STATE OF CALIFORNIA
PUBLIC UTILITIES COMMISSION

PUC > Energy > Transmission and Environmental Review > Current Projects

San Diego Gas & Electric

Master Special Use Permit and Permit to Construct Power Line Replacement Projects

(Application No. A.12-10-009)

NOTE: Linked files presented on this page are in PDF format. To view them, you will need to download the free Adobe Acrobat Reader if it is not already installed on your computer. For faster results in displaying the larger files, right-click the file's link, click "Save Target As" to download the file to your hard drive, then double-click the downloaded file.

 

 

Back to Power Line Replacement Projects Main Page


Welcome to the California Public Utilities Commission (CPUC) Mitigation Monitoring, Compliance and Reporting Program website for the San Diego Gas & Electric (SDG&E) Master Special Use Permit (MSUP) and Permit to Construct (PTC) Power Line Replacement Projects located in and around the Cleveland National Forest (CNF) in San Diego County, California.

Pursuant to the CPUC approval of the Project, SDG&E is required to implement the Applicant Proposed Measures (APMs) and mitigation measures identified in the Final Environmental Impact Report (EIR)/Environmental Impact Statement (EIS) and the Mitigation Monitoring, Reporting, and Compliance Program (MMRCP). The CPUC, as a lead agency under CEQA, is responsible for ensuring that the APMs and mitigation measures, as well as plans reviewed and approved by other agencies, are implemented throughout the construction phase of the Project. Below are project documents related to mitigation monitoring that are available for public review.

Quick Links


Mitigation Monitoring, Compliance and Reporting Program

Notice to Proceed

Environmental Monitoring Reports

Minor Project Refinements Request

 

Mitigation Monitoring, Compliance and Reporting Program


The program�s goal is to ensure compliance with CPUC�s adopted mitigation. The CPUC, in conjunction with SDG&E, drafted a Mitigation Monitoring Compliance and Reporting Program (MMCRP) to ensure compliance with mitigation measures approved in the Final EIR/EIS. Click on link below to view a complete copy of the MMCRP.

MMCRP

 

Notice to Proceed (NTP)


A NTP is issued contingent upon SDG&E�s compliance with pre-construction requirements as specified by the approved mitigation measures and responsible agency permitting requirements. A link to the approved pre-construction documentation is provided below.

Pre-Construction Documentation

Notice to Proceed

Description

NTP Request

NTP Approval

001

Construction activities associated with TL625B and TL625E and staging yards

SDG&E Request
07/25/16

SDG&E Request Resubmitted (09/1/16)

NTP-1
Attachment A
09/21/16

NTP-1 Clarification
10/31/16

002

Construction activities associated with TL6931

SDG&E Request 12/12/16

NTP-2
Attachment A

003

Geotechnical Work for TL 682

SDG&E Request 2/6/17

NTP-3
Attachment A

004

Construction activities associated with TL682, Phase I (Pole 118102 to Warners Substation)

SDG&E Request 4/4/15, as revised 5/10/17

NTP-4
Attachment A

005

Geotechnical Work for C440 and C449

SDG&E Request

NTP-5
Attachment A

006

Construction Activities associated with TL682 Phase II: Rincon Substation to Pole Z118064

SDG&E Request

NTP-6
Attachment A

007

Construction Activities Associated with Circuit C78

SDG&E Request

NTP-7
Attachment A

008

Construction Activities Associated with C442

SDG&E Request

NTP-8
Attachment A

009

Geotechnical borings and seismic surveys along TL629A and TL625D

SDG&E Request

NTP-9
Attachment A

010

Construction activities associated with Phase 1 of C440

SDG&E Request

NTP-10
Attachment A

011

Geotechnical investigations on TL629C

SDG&E Request

NTP-11
Attachment A

012

Reconstruct the TL6957 (formerly 625D)

SDG&E Request

NTP-12
Attachment A

013

Reconstruct Phase III of the TL682 Component

SDG&E Request

NTP-13
Attachment A

014

Reconstuct/Reclocate C157

SDG&E Request

NTP-14
Attachment A

015

Reconstruct/Remove C449

SDG&E Request

NTP-15
Attachment A

016

Geotechnical investigations on TL6923 and TL 625C

SDG&E Request

NTP-16
Attachment A

017

Reconstruct TL629C (Glencliff Substation to Cameron Tap)

SDG&E Request

NTP-17
Attachment A

018

Geotechnical investigations on C 79A

SDG&E Request

NTP-18
Attachment A

019

Reconstruct TL 6958

SDG&E Request

NTP-19
Attachment A

020

Reconstruct TL 629A (Descanso to Glencliff Substation)

SDG&E Request

NTP-20
Attachment A

021

Reconstruct C79A

SDG&E Request

NTP-21
Attachment A

022

Reconstruct TL 625C

SDG&E Request

NTP-22
Attachment A

023

Reconstruct C 440 Phase I Overhead

SDG&E Request

NTP-23
Attachment A

024

Reconstruct TL 6923

SDG&E Request

NTP-24
Attachment A

025

Remove TL 626 from Service and to Convert the Northern Section of TL626 from 69kV to 12 kV

SDG&E Request

NTP-25
Attachment A

026

Convert the Southern Section of TL 626 from 69 kV to 12 kV

SDG&E Request

NTP-26
Attachment A

027

Reconstruct C 440 Phase II

SDG&E Request

NTP-27
Attachment A

Data Requests
CPUC Data Request 1 (08/15/16) SDG&E Data Response 1 (08/24/16)
CPUC Data Request 2 (10/25/16) SDG&E Data Response 2 (11/02/16)
CPUC Data Request 3 (2/8/17) SDG&E Data Response 3 (3/18/17)
CPUC Data Request 4 (3/3/17) SDG&E Data Response 4 (3/16/17)
CPUC Data Request 5 (4/3/17) SDG&E Data Response 5 (4/6/17)

 

Environmental Monitoring Reports


A CPUC Environmental Monitor (EM) is monitoring construction activities to ensure that they are conducted in accordance with the approved mitigation measures and permit conditions. Reports documenting construction status and compliance activities will be provided when available.

Weekly Report #

Reporting Period

Environmental Issues/Concerns

001

September 23-October 2, 2016

No issues/concerns reported.

002

October 3-October 16, 2016

Approved parking areas.

003 October 17-October 30, 2016 No issues/concerns reported.
004 October 31-November 13, 2016 No issues/concerns reported.
005 November 14-November 27, 2016 No issues/concerns reported.
006 November 28-December 11, 2016 Work limits.
007 December 12-December 25, 2016 No issues/concerns reported.
008 December 26, 2016 - January 8, 2017 No issues/concerns reported.
009 January 9 - January 22, 2017 Dewatering system.
010 January 23 - February 5, 2017 Waste disposal, Fire equipment.
011 February 6 - February 19, 2017 Work limits.
012 February 20 - March 5, 2017 Work limits.
013 March 6 - March 19, 2017 No issues/concerns reported
014 March 20 - April 2, 2017 No issues/concerns reported
015 April 3 - April 16, 2017 No issues/concerns reported
016 April 17 - April 30, 2017 No issues/concerns reported
017 May 1-May 14, 2017 Work Limits
018 May 15-May 28, 2017 No issues/concerns reported
019 May 29-June 11, 2017 No issues/concerns reported
020 June 12-June 25, 2017 No issues/concerns reported
021 June 26-July 9, 2017 Work Limits
022 July 10-July 23, 2017 No issues/concerns reported
023 July 24-August 6, 2017 No issues/concerns reported
024 August 7-August 20, 2017 Nest Buffer Encroachment
025 August 21-September 3, 2017 No issues/concerns reported
026 September 4-September 17 Work Limits
027 September 18-October 2, 2017 No issues/concerns reported
028 October 2-October 15, 2017 Work Limits
029 October 16-October 29, 2017 No issues/concerns reported
030 October 30-November 12, 2017 Work Limits
031 November 13-November 26, 2017 Work Limits
032 November 27-December 10, 2017 No issues/concerns reported
033 December 11-December 24, 2017 Work Limits
034 December 25, 2017 � January 7, 2018 Work Limits
035 January 8 � January 21, 2018 Work Limits
036 January 22 � February 4, 2018 No issues/concerns reported
037 February 5 � February 18, 2018 Work limits
038 February 19 � March 4, 2018 No issues/concerns reported
039 March 5 � March 18, 2018 No issues/concerns reported
040 March 19 � April 1, 2018 No issues/concerns reported
041 April 2 � April 15, 2018 No issues/concerns reported
042 April 16 � April 30, 2018 Fire Equipment
043 April 30 � May 13, 2018 No issues/concerns reported
044 May 14 � May 27, 2018 No issues/concerns reported
045 May 28 � June 10, 2018 No issues/concerns reported
046 June 11 � June 24, 2018 No issues/concerns reported
047 June 25 � July 8, 2018 No issues/concerns reported
048 July 9-July 22, 2018 Cultural resources monitoring
049 July 23-August 5, 2018 Work Limits, Cultural resources monitoring
050 August 6-August 19, 2018 Fire Equipment
051 August 20-September 2, 2018 Work Limits, Fire Equipment
052 September 3-September 16, 2018 Work Limits
053 September 17-September 30, 2018 Trash Management
054 October 1-October 14, 2018 Biological Monitoring
055 October 15-October 28, 2018 Work Hours
056 October 29-November 11, 2018 Work Hours
057 November 12-November 25, 2018 No issues/concerns reported
058 November 26-December 9, 2018 Work Limits
059 December 10-December 23, 2018 Work Limits
060 December 23-January 13, 2019 Work Hours
061 January 14-January 27, 2019 Work Limits
062 January 28-Feburary 10, 2019 Work Limits
063 February 11-February 24, 2019 Work Limits
064 February 25-March 10, 2019 Work Limits
065 March 11-March 24, 2019 Work Limits, Work Hours
066 March 25-April 7, 2019 No issues/concerns reported
067 April 8-April 21, 2019 Work Hours
068 April 22-May 5, 2019 Work Hours
069 May 6-May 19, 2019 No issues/concerns reported
070 May 20-June 2, 2018 No issues/concerns reported
071 June 3-June 16, 2019 Covering work areas
072 June 17, 2019-June 30, 2019 No issues/concerns reported
073 July 1-July 14, 2019 Cultural Monitoring
074 July 15-July 28, 2019 No issues/concerns reported
075 July 29-August 11, 2019 Work Limits, Work Hours, Work Activity on USFS during PAL EV
076 August 12-August 25, 2019 No issues/concerns reported
077 August 26-September 8, 2019 No issues/concerns reported
078 September 9-September 22, 2019 Work limits, Work Hours, Authorization from USFS for work during PAL EV, SWPPP
079 September 23-October 6, 2019 Work hours
080 October 7-October 20, 2019 Work Limits
081 October 21-November 3, 2019 No issues/concerns reported
082 November 4-November 17, 2019 Work Limits, Excavation Covering, Work Hours
083 November 18-December 1, 2019 SWPPP, Work Limits
084 December 2-December 15, 2019 Excavation Covering, Work Limits, Fire Tools, Work Hours, SWPPP
085 December 16-December 29, 2019 Work Limits, SWPPP
086 December 30, 2019-January 12, 2020 SWPPP, Work Limits, Fire Tools
087 January 13-January 26, 2020 Work Limits, Cultural Monitoring
088 January 27-February 9, 2020 Work Limits, Excavation Covering
089 February 10-February 23, 2020 Work Limits, Work Hours
090 February 24-March 8, 2020 Work Hours, Work Limits, Trash Management
091 March 9-March 22, 2020 Work Hours, Work Limits
092 March 23-April 5, 2020 Work Limits
093 April 6-April 19, 2020 SWPPP
094 April 20-May 3, 2020 Work Limits, SWPPP
095 May 4-May 17, 2020 No issues/concerns reported
096 May 18-May 31, 2020 Work Limits, Excavation Coverings
097 June 1-June 14, 2020 Work hours, Work Limits, Excavation Coverings, Biological Monitoring
098 June 15-June 28, 2020 Work Limits, Cultural and Biological Monitoring, APP/NBMP, Fire Tools, Spill Clean-up
099 June 29-July 12, 2020 Work Limits, SWPPP, CFPPP
100 July 13-July 26, 2020 Work Hours, WEAP Training, Dust Control, Work Limits
101 July 27-August 9, 2020 Dust Control
102 August 10-August 23, 2020 No issues/concerns reported
103 August 24-September 6, 2020 Cultural Resources
104 September 7-September 20, 2020 Work Limits, CFPPP
105 September 21-October 4, 2020 Work Limits, CFPPP
106 October 5-October 18, 2020 CFPPP
107 October 19-November 1, 2020 No issues/concerns reported
108 November 2-November 15, 2020 Work Limits, Biological Monitoring, Trash Management
109 November 16-November 29, 2020 Work Limits
110 November 30-December 13, 2020 No issues/concerns reported
111 December 14-December 27, 2020 No issues/concerns reported
112 December 28-January 10, 2021 CFPPP
113 January 11-January 24, 2021 Work Limits
114 January 25- February 28, 2021 Work Limits

 

Minor Project Refinement Requests


The Commission decision approving the permit to construct authorizes Energy Division staff to approve requests by SDG&E for minor project refinements. The decision states that the Energy Division may approve requests by San Diego Gas & Electric Company for minor project refinements that may be necessary due to final engineering of the Power Line Replacement Projects so long as such minor project refinements are located within the geographic boundary of the study area of the Environmental Impact Report and do not, without mitigation, result in a new significant impact or a substantial increase in the severity of a previously identified significant impact based on the criteria used in the environmental document; conflict with any mitigation measure or applicable law or policy; or trigger an additional permit requirement. San Diego Gas & Electric Company shall seek any other project refinements by a petition to modify this decision.

SDG&E's Minor Project Refinement Requests will be made available below when submitted to the CPUC.

Minor Project Refinement #

Description

MPR Request

MPR Approval

001

Modifications to Merrigan, Japatul Spur and Anderson Staging Yards

10/5/16, as revised 10/18/16

10/21/16

002

Modifications to TL625B and TL629E

12/21/16

2/10/17

003

Addition of Water Source for Construction�Wilson Pond Facility

01/18/17

04/04/17

004

Use of two new staging and fly yards-TL 682

03/20/17

05/16/17

005

Modifications to Circuit (C) 78

05/09/17

08/15/17

006

Drainage Structure Installation at Pole Z272867 (TL 625B)

06/20/17

07/06/17

007

Use of Love Valley Staging and Fly Yard

08/01/17

09/25/17

008

Use of Mendenhall Fly Yard

08/14/17

09/01/17

009

Refinements for Phase I and Phase II of TL682

10/10/17

11/21/17

010

Request to shift one pole and add an additional workspace

10/16/17

10/27/17

011

Modifications to TL6957 (formerly TL625D)

1/9/18

3/12/18

012

Addition of the Creekside Ranch Staging and Fly Yard

1/22/18

2/6/18

013

Request to shift one pole and add an additional workspace

2/7/18

2/9/18

014

Request to begin construction on Phase III of TL682. This request is combined with NTP #13

2/15/18

4/5/18

015

Refinements for TL682

2/22/18

3/14/18

016

Refinements for TL629E

3/29/18

4/3/18

017

Refinements for C157 and addition of Frye Staging and Fly Yard

04/12/18

6/26/18

018

Refinements for C449

5/29/18

8/30/18

019

Refinements for TL629C and addition of Buckman Springs Fly Yard

7/2/18

8/30/18

020

Refinements for C157

7/31/18

8/29/18

021

Interset Pole on TL 682

8/23/18

9/24/18

022

Refinements for TL 6958

10/16/18

11/30/18

023

Expansion of Buckman Springs Fly Yard and request for use of Old Buckman Springs and Rodriguez Staging Yards

11/15/18

12/4/18

024

New Construction Only Access Road for C 449 and TL 629C

11/26/18

12/20/18

025

Bartlett Staging Yard

12/11/18

1/22/19

026

Refinements for TL 629A

2/22/19

4/19/19

027

Expansion of Cameron Staging Yard

03/01/19, as revised 03/08/19

03/12/19

028

Underground workspaces at three existing pole locations on C 449

03/07/19

03/12/19

029

Refinements for C79A

03/28/19

05/29/19

030

Modification of navigation access road to Pole P45476

03/29/19

04/05/19

031

Refinements to TL 625C

4/26/19

6/18/19

032

Refinements to C440 Phase I Overhead

5/6/19

7/11/19

033

C 440 Conversion of Staging Yard 2 and 2A to Staging and Fly Yards

5/14/19, as revised 6/3/19

6/4/19

034

River Drive Staging Yard

05/17/19

05/29/19

035

TL 629A Refinements

6/6/19

6/18/19

036

C 79 Paso Picacho Staging Yard

6/28/19

7/17/19

037

TL 629A Merrigan Yard Expansion

6/28/19

7/3/19

038

TL 629A Refinements

7/26/19

8/14/19

039

TL 625C Refinements

9/05/19

9/19/19

040

Addition of underground alignment for C 440

9/12/19

10/10/19

041

TL 6923 Refinements

10/2/19, revised 10/30/19

11/22/19

042

Addition of temporary access/entry/turnaround areas, temporary pole work areas, and footpaths at Poles Z774861, Z774862, Z774863, and Z774864 for TL 269A

10/29/19, revised 11/08/19

12/9/19

043

Shift replacement pole Z272393 and add temporary pole work area

12/27/19

1/9/19

044

Refinements to TL 626 Conversion South

2/10/20

4/23/20

045

Temporary shoo-fly along TL629A

2/21/20

3/9/20

046

Additional anchors and access road modifications along C 440 Phase I

3/6/20

3/26/20

047

Shift Pole P259353, P259354, P259355, addition of anchors and temporary work areas, and addition of construction-only access road between Boulder Creek Road and the Boulder Creek Fly Yard.

4/9/20

4/22/20

048

Shift Pole P259378 and add a temporary work area along TL 626 Conversion North

8/25/20

10/21/20

049

Remove 43 trees along C 440

9/2/20

10/9/20

050

Shift anchor west of Pole P874922, Pole P258468 and new anchor, and Service Drop 3; Add temporary pole work area, anchor work area, a temporary access/ entry/turnaround, and approximately 310 feet of construction-only access road for Pole P258468 and anchor work area for Pole P874922.

10/21/20

11/2/20

Minor Project Refinement Memo for NTP-27 and Data Response


For Additional Information


To request additional information, please contact us by email, phone, or fax, as follows:

Project email: CNF_MSUP@dudek.com
Project voicemail: (866) 467-4727

The CPUC's project manager is:


Lisa Orsaba, CPUC Project Manager
California Public Utilities Commission
505 Van Ness Avenue
San Francisco CA 94102
Tel. (415) 703-1966
Fax (415) 703-2200

The Forest Service Project Manager is:


Joe Raffaele
United States Forest Service
Cleveland National Forest
10845 Rancho Bernardo Road, Ste. 200
San Diego, CA 92127
Tel: 858-674-2912
Fax: (858) 524-0130

 

Please report any problems to the Energy Division web coordinator.