Change List for this Rule

 

Original Version

Rule 54.8-G

 

54.8-G.    New Rule

 

Strikeout and Underline Version

Rule 54.8-G

54.8-G.    Service / Clearance Poles (See Rule 22.0 – F For Definition)

 

(1)    Service / Clearance Poles Shall Support Only:

 

a)    0 - 750 Volt conductors (See Rule 54.8–G2 )

 

b)    Service drops

 

c)    Associated risers and runs

 

d)    Associated guys

 

e)    Lighting and its associated equipment

 

f)    Communication facilities

 

(2)    Construction Requirements:

 

a)    All supply service drop strength requirements may be applied to 0 - 750 volt conductors (secondary) installed under this Rule.

 

b)    Span lengths shall not exceed 150 feet.

 

c)    Supply conductors (secondary) installed between service / clearance poles shall meet the 0 - 750 volt conductor clearance requirements of Rule 37 , Table 1, Column D and Rule 38 , Table 2, Column D .

 

d)    Multiple service drops, risers and street lights may be served from 0 - 750 volt conductor (secondary) installed under this Rule.

 

Final Version

Rule 54.8-G

 

54.8-G.    Service / Clearance Poles (See Rule 22.0-F For Definition)

 

(1)    Service / Clearance Poles Shall Support Only:

 

a)    0 - 750 Volt conductors (See Rule 54.8-G2 )

 

b)    Service drops

 

c)    Associated risers and runs

 

d)    Associated guys

 

e)    Lighting and its associated equipment

 

f)    Communication facilities

 

(2)    Construction Requirements:

 

a)    All supply service drop strength requirements may be applied to 0 - 750 volt conductors (secondary) installed under this Rule.

 

b)    Span lengths shall not exceed 150 feet.

 

c)    Supply conductors (secondary) installed between service / clearance poles shall meet the 0 - 750 volt conductor clearance requirements of Rule 37 , Table 1, Column D and Rule 38 , Table 2, Column D .

 

d)    Multiple service drops, risers and street lights may be served from 0 - 750 volt conductor (secondary) installed under this Rule.