|
Welcome to the California Public Utilities Commission (CPUC) website for the environmental review of the proposed construction of the PacifiCorp Lassen Substation Project (proposed project) located in the City of Shasta, California. PacifiCorp submitted an application for this project to the CPUC on November 2, 2015 (Application A.15-11-005) accompanied by the Proponents Environmental Assessment (PEA). On July 16, 2016, PacifiCorp submitted an
amendment to the application accompanied by an
amended PEA
for the updated elements of the proposed project. The amended
application revised the proposed overhead distribution line crossing
Interstate 5 (I-5) to an underground distribution line in the same
location. The proposed project is subject to review under the
California Environmental Quality Act (CEQA). CPUC issued its Decision on May 6, 2019 (Decision D.19-04-011). This site provides
access to public documents and information relevant to the CEQA
review process.
Quick Links
Background
Project Description
Application and Proponent’s Environmental Assessment (PEA)
Application Review, Date Requests, and Responses
Environmental Review
Commission Decision (May 6, 2019)
For Additional Information
New
Mitigation Monitoring and Compliance Reporting Program
PacifiCorp filed an application for a Permit to
Construct the Lassen Substation Project with CPUC to construct,
operate and maintain the Lassen Substation Project. PacifiCorp is
proposing to replace and upgrade the existing Mount (Mt.) Shasta
substation serving the City of Mt. Shasta. The applicant objectives
of the proposed project are:
- To ensure the reliability of the system by replacing the existing wooden substation with a new steel pole constructed substation on a new site.
- To ensure that the system has adequate capacity to safely and reliably meet local and contractual system demand.
- To ensure that the new system is designed to accommodate operating within a115kV transmission system.
- To be operational to meet projected summer 2018 peak load demands.
The following are key components of the proposed project:
- Construction of Lassen Substation, which would be built on parcels adjacent to the existing Mt. Shasta Substation, located at 504 South Old Stage Road, Siskiyou County, California.
- Replacement of 36 transmission poles along a 1.5-mile segment of the existing 69kV power transmission system with wood-framed poles to comply with current California regulations. The 69kV system would initially operate at 69kV, but would be built to allow future operation at 115kV.
- Installation of three additional wood poles to connect existing transmission to the proposed substation and connect lines from the existing substation to the new substation.
- Connection of the new Lassen Substation to the existing distribution system by installing three 300-foot underground conduits from a cable pulling vault just outside the proposed substation.
- Reconductor two existing distribution lines, which would include the partial reconductoring of the existing 4.16kV distribution system to 12.5kV, and the undergrounding of approximately 1,200 feet of the existing overhead distribution line.
- Addition of three banks of 12.5kV to 4.16kV stepdown transformers to be added on the 12.5kV distribution feeders near the existing 4.16kV load.
- Removal and restoration of the existing Mt. Shasta Substation.
Project construction is expected to require approximately 12 months to complete.
The proposed project would be located in the City of Mt. Shasta, California, in the south central portion of unincorporated Siskiyou County (see the Regional Location Map). The existing Mt. Shasta Substation and proposed Lassen Substation sites are both located west of Interstate 5 (I-5) and the pole replacement and reconductoring activities would occur both east and west of the I-5.
The amendment to application and amended PEA, supersede the
original application and PEA for the updated elements of the
proposed project. The amended application revised the proposed
overhead distribution line crossing Interstate 5 (I-5) to an
underground distribution line in the same location. Click on the
following links to copies of these documents.
Amendment to Application - July 16, 2016
Amended
Proponents Environmental Assessment (PEA) - July 2016
Application for the Lassen Substation Project - November 2015
Proponents Environmental Assessment (PEA) - October 2015
PEA Appendices
Appendix A - Visual Simulations
Appendix B - Biological Technical Report
Appendix D - Army Corp of Engineers 404 Jurisdictional Delineation
Appendix E - Geotechnical Report
Appendix F - Phase I Environmental Site Assessment Reports
Note: Appendix C is the cultural resources technical report and covers culturally sensitive resources. It is provided in confidentiality to the CPUC to protect the locations of potentially sensitive resources.
The CPUC conducted a completeness review of the PEA and amended
PEA to identify additional data needs from the applicant to complete
the environmental review. Based on this review, PacifiCorp’s
application was deemed complete by CPUC on July 28, 2016. CPUC’s
completeness letter, data requests, and PacifiCorp responses are
listed in the table below. Note that some of the files linked below
have bookmarks that can be seen when clicking on the bookmark icon.
CPUC Review and Data Request
|
PacifiCorp’s Response
|
Data Request Response Attachments
|
CPUC Deficiency letter and Data Request 1.0
(Submitted December 2, 2015)
|
CA A.15-11-005 – Response to CPUC Data Request 1.0
(dated January 19, 2016, February 8, 2016, and
February 22, 2016)
|
January 19, 2016
PEA_Admin_a-1-7_Contacts_Correspondence
PEA_1.7.a-1-4_PublicOutreach
PEA_3.1.a_OverviewMap
PEA_3.1.b.1-4_Figures
PEA_3.4.1.e_LassenSubPlans
PEA_3.4.1.f.1-3_GP
PEA_3.4.1.h
PEA_3.4.3.a-1-3
PEA_3.4.3.b-1-2
PEA_3.4.3.e_EL551
PEA_3.5.a
PEA_3.6.d
PEA_5.0_Fig_5-1_Cumulative_Projects
February 8,
2016
PEA_4.4-1_AnnualConstruction
PEA_4.4-2_AQ_GHG_Emissions
PEA_4.5-1_BioResources
PEA_4.5-2_RevisedBioHabAssessment
PEA_4.7-1_Table
PEA_4.12_Revised_Noise
February 22, 2016
PEA_4.1.b_VP10
|
CPUC Data Request 2.0
(Submitted January 19, 2016)
|
CA A.15-11-005 – Response to CPUC Data Request 2.0
(dated February 22, 2016)
|
February 22, 2016
PEA_3.0.a_I-5_CrossingIllustration
PEA_3.0.b_JessieStAeriaView_4.18.05
PEA_3.0.c_General Plan
PEA 4.1.a_VP3
PEA_4.1.b_VP2_VP6
PEA_4.1.c.1-5_Caltrans
|
CPUC Completeness letter and Data Request 3.0
(Submitted July 28, 2016)
|
CA
A.15-11-005 – Response to CPUC Data Request 3.0
(dated August 9, 2016)
|
August 9, 2016
PEA
4.1_VP3_DR3
|
Final Initial Study/Mitigated
Negative Declaration (IS/MND)
On June 19, 2017, the CPUC prepared a Final Mitigated Negative Declaration (Final MND) under CEQA for consideration of the PacifiCorp Lassen Substation Project (see links below). The information in the Final MND describes the proposed project and potential environmental impacts, identifies those impacts that could be significant, and presents mitigation measures to avoid or minimize potentially significant impacts.
The Final
IS/MND incorporates all comments received during the public review
period for the Draft IS/MND, as well as revisions discussed and
agreed upon during various discussions with the applicants and the
CPUC. The responses to comments are provided in Section 7 of the
Final IS/MND. Revisions to the Draft IS/MND are shown in
strikeout/underline
in the Final IS/MND. No substantial changes to the environmental
document analyses or conclusions resulted from evaluation of the
comments received during the public review period. No substantial
revisions that would merit recirculation as defined by 15073.5(b) of
Title 14 of CEQA were made to the project or analyses after public
comment. Click on the following links for copies of these documents.
Response to Mount Shasta Tomorrow Comments on Final IS/MND
On September 22, 2017 Mount Shasta Tomorrow filed comments on the Final IS/MND.
Appendix A contains the CPUC response to the comments. The comments highlighted minor errors in the Final IS/MND.
Corrections to the Final IS/MND have been made and are listed in the Errata linked below. The comments raise no new important issues or
potentially significant effects to the environment. These changes to the Final IS/MND do not qualify as substantial revisions as defined in
Section 15073.5(b) of the California Environmental Quality Act Guidelines, and therefore do not require recirculation. Click on the following links for copies of these documents.
Draft Initial
Study/Mitigated Negative Declaration (IS/MND) Publication
On November
23, 2016, the CPUC released a Notice of Intent (NOI) to Adopt a MND
for the Lassen Substation Project, showing that the proposed
project, as mitigated, would not have any significant effects on the
environment. The NOI and Draft IS/MND are available by clicking on
the following links:
The Commission voted on April; 25, 2019 to grant PacifiCorp a permit to construct the Lassen Substation Project (the Decision was issued on May 6, 2019). A Notice of Determination was filed with the State Clearinghouse on April 26, 2019.
The CPUC, through its Environmental Review Team, is conducting an environmental review of the project. To request additional information or to be added to the mailing list, please contact us by email, fax, or phone, as follows:
Project email: LassenSubstation@dudek.com
Project voicemail: (844) 379-3477
Project fax: (844) 386-5633
The CPUC’s Project Manager is:
Michael Rosauer, CPUC Project Manager
California Public Utilities Commission
505 Van Ness Avenue
San Francisco, CA 94102
Tel.: (415) 703-2579
Please report any problems to the Energy Division web coordinator.
|
|