environmental Assessment (PEA) and Application

SCE filed an application and PEA for the WOD Project on October 25, 2013.

The CPUC conducted a 30-day completeness/deficiency review and, based on the review of the PEA, sent deficiency letters to SCE on November 25, 2013, and February 18, 2014, indicating that the PEA remained incomplete. Based on additional information provided by SCE, on September 11, 2014, the CPUC determined that the application and PEA were complete.

Environmental Review History

Notice of Preparation (NOP) and Notice of Intent (NOI). Issuance of a CEQA Notice of Preparation (NOP) and NEPA Notice of Intent (NOI) is the first step in the EIR/EIS process. These documents provide a description of the proposed Project and potential alternatives, as well as a schedule of the CPUC and BLM's proposed scoping process that will include public scoping meetings and agency consultations. The NOP was published on May 7, 2014. The NOI was published on July 1, 2014.

Scoping Meetings. In order for the public and regulatory agencies to have an opportunity to ask questions on the scope of the EIR/EIS, the CPUC held 4 scoping meetings in the project area on May 19, 20, and 21, 2014, and the BLM held one scoping meeting on July 16, 2014. Information presented at the meetings, and meeting transcripts, are available here.

Public Scoping Report. The CPUC and BLM prepared Public Scoping Reports that documented the scoping activities and oral comments from the scoping meetings, as well as the written documents submitted in response to the NOP and NOI. These reports served as information sources to the CPUC and BLM in their determination of the range of issues and alternatives to be addressed in the Draft EIR/EIS.

Data Requests. During the preparation of the EIR and EIS, the CPUC and BLM identified information items needed for the EIR/EIS analysis and submitted data requests to SCE. In addition, after release of the Draft EIR/EIS, several data requests were submitted to the CPUC. Copies of each request and the responses are provided here.

Environmental Impact Report/Environmental Impact Statement (EIR/EIS)

Draft EIR/EIS. The Draft EIR/EIS was published August 7, 2015. The comment period closed on September 22, 2015. Comments submitted on the Draft EIR/EIS are available here.

Final EIR. The Final EIR for CEQA compliance was published by the CPUC on December 11, 2015. Comments that were submitted on the Draft EIR/EIS are presented in Volume 4 of the Final EIR, along with responses to all comments. (The BLM issued a separate Final EIS.)

Revised Phased Build Alternative Description. The CPUC prepared a revised Phased Build Alternative description from the Alternatives Screening Report in Appendix 5 of the West of Devers Upgrade Project Final EIR that was distributed on December 11, 2015. This revised alternative description was based on additional information provided in the Opening Testimony submitted in January 2016 in the project's General Proceeding A.13-10-020, and can be accessed here.

Addendum to Final EIR. On April 12, 2016, the CPUC released an Addendum to the West of Devers Upgrade Project Final EIR, which can be accessed here. The Addendum incorporates changes to Final EIR text and mitigation measures in response to additional information that was submitted by SCE in filings to the CPUC.

Final EIS. The Final EIS was published on August 12, 2016 and is available on the BLM project website, which can be accessed here.

COMMENTS & QUESTIONS?

Construction of the approved project is anticipated to occur in phases over a 4-year period. If you have comments, complaints, or questions regarding the project, please contact us using the CPUC's WOD project e-mail or voicemail, as follows:

Project e-mail: westofdevers@aspeneg.com
Project voicemail: (888) 456-0254

The CPUC's Project Manager is:
John Forsythe, CPUC Environmental Project Manager
California Public Utilities Commission
c/o Aspen Environmental Group
235 Montgomery Street, Suite 640
San Francisco, CA 94104-2920
JohnForsythe@cpuc.ca.gov
   

This page contains tables and is best viewed with Firefox or Internet Explorer. Please report any problems to the Energy Division web coordinator.

   
 
Project Home Page - CPUC Environmental Information - CPUC Home