Rule 54.10-E1
54.10-E1) Insulation: The phase conductors and their jumper connections, excluding jumper connections at the pole, shall be covered with insulation suitable for the voltage involved and shall conform with the requirements of Rule 20.8–G. Jumper connections at the pole shall comply with the clearance requirements of Table 2, Cases 17-D.
Strikeout and Underline Version
Rule 54.10-E1
54.10-E1)
Insulation: The phase conductors and their jumper connections, excluding jumper
connections at the pole, shall be covered with insulation suitable for the
voltage involved and shall conform with the requirements of Rule 20.8–G
20.9–G. Jumper connections at the pole shall
comply with the clearance requirements of Table 2, Cases 17-D.
Final Version
Rule 54.10-E1
54.10-E1) Insulation: The phase conductors and their jumper connections, excluding jumper connections at the pole, shall be covered with insulation suitable for the voltage involved and shall conform with the requirements of Rule 20.9–G. Jumper connections at the pole shall comply with the clearance requirements of Table 2, Cases 17-D.