Original Version
Rule 54.8-G
54.8-G. New Rule
Strikeout and Underline Version
Rule 54.8-G
54.8-G. Service / Clearance Poles (See Rule 22.0 – F For Definition)
(1) Service / Clearance Poles Shall Support Only:
a) 0 - 750 Volt conductors (See Rule 54.8–G2 )
b) Service drops
c) Associated risers and runs
d) Associated guys
e) Lighting and its associated equipment
f) Communication facilities
(2) Construction Requirements:
a) All supply service drop strength requirements may be applied to 0 - 750 volt conductors (secondary) installed under this Rule.
b) Span lengths shall not exceed 150 feet.
c) Supply conductors (secondary) installed between service / clearance poles shall meet the 0 - 750 volt conductor clearance requirements of Rule 37 , Table 1, Column D and Rule 38 , Table 2, Column D .
d) Multiple service drops, risers and street lights may be served from 0 - 750 volt conductor (secondary) installed under this Rule.
Final Version
Rule 54.8-G
54.8-G. Service / Clearance Poles (See Rule 22.0-F For Definition)
(1) Service / Clearance Poles Shall Support Only:
a) 0 - 750 Volt conductors (See Rule 54.8-G2 )
b) Service drops
c) Associated risers and runs
d) Associated guys
e) Lighting and its associated equipment
f) Communication facilities
(2) Construction Requirements:
a) All supply service drop strength requirements may be applied to 0 - 750 volt conductors (secondary) installed under this Rule.
b) Span lengths shall not exceed 150 feet.
c) Supply conductors (secondary) installed between service / clearance poles shall meet the 0 - 750 volt conductor clearance requirements of Rule 37 , Table 1, Column D and Rule 38 , Table 2, Column D .
d) Multiple service drops, risers and street lights may be served from 0 - 750 volt conductor (secondary) installed under this Rule.